Attorney General v. Public Service Commission 2

350 N.W.2d 320, 133 Mich. App. 790
CourtMichigan Court of Appeals
DecidedApril 17, 1984
DocketDocket No. 68813
StatusPublished
Cited by8 cases

This text of 350 N.W.2d 320 (Attorney General v. Public Service Commission 2) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Attorney General v. Public Service Commission 2, 350 N.W.2d 320, 133 Mich. App. 790 (Mich. Ct. App. 1984).

Opinion

Per Curiam:.

The Attorney General appeals as of right from the December 13, 1982, order of Ingham County Circuit Court Judge Robert Holmes Bell which affirmed three Michigan Public Service Commission (commission) orders allowing Detroit Edison Company rate increases pursuant to the "System Availability Incentive Provision” (SAIP).

The purpose of the challenged increase was to encourage Edison to improve the availability of its electric generating units.

The SAIP was first established in MPSC Case No. U-5108, by order dated May 27, 1977. After 85 days of hearings before the commission concerning Edison’s rate base, rate of return, adjusted net [793]*793operating income, revenue deficiency, rate design, and service rules, and after comments from parties, staff, and the hearing referee, the commission made the following findings:

"High system availability is crucial to the ability of applicant to provide its customers with reliable service at low cost. The commission believes that a specific incentive will encourage applicant to make the required extra effort to achieve the maximum system availability. If high levels of availability are achieved, the savings to customers should exceed the increased equity return. Conversely, if applicant’s system availability falls unreasonably low, applicant should bear some of the resulting increased costs.
"The commission therefore finds that the staff’s proposal that the commission establish a system availability incentive provision is reasonable and should be adopted for jurisdictional electric retail service customers.
"The commission finds that system availability should . be determined on a calendar year basis using the East Central Area Reliability method.”

The commission based its conclusion on the testimony of staff witness Fischer:

"Staff witness Fischer proposed the establishment of an incentive provision to encourage applicant to improve the availability of its electric generating units. Unit availability is the fraction of a total time period during which an electric generating unit is capable of producing electricity. A unit may be available or only partially available because of scheduled maintenance or because of an unscheduled, forced reduction of generating capability. Mr. Fischer stated that ideally, considering required preventive maintenance, a generating unit should be available at full capacity about 85% of the time. An electric system with a high availability of its generating units has relatively lower customer bills in the short and long run than a system with low availa[794]*794bility. High availability of low cost generating units reduces fuel and purchased power costs which results immediately in lower customer bills. Over the long run, sustained high availability reduces the reserve requirements, which also reduces customer bills.”

The commission set forth the procedure as follows:

"The commission finds that the record in this proceeding should be kept open for the receipt of evidence and the adjustment of rates, if any be necessary, according to the following procedure:
"During the first week in April of each year, applicant should file prepared testimony and supporting exhibits setting forth the average system availability for the preceding calendar year. As soon as practicable after the filing of applicant’s material, there should be hearings for the purpose of cross-examination of applicant’s witnesses. The staff should perform an engineering review of applicant’s system availability during the period in question and place a report on the record. After the close of the hearing, the administrative law judge should make a report and recommendation. After reviewing the record, the commission shall determine whether applicant’s authorized rate of return will remain unchanged, or be altered in accordance with the scale established below. If there is either an increase or decrease in the authorized rate of return, the rates should be adjusted to accomplish the change, using the capital structure and other pertinent rate calculation elements found to be proper in this opinion and order. The rates should be adjusted an appropriate number of mills per kWh based on sales during the calendar year in question.
"The positive element of the incentive provision scale should be low enough to be achievable by applicant, but not so low as to virtually guarantee an increased rate of return. The negative element should be high enough to be meaningful but not so high as to ensure a reduction in applicant’s return.
[795]*795"The commission finds the following scale to be reasonable:
"Annual Average System Availability
0 -70%
70.1- 80%
80.1- 85%
85.1 -100%
Equity Return Incentive Adjustment
-.25%
-0-%
+.25%
+ .50%”

No appeal was taken from this order in MPSC Case No. U-5108 which originally established the SAIP for Edison. Appeals from three commission orders implementing the SAIP for the years 1978, 1979, and 1980 were consolidated in the circuit court. On December 13, 1982, Ingham County Circuit Court Judge Robert Holmes Bell affirmed the commission’s ruling by opinions and order. The Attorney General now appeals to this Court.

The Attorney General argues on appeal that the SAIP violates several regulatory statutes.

Appellate review of Public Service Commission orders is narrow in scope. Under MCL 462.25; MSA 22.44, all rates, fares, charges, classification and joint rates, regulations, practices, and services prescribed by the commission are deemed, prima facie, to be lawful and reasonable. Michigan Consolidated Gas Co v Public Service Comm, 389 Mich 624; 209 NW2d 210 (1973); Consumers Power Co v Public Service Comm, 65 Mich App 73; 237 NW2d 189 (1975); Attorney General v Public Service Comm, 122 Mich App 777, 796; 333 NW2d 131, lv den 418 Mich 886 (1983). The person attacking an order of the commission must prove by clear and satisfactory evidence that the order complained of is unlawful or unreasonable. MCL 462.26; MSA 22.45; Lansing v Public Service Comm, 330 Mich 608; 48 NW2d 133 (1951); Michigan Bell Telephone Co v Public Service Comm, 85 Mich App 163; 270 [796]*796NW2d 546 (1978); Attorney General v Public Service Comm, supra, pp 796-797.

Although not specifically authorized by statue or case law, the establishment of the System Availability Incentive Provision comes within the commission’s statutory power.

The public service commission act confers broad discretion and authority upon the Public Service Commission. The act provides, in part, that:

"(1) The public service commission is vested with complete power and jurisdiction to regulate all public utilities in the state except a municipally owned utility, the owner of a renewable resource power production facility as provided in section 6d, and except as otherwise restricted by law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Detroit Edison Co. v. Public Service Commission
562 N.W.2d 224 (Michigan Court of Appeals, 1997)
Abate v. PSC
522 N.W.2d 140 (Michigan Court of Appeals, 1994)
Consumers Power Co. v. Public Service Commission
472 N.W.2d 77 (Michigan Court of Appeals, 1991)
Ass'n of Businesses Advocating Tariff Equity v. Public Service Commission
173 Mich. App. 647 (Michigan Court of Appeals, 1988)
Attorney General v. Public Service Commission
141 Mich. App. 505 (Michigan Court of Appeals, 1984)
Attorney General v. Public Service Commission 2
358 N.W.2d 351 (Michigan Court of Appeals, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
350 N.W.2d 320, 133 Mich. App. 790, Counsel Stack Legal Research, https://law.counselstack.com/opinion/attorney-general-v-public-service-commission-2-michctapp-1984.