Consumers Power Co. v. Public Service Commission

493 N.W.2d 902, 196 Mich. App. 436
Michigan Court of Appeals·Decided October 20, 1992·No. NO 1; Docket 136361, 139592, 139593·Published·Cited by 6 cases

Opinion

*440 Per Curiam.

Consumers Power Company appeals as of right, and the Midland Cogeneration Venture Limited Partnership (mcv) and the Attorney General cross appeal as of right, a number of orders of the Public Service Commission regarding Consumers’ 1990 and 1991 power supply cost recovery (pscr) plans and factors.

On September 10, 1987, the mcv filed with the psc an application for approval of capacity charges in a contract for the sale of electricity to Consumers. The application stated that the mcv intended to construct and operate a gas-fired cogeneration plant in Midland, Michigan, to supply steam and electricity to Dow Chemical Company and to sell electricity to Consumers. It was docketed as Case No. U-8871. The psc consolidated the mcv’s application with other applications and complaints, invited additional submissions, and used the consolidated case to implement the federal Public Utility Regulatory Policies Act of 1978 (purpa), PL 95-617, 92 Stat 3117. Section 210 of the purpa, 16 USC 824a-3, encourages the development of alternative power sources in the form of cogeneration and small power production facilities. The purpa defines a "cogeneration facility” as one that produces both electric energy and some other form of useful energy, such as steam or heat. Pursuant to the purpa, the Federal Energy Regulatory Commission (ferc) promulgated rules to encourage development of alternative sources of power, including rules requiring utilities to offer to buy electricity from, and to sell electricity to, qualifying cogeneration and small power production facilities (qfs).

The contested case hearings regarding the consolidated applications of the mcv and other qfs were lengthy. Sixty parties and more than one hundred witnesses participated in the hearings.

*441 The psc issued a series of orders in that case from January 31, 1989, until January 22, 1990. Those orders were the subject of a previous appeal as of right by Consumers, the mcv, the Attorney General, and other parties. In an opinion released on May 7, 1991, this Court held that the psc had properly exercised its authority in determining the avoided capacity cost that could be passed on to customers through the power supply cost reconciliation process required by 1982 PA 304 (Act 304), MCL 460.6j(12); MSA 22.13(6j)(12). This Court also held that the psc acted properly in determining future capacity needs, in determining the costs that would be avoided by using a hypothetical coal-fired facility, and in adopting a rate structure that would reflect the avoided costs over the term of the contract. However, the Court held that the psc exceeded its authority in limiting the percentage of avoided capacity that could be supplied by a single qf and in limiting the percentage that could be produced from a single fuel source. It was found that Consumers properly could have contracted with the mcv to have its entire projected capacity supplied from the mcv facility, and the psc should have approved that contract if the negotiated price was no more than the projected avoided capacity costs on the day the contract was signed. Because of certain unresolved factual issues, this Court remanded to the psc for further proceedings. Consumers Power Co v Public Service Comm, 189 Mich App 151; 472 NW2d 77 (1991).

Meanwhile, on September 29, 1989, Consumers filed an application for approval of its 1990 pscr plan, factors, and forecast, covering the plan year 1990 and the five-year forecast for 1990-94, as required by §§ 6j(3) and (4) of Act 304. It was docketed as psc Case No. U-9432. Consumers sought approval of a .652 cents/kwh (kilowatt *442 hour) pscr factor for each month in 1990 reflecting purchases of generating capacity from qfs, including the mcv at a rate of 4.15 cents/kwh paid on the basis of availability. The Attorney General was allowed to intervene and filed a motion for partial summary disposition and for approval of temporary factors, requesting the psc to issue a temporary order authorizing a maximum pscr factor of negative .304 cents/kwh. The psc staff joined in the Attorney General’s motion. On December 21, 1989, the psc granted the motion and issued a temporary order finding that the appropriate temporary pscr factor for Consumers to use in billing its customers was negative .304 cents/kwh. The psc further held that upon the commercial operation date of any qf, including the mcv, Consumers could implement a pscr factor consistent with the psc’s findings in Case No. U-8871.

Consumers appealed as of right the psc’s December 21, 1989, temporary order, contending only that the psc improperly issued a temporary order without holding evidentiary hearings. This Court disagreed, holding that the psc did not err in relying upon evidentiary hearings in Case No. U-8871 to fulfil the requirement that parties be given a reasonable opportunity for a full and complete hearing in connection with any temporary orders. Consumers Power Co v Public Service Comm, 192 Mich App 180, 186; 481 NW2d 1 (1991).

On the same day that the psc issued the temporary order in Case No. U-9432, December 21, 1989, it issued an order in Case No. U-8871 holding that for purposes of § 6j(13)Cb) of Act 304, the psc would approve average capacity charge payments by Consumers to the mcv at the rate of 3.77 cents/kwh, and not the 4.15 cents/kwh agreed to by Consumers and the mcv in their contract. In addition, the psc held that this capacity charge would be "back- *443 loaded” for a period of 17.5 years, so that capacity charge payments in the first year would equal only 2.26 cents/kwh. 1

Several parties moved to strike virtually all of Consumers’ testimony and exhibits in Case No. U-9432 regarding its planned purchases of capacity from the mcv, arguing that the findings in Case No. U-8871 were controlling. The hearing referee granted these motions. Consumers then filed testimony to support a pscr factor of 2.26 cents/kwh, i.e., the average backloaded capacity charge approved by the psc in Case No. U-8871. This resulted in a reduction of the projected power supply costs for purchases of energy and capacity from the mcv in Consumers’ 1990 pscr plan from $371,-832,920 to $230,798,345. However, the psc staff argued that the. projected pscr factor for 1990 should be reduced even further, inasmuch as Consumers never submitted a revised contract with the mcv for psc approval, as required by one or more orders in Case No. U-8871. The staff argued that capacity charges paid by Consumers to the mcv should not be paid on the basis of availability, but rather on the basis of energy actually delivered. The hearing referee agreed and reduced the projected power supply costs for purchases of energy and capacity from the mcv by an additional $36,038,318.

Free access — add to your briefcase to read the full text and ask questions with AI

Consumers Power Co. v. Public Service Commission, 493 N.W.2d 902, 196 Mich. App. 436 (Mich. Ct. App. 1992).

493 N.W.2d 902 (Consumers Power Co. v. Public Service Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Abate v. Psc
216 Mich. App. 8 (Michigan Court of Appeals, 1996)
Residential Ratepayer Consortium v. Public Service Commission
497 N.W.2d 558 (Michigan Court of Appeals, 1993)
Trumble’s Rent-L-Center, Inc v. Employment Security Commission
495 N.W.2d 180 (Michigan Court of Appeals, 1992)