RESCH v. CATLIN INDEMNITY COMPANY

CourtDistrict Court, D. New Jersey
DecidedMarch 23, 2020
Docket2:19-cv-08699
StatusUnknown

This text of RESCH v. CATLIN INDEMNITY COMPANY (RESCH v. CATLIN INDEMNITY COMPANY) is published on Counsel Stack Legal Research, covering District Court, D. New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
RESCH v. CATLIN INDEMNITY COMPANY, (D.N.J. 2020).

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF NEW JERSEY

TODD RESCH, Civil No.: 19-8699 (KSH) (CLW) Petitioner,

v. CATLIN INDEMNITY COMPANY, OPIN ION

Respondent.

Katharine S. Hayden, U.S.D.J. I. Introduction This matter comes before the Court on the petition of Todd Resch to vacate an arbitration award issued in the context of a dispute between him and his insurer, Catlin Indemnity Company, over his fire-damaged boat. The Court denies the petition. II. Background The factual background is straightforward and undisputed. Resch owns a pleasure boat that was damaged in 2015 while it was docked in a marina located in Stony Point, New York after a nearby boat caught fire. Resch made a claim for the damage under an insurance policy (the “Policy”) that he held with Catlin. The surveyor Resch hired determined that the boat was a total loss. Catlin’s surveyor disagreed. Unable to resolve the dispute, Resch invoked the following provision in the Policy: If we fail to reach an agreement with you regarding cause of loss, extent of related damages or reasonable repairs related to any property loss, either you or we may make written demand for appraisal. Within thirty (30) days after receipt of an appraisal demand, we and you will each select a competent, impartial appraiser with no prior involvement with the yacht or occurrence. The two (2) appraisers will review the loss and come to an agreement in regard to the facts in dispute. If the two (2) appraisers cannot reach an agreement, they will select an additional, mutually-acceptable, impartial umpire, with no prior involvement with the yacht or occurrence who will make a binding and enforceable determination. The agreement of the appraisers, or decision of the umpire, will be binding and enforceable against either you or us in a court of competent jurisdiction. We and you will each pay the cost of our own selected appraiser and will share any umpire’s fees equally.

(D.E. 2, Petition, Ex. A, Policy § 4.18 (emphasis added).) The surveyors1 selected by the parties could not reach agreement, and ultimately Robert Schofield, a naval architect and engineer, was appointed as impartial umpire.2 The parties sent him a joint letter on September 28, 2018, outlining the dispute, stipulating to certain facts, and addressing procedural matters, including the logistics of submissions from the parties’ surveyors and payment of expenses. (Petition, Ex. C, Joint Retention Letter.) The letter also contemplated Schofield’s inspection of the boat. (Id.) In characterizing the issue, the letter stipulated that “[a] dispute ha[d] arisen between Mr. Resch and Catlin regarding the extent of related damages or reasonable repairs resulting from such exposure” to the fire from the other boat. (Id. (emphasis added).) Schofield issued a report on December 17, 2018. (Petition, Ex. D, Impartial Umpire’s Report.) On page 2 Schofield listed the rules of his engagement, pursuant to the retention letter and a joint teleconference that preceded it: (1) I was tasked to attend an inspection of the subject boat, jointly attended by the two named surveyors for Insured and Underwriters. (2) I was tasked to review reports submitted to me by surveyors and/or appraisers appointed by each of the two parties in contention. (3) I was tasked to determine the cause of the loss, extent of damages resulting from the cause of the loss, and determine the reasonableness of methods and cost of proposed repairs to restore the insured vessel condition before the loss.

1 Although the policy uses the phrase “appraisers,” the parties’ submissions consistently refer to these professionals as “surveyors.” The Court will use the same convention.

2 Schofield’s retention as impartial umpire followed Resch’s lawsuit filed to compel his appointment. See Civ. Action No. 18-12475 (D.N.J.). Resch dismissed the suit shortly after filing, purportedly upon Catlin’s agreement to the appointment. (See D.E. 5, Catlin Opp. 3-4.) (Impartial Umpire’s Report at 2.) Schofield’s report detailed his inspection of the vessel and study of the documentation provided to him on behalf of the parties, along with his own relevant experience and his conclusions as to the extent of damages to the vessel and the cost and methods of repair he determined to be reasonable. The report evaluated the repair quotes provided by Catlin, noting that one was in the amount of $35,854.50, “with additional replacement, storage and related costs” bringing that estimate to $41,867. (Id. at 6.) To that amount would be added “fuel costs, storage, bottom painting, haul-out etc.,” bringing “the total repair cost to about $45,000.” (Id.) Another repair quote totaled $36,858, to which “fuel costs, storage, bottom painting, haul-out etc.” would be added, resulting in the “total repair cost

[coming] again to about $45,000.” (Id.) The report went on to detail the reasons why Schofield rejected the opinions and conclusions Resch submitted. (Id. at 7-9.) Schofield ultimately concluded as follows: On the basis of the tendered quotation for repair, Extent of Loss is therefore established as the quoted cost of repair of $41,867, plus transportation and ancillary dockyard costs, including hull bottom antifouling recoating, yard storage fees and related costs, approximately $45,000, all.

(Id. at 6.) The report ended with the following paragraph: I may have additional opinions in this matter, pending my review of additional produced reports and materials. Should any other Experts’ reports become available between the issuance of this Report and conclusion of this matter, the Undersigned reserves the right to analyze, study, calculate and compare such information as it becomes available.

(Id. at 9.) In a January 29, 2019 email to the parties, Schofield clarified an aspect of his report and observed that his assignment had been completed. (D.E. 2-6, 1/29/19 Email.) On March 18, 2019, Resch filed his petition to vacate. III. Standard of Review “There is a strong presumption under the Federal Arbitration Act, 9 U.S.C. § 1 et seq., in favor of enforcing arbitration awards.” Brentwood Med. Assocs. v. UMW, 396 F.3d 237, 241 (3d Cir. 2005) (citing Moses H. Cone Mem’l Hosp. v. Mercury Constr. Corp., 460 U.S. 1, 24-25 (1983)). An arbitration award is presumed valid unless affirmatively shown to be otherwise, id.,

and is reviewed extremely deferentially, although the Court is not a mere rubber stamp, Hamilton Park Health Care Ctr. Ltd. v. 1199 SEIU United Healthcare Workers East, 817 F.3d 857, 861 (3d Cir. 2016). The award may only be attacked as invalid on one or more of the grounds in 9 U.S.C. § 10, or as against public policy. Brentwood, 496 F.3d at 241. Resch invokes 9 U.S.C. § 10(a)(4), under which the Court may vacate an arbitration award where the arbitrator exceeded his powers or “so imperfectly executed them that a mutual, final, and definite award upon the subject matter submitted was not made.” An arbitrator only “exceeds his powers” when “he decides an issue not submitted to him, grants relief in a form that cannot be rationally derived from the parties’ agreement and submissions, or issues an award that

is so completely irrational that it lacks support altogether.” Sutter v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
RESCH v. CATLIN INDEMNITY COMPANY, Counsel Stack Legal Research, https://law.counselstack.com/opinion/resch-v-catlin-indemnity-company-njd-2020.