Abate v. Psc

216 Mich. App. 8
CourtMichigan Court of Appeals
DecidedMarch 19, 1996
DocketDocket Nos. 163930, 165005, 165713
StatusPublished
Cited by1 cases

This text of 216 Mich. App. 8 (Abate v. Psc) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Abate v. Psc, 216 Mich. App. 8 (Mich. Ct. App. 1996).

Opinion

216 Mich. App. 8 (1996)

ASSOCIATION OF BUSINESSES ADVOCATING TARIFF EQUITY
v.
PUBLIC SERVICE COMMISSION
ATTORNEY GENERAL
v.
PUBLIC SERVICE COMMISSION

Docket Nos. 163930, 165005, 165713.

Michigan Court of Appeals.

Submitted August 10, 1995, at Lansing.
Decided March 19, 1996, at 9:05 A.M.

Hill Lewis (by Roderick S. Coy and Timothy P. Collins), for Association of Businesses Advocating Tariff Equity.

Frank J. Kelley, Attorney General, Thomas L. Casey, Solicitor General, and Luis F. Fernandez, Larry F. Brya, and Robert L. Mol, Assistant Attorneys General, for the Attorney General.

Don L. Keskey and Henry J. Boynton, Assistant Attorneys General, for the Public Service Commission.

Loomis, Ewert, Ederer, Parsley, Davis & Gotting, P.C. (by William D. Parsley, Harvey J. Messing, and Gary L. Field), and David A. Mikelonis and Jon R. Robinson, for Consumers Power Company.

Conner & Bentley, P.C. (by Pat D. Conner), and Robert C. Evans, for Michigan Cogeneration Partners.

Foster, Swift, Collins & Smith, P.C. (by Stephen O. Schultz and Steven H. Lasher), for Midland Cogeneration Venture Limited Partnership.

Fraser Trebilcock Davis & Foster, P.C. (by David E.S. Marvin and Thomas J. Waters), for Dow Chemical Company, Grand River Equities, Indeck Energy Services of Otsego, Inc., and Michigan Power Limited Partnership.

*11 Before: MARILYN KELLY, P.J., and CORRIGAN and C.D. STEPHENS,[*] JJ.

MARILYN KELLY, P.J.

This dispute began more than five years ago and now occupies over 19,000 pages of testimony and more than 500 exhibits presented at hearings before the Michigan Public Service Commission (MPSC). In Docket Nos. 163930 and 165713, appellant Association of Businesses Advocating Tariff Equity (ABATE) appeals from MPSC orders entered on March 31, 1993 and May 26, 1993 deciding issues on remand and denying rehearing, respectively. In Docket No. 165005, appellant Attorney General (AG) appeals from the same orders. We affirm.

THE BACKGROUND OF THE APPEALS

In 1978, Congress enacted the National Energy Act, which was designed to combat the nationwide energy crisis. Part of the Act is known as the Public Utility Regulatory Policies Act. Section 210 of the Act, found at 16 USC 824a-3, was designed to ease the crisis by encouraging the development of small power production facilities. Section 210(a) directed the Federal Energy Regulatory Commission to promulgate regulations requiring utilities to buy electricity from qualifying cogeneration and small power production facilities (QFS). Under the Commission's regulations, particularly 18 CFR 292.304, utilities are required to purchase power from QFS at full "avoided cost." Avoided cost is the cost to a utility of energy or capacity, or both, which the utility would have generated for itself or purchased from another facility but for the purchase from the QF. Avoided cost is defined *12 as either avoided energy or avoided capacity costs. The former is the cost associated with the production of energy. The latter is the cost associated with providing the capability to deliver energy.

The Midland Cogeneration Venture (MCV) is a limited partnership formed for the purpose of constructing and operating a gas-fired cogeneration plant. On September 10, 1987, MCV filed an application with the MPSC for approval of capacity charges in a contract for the sale of electricity to Consumers Power Company (CP). The MPSC docketed MCV'S application as Case No. U-8871, and consolidated it with other applications from QFS and complaints against CP.

In an interim order issued on January 31, 1989, the MPSC made the finding that CP needed a QF capacity of 1,290 megawatts (MW), but reduced that figure out of caution to 1,160 MW. The MPSC based this figure on a projected 1997 need, as determined by a coal-fired plant model, called a proxy. The MPSC determined that CP was entitled to recover from ratepayers an avoided capacity rate of 3.77 cents per kilowatt hour (kWh). The payments would be backloaded, i.e., reduced at the beginning and increased at the end of the project. The MPSC gave CP ninety days to negotiate and sign contracts with its QFS.

In the appeals before us, CP, MCV, the AG, ABATE and other parties appealed as of right from the MPSC's series of orders. In Consumers Power Co v Public Service Comm[1] (Consumers Power I), this Court affirmed in part and reversed in part the MPSC's orders. We held that the MPSC properly exercised its authority acting pursuant to MCL 460.6j; MSA *13 22.13(6j). It appropriately determined the avoided capacity cost which could be passed on to ratepayers, the future capacity needs, the avoided costs using a hypothetical coal-fired facility and a rate structure. We found that clear and satisfactory evidence supported the use of a hypothetical coal-fired plant to determine CP's future avoided capacity costs.

We also found that the determination that 1,160 MW of new capacity would be needed in the future was supported by the evidence. We ruled that the avoided capacity charge adopted by the MPSC was supported by the evidence. We stated that the MPSC should deny approval of CP's contract with MCV only if the negotiated rate of 4.15 cents/kWh exceeded the avoided capacity cost when the agreement was signed. We then remanded the case to the MPSC for a determination of the avoided capacity cost on the date the contract was signed. We directed that the MPSC clarify whether all factors contained in 18 CFR 292.304(e) were considered in setting avoided cost.

In March, 1990, MCV began selling power under the unapproved 1987 contract with CP. CP filed a series of annual power supply cost recovery cases. In a temporary order dated December 21, 1989, the MPSC limited CP's power supply cost recovery charges to the backloaded QF rate established in Case No. U-8871. In Consumers Power Co v Public Service Comm,[2] this Court affirmed the temporary order. In a series of other orders, the MPSC limited CP's authorized charges to 3.77 cents/kWh, and allowed CP to charge only for energy actually delivered, not for all available capacity. Various parties appealed as of right.

*14 In Consumers Power Co v Public Service Comm No 1,[3] this Court affirmed those orders. We held that the MPSC was not required to accept new evidence regarding the reasonableness and prudence of the capacity charges in the contract between CP and MCV. Rather, the MPSC was entitled to rely on evidence produced in Case No. U-8871, where those issues had been litigated.

THE REVISED SETTLEMENT PROPOSAL

Pursuant to the remand in Consumers Power I, supra, CP, ABATE and the MPSC staff filed a joint stipulation in a number of cases, including Case No. U-8871. The MPSC rejected the stipulation on the basis that it allowed CP to pick and choose among the findings in Case No. U-8871. Following the rejection of the stipulation, the MPSC instructed its staff to attempt to negotiate a settlement. On September 8, 1992, CP, the MPSC staff and several QFS filed a revised settlement proposal. The case was docketed as Case No. U-10127.

The MPSC held a contested case hearing in Case No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Western Resources, Inc. v. Kansas Corporation Comm'n
42 P.3d 162 (Court of Appeals of Kansas, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
216 Mich. App. 8, Counsel Stack Legal Research, https://law.counselstack.com/opinion/abate-v-psc-michctapp-1996.