Pennwalt Corp. v. Public Service Commission

420 N.W.2d 156, 166 Mich. App. 1
CourtMichigan Court of Appeals
DecidedFebruary 1, 1988
DocketDocket 89708
StatusPublished
Cited by17 cases

This text of 420 N.W.2d 156 (Pennwalt Corp. v. Public Service Commission) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pennwalt Corp. v. Public Service Commission, 420 N.W.2d 156, 166 Mich. App. 1 (Mich. Ct. App. 1988).

Opinion

Hood, P.J.

Plaintiff, Pennwalt Corporation, appeals as of right from an order of the Ingham Circuit Court affirming the decision of the Michigan Public Service Commission in which the commission ruled that defendant The Detroit Edison Company could include in the rate base used to calculate the rate Edison charged plaintiff for steam and electric service its total expenditures incurred in constructing a wastewater treatment facility.

Until April 1, 1964, plaintiff owned and operated its own power plant in Wyandotte, Michigan, which supplied electricity and steam to its plant engaged in manufacturing and processing industrial chemicals. On April 1, 1964, plaintiff sold its steam and electrical generating equipment to Edison and leased to Edison the real estate upon which the equipment stood. In exchange, Edison agreed to supply plaintiff with electricity and industrial process steam for use at plaintiff’s plant, at a specified rate. In early 1981, Edison applied to the commission to increase its rates. The case was assigned number U-6488. Plaintiff intervened in the action, claiming that Edison’s rate base should *4 be reduced by an amount up to $1,693,000 to reflect allegedly excessive costs of installation, construction, engineering, and supervision of a waste-water treatment facility. 1 Edison, on the other hand, maintained that the total cost of the waste-water treatment facility should be included in its rate base because the costs associated therewith were justified and reasonable. The commission found Edison’s total costs to be reasonable and, thus, allowed Edison to include the total costs in its rate base. Plaintiff filed a complaint in Ingham Circuit Court, seeking review of the commission’s decision. The case was dismissed for lack of progress on January 11, 1983. Pennwalt appealed to this Court, which affirmed. Pennwalt Corp v Public Service Comm #1, 136 Mich App 530; 357 NW2d 712 (1984), lv den 428 Mich 889 (1987).

In the meantime, Edison petitioned the commission for another rate increase on September 14, 1981. That case was assigned case number U-6949. Plaintiff again intervened, again challenging the reasonableness of Edison’s expenditures in constructing the wastewater treatment facility. Edison moved to strike the testimony of Pennwalt’s witness, Philip C. Youngs, and the hearing officer granted the motion, finding that the principles of res judicata and collateral estoppel barred relitigation of the issue of the reasonableness of Edison’s expenditures since, in case number U-6488, the commission had found the costs to be reasonable. Plaintiff filed an application for leave to appeal to the commission. On November 23, 1982, the commission granted plaintiff’s application for leave to appeal, and ruled that Pennwalt should be allowed to present new evidence or evidence of changed *5 circumstances relevant to the reasonableness of Edison’s expenditures. After the testimony and exhibits of Youngs were presented, the commission issued its opinion and order on March 31, 1983, holding that Edison’s expenditures were reasonable and that the entire expenditures could be used in formulating Edison’s rate base. In so holding, the commission stated:

The burden of proof throughout the reopened proceeding was on Pennwalt to bring forth new evidence or changed circumstances which would show the unreasonableness of the Commission’s decision in Case No. U-6488. . . .
After reviewing the supplemental record and the briefs and exceptions in this matter, the Commission finds that Pennwalt has not met its burden of proof. Pennwalt has not introduced new evidence or changed circumstances to persuade the Commission that its original decision in Case No. U-6488 was unreasonable regarding the Pennsalt[ 2 ] Waste-water Treatment Facility’s costs. . . .
. . . The new alternatives presented by Pennwalt do not fall into the category of either new evidence or changed circumstances. . . .
. . . Pennwalt has not carried its burden of introducing evidence to show changed circumstances which cause the Commission’s previous action to be unreasonable.
The Commission does not address specifically each of Pennwalt’s exceptions because they do not address the issue at hand. The Commission therefore summarily rejects those exceptions. Based on the discussion above, the Commission finds that Applicant’s costs for the Pennsalt Wastewater Treatment Facility are reasonable. For all future proceedings, this item is found to be a legitimate expense, and any party wishing to contest it must *6 bear the burden of bringing forth new evidence or changed circumstances.

Plaintiff appealed to the Ingham Circuit Court. The circuit court affirmed, stating:

At pages 117-118 of its March 31, 1983 Opinion Order in U-6949, the Comission found Pennwalt failed to carry its burden of introducing new evidence to persuade the Commission that its decision in U-6488 was unreasonable. The Commission found the alternatives presented by Mr. Young [sic] on the reopened record were neither new evidence nor evidence of changed circumstances. The Court agrees.
* * *
In reaching this decision, the Court finds it is of particular import that Edison’s construction investment in the wastewater treatment facility at the Pennsalt Power Plant was a fixed past event on July 21, 1981 when the Commission issued its order in U-6488. Pennwalt alleges no events since that time which make that order unreasonable. Although each element of a utility rate is generally subject to challenge, the Court holds that a fixed past event such as this construction project, once determined reasonable, is susceptible to later challenge only upon a showing of new evidence or changed circumstances. Therefore, the Commission properly shifted the burden to Pennwalt in the reopened proceeding. Pennwalt failed to meet this burden.

On appeal, plaintiff first claims that, in case number U-6949, the commission and the trial court erred in placing the burden on plaintiff to bring forth new evidence or evidence of changed circumstance to establish that Edison’s expenditures in constructing the wastewater treatment facility were unreasonable. Plaintiff contends that the burden should have remained on Edison to *7 prove that its costs were reasonable. Edison, on the other hand, argues that the doctrines of res judicata and collateral estoppel should have barred plaintiff from relitigating the reasonableness of the expenditures and that, by allowing the plaintiff to relitigate the question of reasonableness by permitting the admission of new evidence or evidence of changed circumstances, the commission and the court gave plaintiff even more rights than plaintiff was entitled to.

The duties of the Michigan Public Service Commission are set forth at MCL 460.1 et seq.; MSA 22.13(1) et seq. The commission is given broad discretionary power to set just and reasonable rates for privately owned public utilities. Attorney General v Public Service Comm,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Detroit Edison Co.
296 Mich. App. 101 (Michigan Court of Appeals, 2012)
In re Consumers Energy Co.
291 Mich. App. 106 (Michigan Court of Appeals, 2010)
Consumers Energy Co. v. Public Service Commission
707 N.W.2d 633 (Michigan Court of Appeals, 2005)
VanWulfen v. Montmorency County
345 F. Supp. 2d 730 (E.D. Michigan, 2004)
Consumers Power Co. v. Public Service Commission
493 N.W.2d 902 (Michigan Court of Appeals, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
420 N.W.2d 156, 166 Mich. App. 1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pennwalt-corp-v-public-service-commission-michctapp-1988.