Abate v. PSC

527 N.W.2d 533, 208 Mich. App. 248
Michigan Court of Appeals·Decided December 29, 1994·No. Docket Nos. 141277, 141284, 142119, 142493·Published·Cited by 24 cases

Opinion

208 Mich. App. 248 (1994)
527 N.W.2d 533

ASSOCIATION OF BUSINESSES ADVOCATING TARIFF EQUITY
v.
PUBLIC SERVICE COMMISSION

Docket Nos. 141277, 141284, 142119, 142493.

Michigan Court of Appeals.

Submitted October 19, 1994, at Lansing.
Decided December 29, 1994, at 9:30 A.M.

Hill Lewis (by Roderick S. Coy, Timothy P. *250 Collins, and Joseph R. Assenzo), for the Association of Businesses Advocating Tariff Equity.

David A. Mikelonis, James E. Brunner, and H. Richard Chambers, and Loomis, Ewert, Ederer, Parsley, Davis & Gotting, P.C. (by Michael G. Oliva and Ronald W. Bloomberg), for Consumers Power Company.

Don L. Keskey, Henry J. Boynton, Philip J. Rosewarne, and Patricia S. Barone, Assistant Attorneys General, for the Public Service Commission.

Frank J. Kelley, Attorney General, Thomas L. Casey, Solicitor General, and Luis F. Fernandez and Paul E. Novak, Assistant Attorneys General, for the Attorney General.

Before: NEFF, P.J., and MARILYN KELLY and P.R. JOSLYN,[*] JJ.

PER CURIAM.

These four consolidated appeals as of right, MCL 462.26; MSA 22.45, are from a May 7, 1991, decision of the Public Service Commission (PSC) and a July 1, 1991, PSC decision denying petitions for rehearing. The PSC case, No. U-7830 Step 3B, involved a request by Consumers Power Company for rate relief of over $2 billion. The PSC found that Consumers was entitled to about $760 million of rate relief. After certain offsets, the net award was about $346 million, to be collected over ten years and without interest. We affirm.

I

Consumers filed an application for an electric *251 rate increase on November 18, 1983, No. U-7830, seeking to recover costs related to the development and construction of a two-unit, 1,300 megawatt, nuclear power plant at Midland, Michigan. Plans for the plant were announced in 1967. Consumers canceled the project on July 16, 1984. According to Consumers, the plant was then eighty-five percent complete and Consumers had invested approximately $4.2 billion in the project.

Construction of the nuclear facility was fraught with difficulties and delay. One witness characterized the cost to remedy a problem of improperly compacted soil as equivalent to paying for a third reactor. The Atomic Energy Commission and subsequently the Nuclear Regulatory Commission (NRC) maintained oversight of the project. The NRC found serious quality assurance and quality control problems. In the aftermath of the accident at Three Mile Island in Pennsylvania on March 19, 1979, federal authorities increased their regulatory vigilance.

At its inception, the Midland project was a joint venture of Consumers and Dow Chemical Company. Dow's eventual financial stake in the project amounted to about $500 million. Consumers and Dow negotiated a contract in June 1978 that permitted Dow to walk away from the project without liability unless both nuclear units were in commercial operation by December 31, 1984. This date became known as the "drop dead" date.

The architect, engineer, and primary contractor for the project, Bechtel Power Corporation, prepared analyses known as "forecasts" regarding the course of the project to completion. In late 1979 or early 1980, Bechtel developed "Forecast 6." It forecast the "most probable fuel load dates" for Unit 2 to be in April 1984 and for Unit 1 to be in September 1984. It was highly unlikely that these *252 load dates would permit commercial operation of both the reactors by the drop dead date.

In February 1980, Consumers and Bechtel tried to improve the construction schedule in order to allow for a November 1983 load date. However, a review team made up of Consumers' personnel did not seriously question the conclusions in Forecast 6, but concluded that a November 1983 load date was as "aggressive" a plan as could be realistically pursued.

At a March 5, 1980, meeting of Consumers' directors, management presented Forecast 6 as well as a "breakeven study" and a study regarding alternatives for the project known as the "Midland Alternatives Study." A virtual doubling in the expected cost of the plant was explained to the directors in March 1980. The directors approved a resolution authorizing the company to proceed with construction of both units in accordance with the Forecast 6 estimates.

A revised version of Forecast 6 was issued by Consumers' review team on May 5, 1980. The report characterized a November 1983 fuel load date as "very optimistic." A "schedule analysis" prepared by June 1980 gave a ten percent probability of loading fuel by November 1983 (given favorable assumptions), a fifty percent probability of loading fuel by February 1984, and a ninety percent probability of loading fuel by April 1984.

At a board meeting on July 2, 1980, Consumers' directors considered revised Forecast 6 and the review team's analyses. There was also discussion of potential problems with federal regulatory approval. Management recommended adopting a schedule that anticipated loading fuel in July and December 1983. The directors adopted the recommendation.

After July 1980, the project continued to experience *253 difficulties, some regulatory and some financial. In December 1982, federal authorities ordered a partial halt to construction because of quality assurance problems. Apparently no further significant construction occurred. Dow withdrew from the project in July 1983. On July 16, 1984, Consumers' directors halted construction completely.

II

Shortly after Consumers ceased construction on the plant, it filed an amendment to its pending electric rate application in No. U-7830 seeking to recover its entire investment in the Midland project. Although Consumers claimed a cost of over $4 billion, its request was eventually reduced to about $2.1 billion, for various reasons. Consumers sought relief in three steps. Step 3 initially sought several hundred million dollars for the cost of the project. Step 3 was subsequently divided into Steps 3A and 3B, with Step 3A being a request for several hundred million dollars of immediate rate relief known as "financial stabilization" relief because of Consumers' precarious financial situation. This appeal deals with Step 3B, in which Consumers sought relief for the balance of its investment in the Midland project.

This Court previously affirmed the PSC'S decision in Step 2, Consumers Power Co v Public Service Comm No 1, unpublished opinion per curiam of the Court of Appeals, decided January 14, 1991 (Docket Nos. 102652, 103983, 105990, and 117930). The PSC'S decision in Step 3A was also affirmed. Attorney General v Public Service Comm, 189 Mich App 138; 472 NW2d 53 (1991) [Attorney General I].

The proceeding in this case, Step 3B, involved three hundred days of hearings and resulted in a *254 record of about 39,000 pages of testimony and 2,400 accepted exhibits. The hearing referee recommended rate relief of $1.3 billion based on project costs incurred until December 2, 1982. This recommendation was consistent with the position of the PSC staff.

The PSC found that Consumers' decision on July 2, 1980, to go forward with construction of both units with the expectation that fuel would be loaded in 1983 was so unrealistic that Consumers acted imprudently at that time. The PSC concluded th

Free access — add to your briefcase to read the full text and ask questions with AI

Abate v. PSC, 527 N.W.2d 533, 208 Mich. App. 248 (Mich. Ct. App. 1994).

527 N.W.2d 533 (Abate v. PSC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

People of Michigan v. Brenton Tyler Spaulding
Michigan Court of Appeals, 2020
Nicola Binns v. City of Detroit
Michigan Court of Appeals, 2018
In Re Application of Mich. Con. Gas Co.
761 N.W.2d 482 (Michigan Court of Appeals, 2008)
In re Consumers Energy Co.
279 Mich. App. 180 (Michigan Court of Appeals, 2008)
United States v. Michigan
483 F. Supp. 2d 565 (E.D. Michigan, 2007)
Attorney General v. PSC
686 N.W.2d 804 (Michigan Court of Appeals, 2004)
Attorney General v. Public Service Commission
686 N.W.2d 804 (Michigan Court of Appeals, 2004)
Detroit Edison Co. v. PUBLIC SERVICE COM'N
683 N.W.2d 679 (Michigan Court of Appeals, 2004)
Detroit Edison Co. v. Public Service Commission No. 2
683 N.W.2d 679 (Michigan Court of Appeals, 2004)
Attorney General v. MPSC
618 N.W.2d 904 (Michigan Supreme Court, 2000)
Bolt v. City of Lansing
587 N.W.2d 264 (Michigan Supreme Court, 1998)
Consumers Power Co. v. Public Service Commission
572 N.W.2d 222 (Michigan Court of Appeals, 1997)
Bolt v. City of Lansing
561 N.W.2d 423 (Michigan Court of Appeals, 1997)