Dighello v. Busconi

673 F. Supp. 85, 1987 U.S. Dist. LEXIS 10718
CourtDistrict Court, D. Connecticut
DecidedNovember 10, 1987
DocketCiv. A. B-87-167(RCZ), N-81-461(RCZ)
StatusPublished
Cited by26 cases

This text of 673 F. Supp. 85 (Dighello v. Busconi) is published on Counsel Stack Legal Research, covering District Court, D. Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dighello v. Busconi, 673 F. Supp. 85, 1987 U.S. Dist. LEXIS 10718 (D. Conn. 1987).

Opinion

RULING ON PENDING MOTIONS

ZAMPANO, Senior District Judge.

This is another in a seven-year series of lengthy, acrimonious legal proceedings involving former business associates, Ronald DiGhello and Lewis Busconi. Their disputes revolve around the development and construction of a $66 million project on 166 acres of valuable land owned by the parties in Milford, Connecticut. Due to the discord and dissension between the two men, little if any progress has been made to improve or utilize the partially-built facilities on the property.

The parties’ disagreements have spawned several lawsuits — both state and federal — which, in turn, have generated a myriad of motions, counter-motions, petitions, briefs, reply briefs, affidavits, counter-affidavits and other prolific moving papers. Despite valiant efforts by counsel, and lengthy discussions with state judges and this Court, the parties have tenaciously refused to resolve their controversies amicably. Their inane determination “to fight to the finish” is indeed unfortunate. Had the parties compromised their differences in a rational, businesslike way, as recommended by their counsel and the courts, the parcels in question long ago would have been successfully and profitably developed for condominiums, a golf course, and a marina.

In 1982 Magistrate Smith, noting that there were so many disputes between the parties "that merely to identify them would be a triumph in itself,” held that the parties should arbitrate all their disagreements pursuant to their written contract entered into on April 29, 1981. Ruling On Petition To Enforce Arbitration and Cross-Motion To Dismiss, Civ. No. N-81-461 (D.Conn. Mar. 10, 1982). On October 5, 1982, this Court sustained the Magistrate's reasoned and thorough decision and ordered the parties to submit themselves to arbitration. Ruling On Objection To Magistrate’s Ruling, Civ. No. N-81-461 (D.Conn. October 5, 1982).

After an abandoned appeal to the Second Circuit, and another round of legal maneuvers, arbitration finally was commenced before a panel of three arbiters in May 1984 and was concluded in January 1987. The Arbitration Panel filed its Award on February 11, 1987. Consistent with the pattern of prior conduct, the parties have now directed motions to this Court with the customary salvo of “paper.”

Pending before the Court are Dighello’s motion to vacate the Award, and Busconi’s motions to confirm the Award and for further orders.

DISCUSSION

A. THE AWARD

The Arbitration Panel conducted forty days of hearings to resolve the disputes between the parties. The hearings were comprehensive and complete: the parties, represented by counsel, and their witnesses were fully heard, over thirty-eight volumes of .transcripts were recorded, more than 300 exhibits were introduced, and extensive briefs and moving papers were submitted.

In a detailed, reasoned twenty-two page Award, the Arbitration Panel unanimously concluded, inter alia, that: (1) throughout DiGhello’s business dealings with Busconi for the development and construction of the multi-million dollar project, DiGhello acted individually and through a network of corporate entities, which he owned and controlled, known as By-The-Sea, Inc., *87 Luxury Properties, Inc., Brandy Incorporated-Milford, Millionaire, Inc., and Millstone Country Club, Inc.; (2) DiGhello substantially breached existing contracts and agreements by, among other things, failing to execute documents necessary for the construction of housing units, interfering with the delivery of building supplies, and designing a plan whereby Busconi would pay third parties for work never performed; (3) DiGhello’s conduct was a chronicle of “obstruction, interference, and duplicity”; (4) Busconi was entitled to both monetary and equitable relief; (5) despite Busconi’s claims of over thirty million dollars in lost profits and over seven million dollars in out-of-pocket expenses, many of his damages were not proved or not recoverable as a matter of law; (6) Busconi’s allowable money damages were $5,648,-677.20 plus “supplemental interest”; (6) nonmonetary relief to Busconi to enable him to complete the project as originally proposed would not be feasible because of several factors including zoning obstacles, the illegality under state law of the existing plan to sell certain buildings, and other unworkable aspects of the plan for development; (7) due to the property’s complex and entangled state of affairs, the most sensible and suitable nonmonetary relief would be to grant Busconi partial specific performance "to effectuate as much of the original plan as may still be possible”; and (8) under the circumstances, DiGhello would be required to execute and deliver to Busconi certain corrective deeds, easements, declarations, assignments and other documents.

B. DIGHELLO’S MOTION TO VACATE

DiGhello moves, pursuant to 9 U.S.C. § 10(d), to set aside the Award on three grounds: (1) the Arbitration Panel decided issues not submitted to it for resolution; (2) the orders of relief in the Award bind four of DiGhello’s corporate entities that were not named as parties to the arbitration; and (3) the Award is incomplete, ambiguous, and contradictory.

1. Scope of Issues

Section 10(d) provides in relevant part that an award may be vacated “where the arbitrators exceeded their powers.” Thus if an arbitration panel rules on issues not presented to it by the parties, it has exceeded its authority and the award must be vacated. United Steelworkers of America v. Warrior & Gulf Navigation Co., 363 U.S. 574, 582-83, 80 S.Ct. 1347, 1353, 4 L.Ed.2d 1409 (1960); Lackawanna Leather Co. v. United Food & Commercial Workers Int’l Union, 692 F.2d 586, 538-39 (8 Cir.1982); Piggly Wiggly Operators’ Warehouse, Inc. v. Piggly Wiggly Operators’ Union, 611 F.2d 680, 683 (5 Cir.1980). However, Congress has indicated a strong preference for enforcing arbitration agreements, see 9 U.S.C. § 2; Moses H. Cone Memorial Hospital v. Mercury Construction Corp., 460 U.S. 1, 22, 103 S.Ct. 927, 940, 74 L.Ed.2d 765 (1983), and it is well settled that a reviewing court’s power to vacate an award is severely limited so that an award may be set aside only under the very narrow circumstances enumerated in § 10, or if it is “irrational” or “manifestly disregards the law.” See I/S Stavborg v. Nat’l Metal Converters, Inc., 500 F.2d 424, 430-31 (2 Cir.1974); see also Andros Compania Maritima v. Marc Rich & Co., A.G., 579 F.2d 691, 703-04 (2 Cir.1978).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Key Inv. Servs. LLC v. Oliver
Second Circuit, 2025
Gabriel Lagrange v. Harley E. Boone
Louisiana Court of Appeal, 2024
Gulf LNG Energy v. ENI USA Gas Marketing
Supreme Court of Delaware, 2020
Benistar Employer Services Trust Co. v. Benincasa
207 A.3d 67 (Connecticut Appellate Court, 2019)
Lefkovitz v. Wagner
291 F. Supp. 2d 764 (N.D. Illinois, 2003)
Rosati v. Bekhor
167 F. Supp. 2d 1340 (M.D. Florida, 2001)
Rocket Jewelry Box, Inc. v. Noble Gift Packaging, Inc.
986 F. Supp. 231 (S.D. New York, 1997)
Bull HN Information Systems Inc. v. Hutson
983 F. Supp. 284 (D. Massachusetts, 1997)
Cray v. NationsBank of North Carolina, N.A.
982 F. Supp. 850 (M.D. Florida, 1997)
Chicago Pneumatic Tool Co. v. Smith
890 F. Supp. 100 (N.D. New York, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
673 F. Supp. 85, 1987 U.S. Dist. LEXIS 10718, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dighello-v-busconi-ctd-1987.