This text of 442 F. Supp. 2d 387 (Detroit Edison Co. v. Burlington Northern & Santa Fe Railway Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Detroit Edison Co. v. Burlington Northern & Santa Fe Railway Co., 442 F. Supp. 2d 387, 2006 U.S. Dist. LEXIS 38675, 2006 WL 2246172 (E.D. Mich. 2006).

Opinion

OPINION AND ORDER GRANTING DEFENDANT’S MOTION TO REFER CLAIMS TO ARBITRATION AND DENYING PLAINTIFFS’ MOTION FOR LEAVE TO AMEND COMPLAINT AND DISMISSING COMPLAINT

DUGGAN, District Judge.

On December 23, 2005, Plaintiffs filed this action against Defendant BNSF Railway seeking declaratory relief and damages for their claims of breach of contract, breach of contract based on custom, breach of implied covenant of good faith and fair dealing, and promissory estoppel. Presently before the Court are Defendant’s Motion to Stay Court Proceedings and to Refer Claims to Arbitration and Plaintiffs’ Motion for Leave to File First Amended Complaint. The Court heard oral arguments on these motions on May 4, 2006.

I. Background

Plaintiffs Detroit Edison and its corporate affiliates, Midwest Energy Resources Company, and DTE Coal Services, Inc., use rail services to move coal to industrial coal consumers and electric generation stations. Plaintiff Detroit Edison and Defendant BNSF entered into a Coal Transportation Agreement, BNSF-C-12152 (the “Agreement”), whereby BNSF agreed to transport coal from mines in Wyoming and Montana to the upper Midwest and for interchange to other rail carriers at Chicago, Illinois.

In their lawsuit, Plaintiffs allege that Defendant is obligated by the Agreement to furnish locomotives for the movement of Detroit Edison trains that remain with the *389 coal trains and “run through” 1 beyond the point where BNSF interchanges the trains with other rail carriers. (Compl.¶ 33). In addition, Plaintiffs contend that BNSF failed to fulfill its obligations with respect to interchange trains with other rail carriers at Chicago. (Compl.¶ 36).

The Agreement contains the following provision:

If a question or controversy arises between the parties concerning the observance, performance, interpretation, administration or implementation of any of the terms, provisions, or conditions contained herein or the rights or obligations of either party under this Agreement, such question or controversy shall in the first instance be the subject of a meeting between the parties to negotiate a resolution of such dispute. If, within thirty (30) days after the meeting, the parties have not negotiated a resolution or mutually extended the period of negotiation, either party may seek resolution of the question or controversy pursuant to binding arbitration.

(Def.’s Mot. Ex. 2, redacted Agreement § 9 at 40).

On February 15, 2006, Defendant filed a demand for arbitration to address the following issues: (1) whether the Agreement imposes an obligation upon BNSF to provide run-through locomotive power beyond the Interchange; and (2) the meaning of “Interchange” as defined in the Agreement. (Def.’s Mot. Ex. 3).

On February 23, 2006, Defendant filed its Motion to Stay Court Proceedings and to Refer Claims to Arbitration.

On March 17, 2006, Plaintiffs filed a Response in Opposition to Defendant’s Motion and Motion for Leave to Amend Complaint.

II. Applicable Law and Analysis

A. Defendant’s Motion to Stay Court Proceedings and to Refer Claims to Arbitration

Defendant moves to refer Plaintiffs’ claims to arbitration pursuant to the Federal Arbitration Act (“FAA”), 9 U.S.C. §§ 2 and 3. The FAA requires arbitration if: (1) there is an agreement with a nexus to interstate commerce that contains an arbitration clause, see 9 U.S.C. § 2; and (2) the arbitration clause covers the issues raised in the complaint, see 9 U.S.C. § 3. Section 4 of the FAA gives the court the authority to issue “an order directing that such arbitration proceed in the manner provided for in such agreement.” 9 U.S.C. § 4.

In adopting the FAA, Congress intended to create “a liberal federal policy favoring arbitration agreements.” Moses H. Cone Mem’l Hosp. v. Mercury Constr. Corp., 460 U.S. 1, 24, 103 S.Ct. 927, 941, 74 L.Ed.2d 765 (1983). Any doubts concerning whether arbitration is required are to be resolved in favor of arbitration. Id. at 24-25, 103 S.Ct. at 941. The Sixth Circuit has found:

When a contract contains an arbitration clause, there is a general presumption of arbitrability, and any doubts are to be resolved in favor of arbitration “unless it may be said with positive assurance that the arbitration clause is not susceptible of an interpretation that covers the asserted dispute”.... Where the arbitration clause is broad, only an express provision excluding a specific dispute, or *390 “the most forceful evidence of a purpose to exclude the claim from arbitration,” will remove the dispute from consideration by the arbitrators.

Highlands Wellmont Health Network, Inc. v. John Deere Health Plan, Inc., 350 F.3d 568, 576-77 (6th Cir.2003) (citing AT & T Techs., Inc. v. Communications Workers of Am., 475 U.S. 643, 650, 106 S.Ct. 1415, 1419, 89 L.Ed.2d 648 (1986)).

Plaintiff argues that the Court should deny Defendant’s Motion because the Agreement contains a permissive arbitration clause, which states that the parties “may seek resolution of the question or controversy pursuant to binding arbitration.” (Agreement § 9 at 40 (emphasis added)). According to Plaintiff, the use of the word “may” in the arbitration provision merely gives the parties the option of arbitrating the dispute, without foreclosing resolution of the dispute through litigation. The Court disagrees.

A number of courts have found that the word “may” in arbitration provisions does not make arbitration optional. See Mollett v. City of Taylor, 197 Mich.App. 328, 339, 494 N.W.2d 832, 837-38 (1992) (finding that a collective bargaining agreement containing a grievance clause providing that an employee “may” go before the commission did not give the employee the option to go to court or the commission, but rather, that the employee could go to the commission “or choose to do nothing at all”); see also Republic Steel Corp. v. Maddox, 379 U.S. 650, 658-59, 85 S.Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bryant v. Domino's Pizza Inc
E.D. Michigan, 2024
Tolbert v. COAST TO COAST DEALER SERVICES, INC.
789 F. Supp. 2d 811 (N.D. Ohio, 2011)
Pch Mut. Ins. Co., Inc. v. Casualty & Surety, Inc.
750 F. Supp. 2d 125 (District of Columbia, 2010)
PCH Mut. Ins. Co., Inc. v. CASUALTY & SUR., INC.
569 F. Supp. 2d 67 (District of Columbia, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
442 F. Supp. 2d 387, 2006 U.S. Dist. LEXIS 38675, 2006 WL 2246172, Counsel Stack Legal Research, https://law.counselstack.com/opinion/detroit-edison-co-v-burlington-northern-santa-fe-railway-co-mied-2006.