Detroit Edison Co. v. Public Service Commission

342 N.W.2d 273, 127 Mich. App. 499
CourtMichigan Court of Appeals
DecidedJuly 20, 1983
DocketDocket 61961, 61962
StatusPublished
Cited by20 cases

This text of 342 N.W.2d 273 (Detroit Edison Co. v. Public Service Commission) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Detroit Edison Co. v. Public Service Commission, 342 N.W.2d 273, 127 Mich. App. 499 (Mich. Ct. App. 1983).

Opinion

Per Curiam:.

This is an appeal as of right by The Detroit Edison Company from a December 23, 1981, judgment of the Ingham County Circuit Court, which affirmed a March 30, 1976, order of the Michigan Public Service Commission, granting the utility a rate increase for electrical service in the amount of $62,425,000.

On April 10, 1975, Edison petitioned the commission for permission to increase its electric rates by $177,865,000. The petition was accompanied by *504 the utility’s motion for partial and immediate interim rate relief in the amount of $88,112,000. The petition became MPSC case U-4807.

Public hearings began July 14, 1976. In the months thereafter, the record spanned 51 days of hearings and included 6,087 pages of transcript and 108 exhibits. On July 24, 1975, Edison renewed its motion for interim relief, this time in the amount of $84,800,000. On September 5, 1975, the commission staff recommended that the utility be granted final rate relief in the amount of $105,-900,000. A week later, the commission staff recommended that the utility be granted interim rate relief in the amount of $39,833,000.

On January 9, 1976, the commission reported to the Governor that it was unable to conclude the rate proceeding within nine months as required by then MCL 460.6a(3); MSA 22.13(6a)(3), most recently amended by 1982 PA 304 and now subsection 6a(4).

On February 9, 1976, the commission denied the utility’s request for interim rate relief, principally because the commission’s final decision was expected shortly. On February 27, 1976, the administrative hearing officer recommended that the utility be granted final rate relief in the amount of $88,334,000. On March 30, 1976, the commission entered its final order, granting the utility final rate relief in the amount of $62,425,000, effective March 31, 1976.

On April 28, 1976, Edison filed a petition in Ingham County Circuit Court for judicial review of the commission’s final order, pursuant to § 26(a) of the so-called railroad commission act, MCL 462.26(a); MSA 22.45(a). At the same time, the utility requested injunctive relief for a rate increase pending judicial review, pursuant to § 26(b). *505 After hearing, and by opinion filed May 19, 1976, and order entered May 28, 1976, then Circuit Judge Donald Reisig granted the utility’s request for injunctive relief and permitted the utility to collect an interim rate increase in the amount of $13,846,000 under bond. The Attorney General, who had intervened in the case, and the commission sought leave to appeal that injunctive order, but this Court denied leave to appeal on September 30, 1976. See Detroit Edison Co v Michigan Public Service Comm, Docket Nos. 28871, 28872, 28091 and 28092. The Attorney General and the commission then sought leave to appeal to the Supreme Court. The Supreme Court also denied leave to appeal. 398 Mich 803 (1976). Edison collected the interim rate increase in its November and December, 1976, utility bills.

Meanwhile, back in circuit court, Judge Reisig had resigned and the case was assigned to Judge Michael Harrison. Judge Harrison conducted a nine-day trial in the summer of 1977 and, by order entered January 13, 1978, he remanded the case to the commission to consider additional evidence, as is permitted by § 26(c) of the railroad commission act, MCL 462.26(c); MSA 22.45(c). The commission rendered its final decision on remand on July 19, 1979. The commission affirmed its previous final order.

On December 23, 1981, Judge Harrison filed an opinion and entered a judgment affirming the commission’s decision. Edison appeals, raising several issues.

I

Edison argues that the commission and circuit court erred by failing to consider the "cumulative impact” of the commission’s alleged failure to *506 adopt an adequate test year, its refusal to award interim rate relief, its failure to reach a timely decision and its denial of an earnings erosion allowance. The failure to consider the overall impact of those rulings resulted in unreasonable, unjust and confiscatory ratemaking in this case, the utility argues. Nevertheless, Edison concedes that it is not appealing those claimed errors in and of themselves. In view of that concession, the "overall impact” argument, if valid at all, is valid only if the individual claims of error have some merit in and of themselves.

II

Edison argues that the commission chose an inappropriate test year on which to base the rates the utility could charge in 1976. The test year adopted by the commission was based on actual data showing the business experience of the company in the first six months of 1975 and data projected into the last six months of 1975. But, the company argues, by the time the commission entered its final order in March of 1976, the data and test year were already nine months out of date. So, the company says, in spite of the commission’s protestations that it was using current or projected test year data, the test year was actually an historical one. Therefore, the argument goes, the test year was inadequate because it led to rates which did not adequately reflect changes in rate base, income and expenses and the effects of inflation on those factors. Edison argues that the commission should have adopted a test year that more accurately resembled the year in which the rates were to be collected and, failing that, the commission should have adopted some adjustment in rates (for example, interim relief or an earnings erosion *507 allowance) to afford the company a reasonable opportunity to earn its authorized rate of return. Edison argues that the circuit court erred by failing to address the effects of adopting an inadequate historical test year and concludes that: "The Court’s lack of consideration or understanding of such consequences is indicative of the Court’s failure to consider the overall impact of its Order.”

The scope of review and the burden of proof on appeal are prescribed by statute. Under § 25 of the railroad commission act, rates set by the commission "shall be in force and shall be prima facie, lawful and reasonable until finally found otherwise * * MCL 462.25; MSA 22.44. Michigan Bell Telephone Co v Public Service Comm, 332 Mich 7; 50 NW2d 826 (1952); Attorney General v Public Service Comm, 118 Mich App 311; 324 NW2d 628 (1982); Consumers Power Co v Public Service Comm, 78 Mich App 581; 261 NW2d 10 (1977); Attorney General v Public Service Comm, 63 Mich App 69; 234 NW2d 407 (1975), lv den 395 Mich 779 (1975). On appeal, the appellant has the burden "to show by clear and satisfactory evidence that the order of the commission complained of is unlawful or unreasonable, as the case may be”. MCL 462.26(e); MSA 22.45(e). In any appeal, the appellant is required to show that findings of fact by the commission are not supported by competent, material and substantial evidence on the whole record. Const 1963, art 6, § 28; Great Lakes Steel Div of National Steel Corp v Public Service Comm, 416 Mich 166; 330 NW2d 380 (1982); Consumers Power Co v Public Service Comm, supra.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Consumers Energy Co.
279 Mich. App. 180 (Michigan Court of Appeals, 2008)
In Re Detroit Edison Co. Application
740 N.W.2d 685 (Michigan Court of Appeals, 2007)
Attorney General v. MPSC
618 N.W.2d 904 (Michigan Supreme Court, 2000)
Consumers Power Co. v. Public Service Commission
448 N.W.2d 806 (Michigan Court of Appeals, 1989)
Boston Gas Co. v. Department of Public Utilities
539 N.E.2d 1001 (Massachusetts Supreme Judicial Court, 1989)
Attorney General v. Public Service Commission
438 N.W.2d 620 (Michigan Court of Appeals, 1988)
General Motors Corp. v. Public Service Commission No 2
438 N.W.2d 616 (Michigan Court of Appeals, 1988)
General Motors Corp. v. Public Service Commission No 1
175 Mich. App. 576 (Michigan Court of Appeals, 1988)
Abate v. Psc
420 N.W.2d 81 (Michigan Supreme Court, 1988)
Pennwalt Corp. v. Public Service Commission
420 N.W.2d 156 (Michigan Court of Appeals, 1988)
Meléndez Ortiz v. Valdejully
120 P.R. Dec. 1 (Supreme Court of Puerto Rico, 1987)
Detroit Edison Co. v. Public Service Commission
400 N.W.2d 644 (Michigan Court of Appeals, 1986)
Northern Michigan Exploration Co. v. Public Service Commission
396 N.W.2d 487 (Michigan Court of Appeals, 1986)
Attorney General v. Public Service Commission 2
358 N.W.2d 351 (Michigan Court of Appeals, 1984)
Attorney General v. Public Service Commission 1
349 N.W.2d 539 (Michigan Court of Appeals, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
342 N.W.2d 273, 127 Mich. App. 499, Counsel Stack Legal Research, https://law.counselstack.com/opinion/detroit-edison-co-v-public-service-commission-michctapp-1983.