Diede Construction Inc. v. Monterey Mechanical Co.

22 Cal. Rptr. 3d 763, 125 Cal. App. 4th 380, 2004 Daily Journal DAR 15303, 2004 Cal. Daily Op. Serv. 11360, 2004 Cal. App. LEXIS 2228
CourtCalifornia Court of Appeal
DecidedDecember 28, 2004
DocketA102035
StatusPublished
Cited by3 cases

This text of 22 Cal. Rptr. 3d 763 (Diede Construction Inc. v. Monterey Mechanical Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Diede Construction Inc. v. Monterey Mechanical Co., 22 Cal. Rptr. 3d 763, 125 Cal. App. 4th 380, 2004 Daily Journal DAR 15303, 2004 Cal. Daily Op. Serv. 11360, 2004 Cal. App. LEXIS 2228 (Cal. Ct. App. 2004).

Opinion

*384 Opinion

POLLAK, J.

Plaintiff Diede Construction, Inc. (Diede) was awarded a $12 million contract to renovate the city hall in the City of Livermore (the city). After the bids were opened but before Diede executed a contract with the city, defendant Monterey Mechanical Company (Monterey), a subcontractor Diede had listed in its bid pursuant to Public Contract Code 1 section 4104, informed Diede that its proposal contained a $300,000 mistake, that it would not honor the proposal, and that Diede should seek to be relieved of its bid to the city pursuant to sections 5101 and 5103. Diede nonetheless proceeded to execute a contract with the city and, when Monterey refused to perform, contracted with other subcontractors to perform Monterey’s portions of the project. Thereafter, Diede filed a complaint seeking to recover from Monterey, on a theory of promissory estoppel, the difference between Monterey’s original bid and the amounts Diede was required to pay the replacement subcontractors. After a bench trial, the court denied Diede’s claim because Diede did not attempt to be relieved from its bid to the city after learning of Monterey’s mistake. We conclude relief is available under sections 5101 and 5103 only for errors in the general contractor’s bid and that Diede was not required to request relief from its bid to the city as a condition of holding Monterey to its bid for the subcontract. Nonetheless, Diede’s right to recover on the basis of promissory estoppel is dependant on its proving that it reasonably relied on Monterey’s mistaken bid in calculating the amount of its bid to the city, as to which the trial court made no finding. Accordingly, we shall reverse the judgment and remand for a determination of this controlling issue.

Factual and Procedural Background

Diede is a general contractor that performs large public works projects. Monterey is a contractor specializing in mechanical, plumbing, and heating, ventilation, and air conditioning (HVAC) work. On August 4, 2000, Diede submitted a bid to perform all work on a project to remodel the city hall for $12,739,375. Monterey’s bid to Diede to perform the HVAC and certain other work on the project was $1,775,000. Diede listed Monterey as its HVAC subcontractor and allocated 18 percent of the total contract price to its work. 2 Diede learned later that day that it was the low bidder on the job.

The next business day, three days later, Monterey faxed a letter to Diede stating that it had discovered an inadvertent clerical error in its proposal and *385 it was therefore withdrawing its bid. The letter explained that Monterey’s proposal failed to include the cost of $302,100 for its controls subcontractor. Diede faxed a reply stating that it had based its bid on Monterey’s quote and expected Monterey to honor its bid. The next morning, Monterey’s attorney sent Diede a letter enclosing two declarations showing how the mistake was made, and advising Diede that if it acted by the next day, it could use the declarations to withdraw its bid under the relief provisions of the Public Contract Code. Diede disagreed that such relief was available for Monterey’s mistake, and it did not wish to forfeit its bid bond, lose the substantial sums expended in bidding on the project, or sacrifice the profit and the enhanced professional reputation that it felt it would realize from completing the project. Accordingly, Diede executed the contract with the city for the original bid amount.

After Monterey refused to perform the subcontract work, Diede executed contracts with the next lowest bidders for the portions of the work Monterey was to perform at an increased cost of $467,064, and filed this action to recover these additional costs from Monterey. The trial court found that Monterey’s proposal contained a material clerical mistake that satisfied the requirements for relief under the Public Contract Code. Accordingly, it held that Diede had not established the elements of promissory estoppel because Diede’s continued reliance on Monterey’s bid after receiving notice of the mistake was unreasonable, and that the damages sought “could have been readily prevented if Diede had sought to be relieved of its bid to the [cjity.” Diede filed a timely notice of appeal.

Discussion

1. Elements of Promissory Estoppel

A general contractor may recover damages incurred as a result of its reasonable reliance on a subcontractor’s mistaken bid under the theory of promissory estoppel. “ ‘A promise which the promisor should reasonably expect to induce action or forebearance of a definite and substantial character on the part of the promisee and which does induce such action or forebearance is binding if injustice can be avoided only by enforcement of the promise.’ [Citation.] This principle is applicable to a proposed subcontractor (promisor) who makes a bid (and with it an implied subsidiary promise to keep the bid open for a reasonable time after the awarding of tire general contract) to a general contractor (promisee) who in turn bids on a construction contract with a third person in reliance upon the subcontractor’s bid (and subsidiary promise) and is the successful bidder.” (Saliba-Kringlen Corp. v. Allen Engineering Co. (1971) 15 Cal.App.3d 95, 100 [92 Cal.Rptr. 799] (Saliba-Kringlen), citing Drennan v. Star Paving Co. (1958) 51 Cal.2d 409 *386 [333 P.2d 757] (Drennan).) “As between the subcontractor who made the bid and the general contractor who reasonably relied on it, the loss resulting from the mistake should fall on the party who caused it.” (Drennan, supra, 51 Cal.2d at p. 416.)

Thus, in order to prevail on its promissory estoppel claim, Diede was required to prove that it had reasonably relied on Monterey’s bid to its detriment, and that injustice could be avoided only by enforcing Monterey’s promise to perform at the quoted price.

2. Statutory Provisions for the Relief of Bidders

“In 1971 the state Legislature established a comprehensive procedure in connection with public contracts ... to enable a contractor to claim relief from a bid mistake by following certain procedural steps.” (A & A Electric, Inc. v. City of King (1976) 54 Cal.App.3d 457, 462 [126 Cal.Rptr. 585] (A & A Electric).) The derivation of these provisions traces back to more limited legislation first enacted in 1937 (see Stats. 1937, ch. 202, § 2, p. 498) and briefly described in A & A Electric, supra, at pages 461-464. These provisions were initially found in Government Code sections 4200 through 4208, but in 1982, without significant change, became chapter 5 of division 2, part 1 of the Public Contract Code, entitled “Relief of Bidders.” (§ 5100 et seq.; Emma Corp. v. Inglewood Unified School Dist.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weitz Co. v. Hands, Inc.
882 N.W.2d 659 (Nebraska Supreme Court, 2016)
Flintco Pacific v. TEC Management Consultants
California Court of Appeal, 2016
Flintco Pacific, Inc. v. TEC Management Consultants, Inc.
1 Cal. App. 5th 727 (California Court of Appeal, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
22 Cal. Rptr. 3d 763, 125 Cal. App. 4th 380, 2004 Daily Journal DAR 15303, 2004 Cal. Daily Op. Serv. 11360, 2004 Cal. App. LEXIS 2228, Counsel Stack Legal Research, https://law.counselstack.com/opinion/diede-construction-inc-v-monterey-mechanical-co-calctapp-2004.