Devon Energy Production Company v. Line Finders

CourtCourt of Appeals for the Tenth Circuit
DecidedSeptember 14, 2022
Docket21-6119
StatusUnpublished

This text of Devon Energy Production Company v. Line Finders (Devon Energy Production Company v. Line Finders) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Devon Energy Production Company v. Line Finders, (10th Cir. 2022).

Opinion

Appellate Case: 21-6119 Document: 010110738905 Date Filed: 09/14/2022 Page: 1 FILED United States Court of Appeals UNITED STATES COURT OF APPEALS Tenth Circuit

FOR THE TENTH CIRCUIT September 14, 2022 _________________________________ Christopher M. Wolpert Clerk of Court DEVON ENERGY PRODUCTION COMPANY, L.P.,

Plaintiff - Appellee,

v. Nos. 21-6119 & 21-6162 (D.C. No. 5:20-CV-00636-F) LINE FINDERS, LLC, d/b/a Line Finders, (W.D. Okla.) f/k/a Line Finders, Inc.,

Defendant - Appellant. _________________________________

ORDER AND JUDGMENT * _________________________________

Before TYMKOVICH, Chief Judge, MATHESON and EID, Circuit Judges. _________________________________

Defendant-Appellant Line Finders, LLC, appeals the district court’s

enforcement of a settlement agreement in favor of Plaintiff-Appellee Devon Energy

Production Company, L.P. Line Finders also appeals the district court’s award of

attorney fees to Devon. We consolidated the appeals. Exercising jurisdiction under

28 U.S.C. § 1291, we affirm the district court’s judgment.

* After examining the briefs and appellate record, this panel has determined unanimously that oral argument would not materially assist in the determination of this appeal. See Fed. R. App. P. 34(a)(2); 10th Cir. R. 34.1(G). The case is therefore ordered submitted without oral argument. This order and judgment is not binding precedent, except under the doctrines of law of the case, res judicata, and collateral estoppel. It may be cited, however, for its persuasive value consistent with Fed. R. App. P. 32.1 and 10th Cir. R. 32.1. Appellate Case: 21-6119 Document: 010110738905 Date Filed: 09/14/2022 Page: 2

I. BACKGROUND

Line Finders provides support services for Devon’s oil and gas operations. In

2018, two Line Finders employees, Marcus Murschel and Michael Elsasser, were

injured in a gas-line explosion allegedly caused by a Devon employee. Mr. Murschel

demanded compensation from Devon, prompting Devon to seek defense and

indemnification from Line Finders under their support services contract—the “Master

Service and Supply Agreement Onshore and Maritime” (MSSA), Aplt. App. at 22.

Line Finders rejected Devon’s request, so Devon filed this diversity action, asserting

claims for declaratory relief, breach of contract, and damages.

The parties engaged in settlement negotiations. Line Finders outlined several

material terms to resolve the dispute, and on April 7, 2021, Devon emailed Line

Finders a counter-offer. Devon proposed, among other things, that the parties file a

joint or unopposed motion to enter judgment in favor of Devon on its claim for

declaratory relief. If granted, Devon would dismiss its remaining claims and Line

Finders would not appeal. If Mr. Murschel or Mr. Elsasser advanced their claims, the

parties would resubmit a request for defense and indemnification to Line Finders’

insurer. If denied coverage, Line Finders would defend and indemnify Devon. Both

parties would sign the written settlement agreement. On April 8, Line Finders agreed

to these terms and invited Devon to prepare a draft settlement agreement for review.

Devon prepared a draft. The parties modified it over the next several weeks.

On May 21, 2021, Devon sent Line Finders the settlement agreement. That same

day, Line Finders’ attorney responded, “The settlement agreement looks fine. Please

2 Appellate Case: 21-6119 Document: 010110738905 Date Filed: 09/14/2022 Page: 3

send me an execution version and I will procure signature.” Id. at 142. Devon did

not immediately send an execution version to Line Finders, however, and on June 9,

Devon received a demand for compensation from Mr. Elsasser, the second Line

Finders employee injured in the explosion. Two days later, on June 11, Devon

signed the settlement agreement, and on June 17, sent it to Line Finders for execution

with Mr. Elsasser’s demand attached. The parties later tendered Mr. Elsasser’s

demand to the insurer, but Line Finders never signed the settlement agreement.

Devon moved the district court to enforce the settlement agreement and enter

judgment on its claim for declaratory relief. Line Finders objected, arguing (1) it

never signed the settlement agreement, which was contingent on mutual execution,

and (2) the settlement agreement was premised on a mistake and fraud because

Line Finders relied on the fact that Mr. Elsasser had not made a demand, which

Devon failed to disclose immediately. Devon disputed both arguments, contending

(1) the settlement agreement superseded all prior understandings and did not require

signatures, and (2) there was no mistake because the settlement agreement expressly

contemplated that both Mr. Murschel and Mr. Elsasser could advance their claims,

nor was there fraud because the parties negotiated, and Line Finders accepted, the

settlement agreement before Mr. Elsasser submitted his demand.

The district court enforced the settlement agreement, ruling that Line Finders’

counsel accepted the settlement agreement on May 21, and nothing in the settlement

agreement required mutual execution. The court also determined there was no

mistake of fact because Line Finders understood it was possible Mr. Elsasser could

3 Appellate Case: 21-6119 Document: 010110738905 Date Filed: 09/14/2022 Page: 4

pursue his claims, which was expressly contemplated in the settlement agreement.

Nor was there fraud, the court concluded, because Line Finders accepted the

settlement agreement on May 21 before Devon received Mr. Elsasser’s demand on

June 9. Thus, the district court recorded a journal entry of judgment in favor of

Devon on its claim for declaratory relief. The district court also granted Devon’s

motion to dismiss its remaining claims and awarded Devon attorney fees. Line

Finders now appeals the district court’s enforcement of the settlement agreement and

award of attorney fees.

II. DISCUSSION

A. Settlement Agreement

1. Legal standards

“A trial court has the power to summarily enforce a settlement agreement

entered into by the litigants while the litigation is pending before it.” United States v.

Hardage, 982 F.2d 1491, 1496 (10th Cir. 1993). State contract law governs issues of

formation. Shoels v. Klebold, 375 F.3d 1054, 1060 (10th Cir. 2004). In Oklahoma,

whether there has been a meeting of the minds to form a settlement agreement is a

question of fact. Gomes v. Hameed, 184 P.3d 479, 485 (Okla. 2008). Thus, although

we generally “review the [district] court’s approval of the settlement agreement for

an abuse of discretion,” Hardage, 982 F.2d at 1495, we review the district court’s

ultimate finding that the parties reached a binding settlement agreement for clear

error, see Shoels, 375 F.3d at 1056.

4 Appellate Case: 21-6119 Document: 010110738905 Date Filed: 09/14/2022 Page: 5

Under Oklahoma law, “[a] settlement agreement is an oral or written contract

between the parties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shoels v. Klebold
375 F.3d 1054 (Tenth Circuit, 2004)
Koch Fuels, Inc. v. State Ex Rel. Oklahoma Tax Commission
1993 OK 140 (Supreme Court of Oklahoma, 1993)
Watkins v. Grady County Soil & Water Conservation District
1968 OK 24 (Supreme Court of Oklahoma, 1968)
Mercury Investment Co. v. F.W. Woolworth Co.
1985 OK 38 (Supreme Court of Oklahoma, 1985)
Harkrider v. Posey
2000 OK 94 (Supreme Court of Oklahoma, 2000)
Russell v. COUNTY COM'RS OF CARTER COUNTY
2000 OK CIV APP 21 (Court of Civil Appeals of Oklahoma, 2000)
Vela v. Hope Lumber & Supply Co.
1998 OK CIV APP 162 (Court of Civil Appeals of Oklahoma, 1998)
Hai v. Baptist Healthcare of Oklahoma, Inc.
2010 OK CIV APP 3 (Court of Civil Appeals of Oklahoma, 2009)
In Re De-Annexation of Certain Real Property From City of Seminole
2009 OK 18 (Supreme Court of Oklahoma, 2009)
Gomes v. Hameed
2008 OK 3 (Supreme Court of Oklahoma, 2008)
SUTTON v. DAVID STANLEY CHEVROLET
2020 OK 87 (Supreme Court of Oklahoma, 2020)
J. P. C. Petroleum Corp. v. Vulcan Steel Tank Corp.
118 F.2d 713 (Tenth Circuit, 1941)
WIGGIN PROPERTIES v. ARCO BUILDING
2022 OK CIV APP 13 (Court of Civil Appeals of Oklahoma, 2021)
Gatz v. Southwest Bank of Omaha
836 F.2d 1089 (Eighth Circuit, 1988)
United States v. Hardage
982 F.2d 1491 (Tenth Circuit, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
Devon Energy Production Company v. Line Finders, Counsel Stack Legal Research, https://law.counselstack.com/opinion/devon-energy-production-company-v-line-finders-ca10-2022.