This text of 1968 OK 24 (Watkins v. Grady County Soil & Water Conservation District) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Watkins v. Grady County Soil & Water Conservation District, 1968 OK 24, 438 P.2d 491 (Okla. 1968).

Opinion

BERRY, Justice.

This appeal involves the correctness of the trial court’s judgment enjoining defendant landowner from interfering with an easement executed in favor of plaintiff, Grady County Soil & Water Conservation District, a public corporation organized and existing under state law.

Defendants owned and occupied a quarter section of land in Grady County as their homestead. Plaintiff Conservation District was carrying out a cooperative plan for control of flood waters in the Laflin and Winter Creek watersheds in the county. This plan required securing of easements for dam sites upon predetermined locations, one of which (Site 5) was to be upon defendants’ land. On November 18, 1963, defendants executed an easement which granted plaintiff the right to construct, maintain and operate a flood control dam upon their land, for a recited consideration of $1.00, which was not paid. The easement, which described defendants’ entire quarter section, was recorded and plaintiff began a detailed survey preliminary to beginning construction. While so engaged defendants directed these representatives to leave the premises.

On April 5, 1965, plaintiff filed suit seeking a restraining order to enjoin defendants from interfering with continuance of surveying and actual construction. Upon allegation of irreparable damage defendants were restrained from further interference by order dated April 30th and the matter set for further hearing.

On June 3, 1965, defendants filed answer denying the material allegations of the petition, and cross-petition alleging the easement had been procured by misrepresentation and fraud and without consideration, and should be canceled, and set aside. Fur- : ther, that defendants were entitled to a permanent injunction, having no adequate rem- . edy at law to prevent plaintiff from build- - ing the dam structure and thereby damaging the land and destroying crops. Defendants asked cancellation of the written easement and removal of same as a cloud upon their title, and that plaintiff be perpetually enjoined from interfering or molesting their property. Defendants also asked damages for trespass and punitive damages.

The temporary restraining order granted plaintiff was continued in effect pending the trial court’s final determination. During this time defendants sought dissolution of the temporary order, and plaintiff sought contempt citations against defendants for alleged violation of the terms of the restraining order. Before trial plaintiff filed amended answer to the cross-petition alleging completion of all preliminary work and execution of contracts for construction of dams in the project, including the structure on defendants’ land, which was a necessary and integral part of the project; further, if defendants were permitted to rescind the easement irreparable damage and expense would be caused members of the District whose lands were included in the project.

*493 The evidence disclosed the easement was obtained from defendants by one Nunley, an employee of the Soil Conservation Service in the county, who took the drafted easement to defendants for execution, but did not direct attention to the fact the instrument granted an easement to the entire tract. The instrument was signed by defendants, in presence of Nunley and Goins, while the parties were near the proposed dam site. Nunley also advised defendants they would have complete control of the dam and impounded water, but defendants were not advised as to height of the dam or spillway or the amount of water permanently covering the land because he did not know. This witness denied advising defendants there would be only .2-3 acres of permanent water, or that the water never would get out of banks in the west branch of the creek. Witness was working from an overlay map which did not provide means for determining the amount of land to be covered permanently.

The data book showing the Work Plan on the watershed had been prepared by the Soil Conservation Service in June, 1963. This booklet would have disclosed pertinent information concerning the project but witness did not have the booklet, and did not furnish a copy to defendants. This proj ect information book disclosed a sediment pool of 16 acres would be entirely on defendants’ land, and the flood water detention pool would cover 52 acres, of which 46 acres would cover their land. When the easement was executed this witness did not know the size area from which construction dirt would be taken, or that with the “draw down” pipe closed there would be 12 acres under water. Although they examined the overlay map, defendants were not told the approximate acreage to be covered at flood stage, or the amount of land to be taken. A member of the District organization previously had presented the proposed easement to defendants, who refused to sign. Nunley was asked to explain the easement to defendants and attempt to secure their agreement and execution of the instrument.

Nunley testified the easement intentionally covered the entire tract because defendants bore a reputation of having lawsuits, and the Conservation Committee wanted everything included so no question might arise. This attitude of Nunley, unrevealed to defendants, was inconsistent with the preliminary negotiations arising when plaintiff’s agents and defendants were inspecting the premises. The record discloses no evidence the plaintiff District imparted or suggested to defendants, in preliminary negotiations or otherwise, any intention to obtain an easement on the entire tract. Even though the testimony of the parties is in conflict, it is significant that the basic inconsistency goes only to a fractional part of the tract to be inundated. This evidence, even considered in the light most favorable to plaintiff, can only be construed as showing the contract was entered into by mistake on the part of both litigants.

The evidence showed a proposed easement had been presented on two prior occasions, and defendants declined to sign. Defendants took Nunley’s word for the instrument and did not read the description. The easement was not explained before being signed, nor the fact that District could raise the dam when desired, or that the entire quarter section was included.

Defendants testified they signed the easement without reading the instrument, relying upon what Nunley told them, but would not have signed had they known the entire quarter was included, or that 46 acres of their land would be covered at flood stage. They were shown an iron stob in the north field and advised this would be flood stage, which might occur once each fifty years. Defendants testified they were advised that only a few trees would need to be removed near the dam, and only 2-3 acres would be covered. Earlier defendants refused to execute the easement when advised that some large trees in the area would have to be removed.

An engineer, who conducted a survey for defendants, testified the base of the trees *494 along the west branch would be approximately 23.5 feet below the top of the dam. There was a small dam impounding water on the northwest stream branch approximately one fourth mile from the dam site. Survey showed the top of this small dam would be approximately 7.6 feet below the spillway level of the proposed dam. Some 400-500 feet upstream was another small dam impounding water. Survey showed the top of this structure was approximately 1.5 feet below the bottom of the emergency spillway.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Zilahy-Welsh v. Denton
N.D. Oklahoma, 2025
Accelerated v. LMI II
Tenth Circuit, 2024
Mecom v. Morris
N.D. Oklahoma, 2022
Get, LLC v. City of Blackwell
407 F. App'x 307 (Tenth Circuit, 2011)
Opinion No. (2005)
Oklahoma Attorney General Reports, 2005
Beck v. Reynolds
1995 OK 83 (Supreme Court of Oklahoma, 1995)
Brown v. City of Oklahoma City, Okl.
45 F.3d 439 (Tenth Circuit, 1994)
French Energy, Inc. v. Alexander
1991 OK 106 (Supreme Court of Oklahoma, 1991)
Hampton v. Surety Development Corp.
1991 OK 94 (Supreme Court of Oklahoma, 1991)
Sabine Corp. v. ONG Western, Inc.
725 F. Supp. 1157 (W.D. Oklahoma, 1989)
Edward E. Gatz Dennis C. Russell Marvin J. Frank Earl R. Willats Jack Shelley, James J. And Patricia Phalen Marlene W. Hechtman Vale H. Sorensen Larry E. Haack Raymond G. And Dorothy Alvine, William Chapman, Glenn A. Goodrich Allen E. Zencka Joseph Lynch Vincent Runco Larry L. Hald Donald D. Kerr Kermit A. Brashear, II Peter D. Knott Dennis D. Weiss William Wolfe Frank Cernik Frank Cernik, Trustee and Buckeye Pizza Corporation v. Southwest Bank of Omaha Packers National Bank Security National Bank of Omaha Bank of Millard U.S. National Bank of Omaha First West Side Bank the Omaha National Bank Northwestern National Bank First National Bank of Omaha Center Bank American National Bank Bank of the Midlands Ames Bank and First Westroad Bank v. The Federal Deposit Insurance Corporation, as Receiver of Penn Square Bank, N.A., Intervenor. Edward E. Gatz Dennis C. Russell Marvin J. Frank Earl R. Willats Jack Shelley James J. And Patricia Phalen Marlene W. Hechtman Vale H. Sorensen Larry E. Haack Raymond G. And Dorothy Alvine, William Chapman, Glenn A. Goodrich Allen E. Zencka Joseph Lynch Vincent Runco Larry L. Hald Donald D. Kerr Kermit A. Brashear, II Peter D. Knott Dennis D. Weiss William Wolfe Frank Cernik Frank Cernik, Trustee and Buckeye Pizza Corporation v. Southwest Bank of Omaha Packers National Bank Security National Bank of Omaha Bank of Millard U.S. National Bank of Omaha First West Side Bank the Omaha National Bank Northwestern National Bank (Now Known as Norwest Bank Nebraska, n.a.) First National Bank of Omaha Center Bank American National Bank Bank of the Midlands and Ames Bank First Westroads Bank v. The Federal Deposit Insurance Corporation, as Receiver of Penn Square Bank, N.A.
836 F.2d 1089 (First Circuit, 1988)
Gatz v. Southwest Bank of Omaha
836 F.2d 1089 (Eighth Circuit, 1988)
Madill Bank and Trust Co. v. Herrmann
738 P.2d 567 (Court of Civil Appeals of Oklahoma, 1987)
Bobo v. Bigbee
1976 OK 40 (Supreme Court of Oklahoma, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
1968 OK 24, 438 P.2d 491, Counsel Stack Legal Research, https://law.counselstack.com/opinion/watkins-v-grady-county-soil-water-conservation-district-okla-1968.