Delaware Riverkeeper Network v. Federal Energy Regulatory Commission

857 F.3d 388, 2017 WL 2231097, 84 ERC (BNA) 1629, 2017 U.S. App. LEXIS 8930
CourtCourt of Appeals for the D.C. Circuit
DecidedMay 23, 2017
Docket16-1092
StatusPublished
Cited by12 cases

This text of 857 F.3d 388 (Delaware Riverkeeper Network v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Delaware Riverkeeper Network v. Federal Energy Regulatory Commission, 857 F.3d 388, 2017 WL 2231097, 84 ERC (BNA) 1629, 2017 U.S. App. LEXIS 8930 (D.C. Cir. 2017).

Opinion

EDWARDS, Senior Circuit Judge:

This case involves three federal statutes: the Natural Gas Act (“NGA”), 15 U.S.C. § 717, et seq.; the Clean Water Act (“CWA”), formally titled the Federal Water Pollution Control Act Amendments of 1972, 33 U.S.C. § 1251, et seq.; and the National Environmental Policy. Act (“NEPA”), 42 U.S.C. § 4321, et seq. Although the Federal Energy Regulatory Commission (“FERC” or “Commission”) administers only the NGA, all three statutes apply to the disputed actions taken by the Commission in this case.

On September 30, 2013, Transcontinental Gas Pipe Line Company, LLC (“Tran-sco”) filed an application with FERC to construct and operate its proposed Leidy Southeast Project (“Leidy Project”). The project was designed to expand the capacity of Transco’s existing natural gas pipeline and add new facilities in Pennsylvania and New Jersey. Pursuant to the requirements of NEPA, FERC conducted an environmental review of the project and issued an environmental assessment (“EA”) on August 11, 2014. The EA found, with appropriate mitigating, measures, “no significant impacts” associated with the Leidy Project. However, it required Transco to obtain “all applicable authorizations required under federal law” prior to FERC authorizing construction. Because it was understood that the Leidy Project might result in discharges into navigable waters, Transco was obligated by § 401 of the CWA to obtain a water quality certification from the state in which the discharge would originate before FERC could authorize any activity that “may result” in such a discharge. See 33 U.S.C. § 1341(a)(1). The EA thus in turn required Transco to obtain this state certification before FERC would authorize any construction.

On June 10, 2014, Transco applied for a § 401 certification from Pennsylvania’s Department of Environmental Protection. On December 18, 2014, before Pennsylvania had acted on Transco’s application, *393 FERC issued a Certificate of Public Convenience and Necessity (“Certificate Order”) under the NGA conditionally approving the Leidy Project. The Certificate Order made it clear that FERC would not authorize any construction until Transco had obtained a § 401 certification from Pennsylvania. Delaware Riverkeeper Network, a nonprofit organization, timely sought rehearing of the Certificate Order before the Commission. FERC denied the request for rehearing. Delaware River-keeper Network and Maya van Rossum, the current Delaware Riverkeeper (together “Riverkeeper”), then petitioned for review in this court. Transco intervened in support of the Commission.

Before this court, Riverkeeper contends that the ■ Commission violated the CWA because it granted Transco’s request to construct and operate the Leidy Project prior to the issuance of Pennsylvania’s § 401 water quality certification. River-keeper also claims that the Commission violated NEPA in failing to establish an accurate baseline from which to conduct its environmental review of the Leidy Project. In particular, Riverkeeper argues that FERC misidentified numerous specially protected wetlands, and miscalculated both the cover type categorization of those wetlands and the total acreage of those wetlands. We find no merit in these claims and, therefore, reject the petition for review.

I. Background

A. Statutory Background

Under the NGA, a natural gas pipeline company must obtain a Certificate of Public Convenience and Necessity from FERC prior to “undertak[ing] the construction or extension” of any natural gas facility for the transportation of natural gas in interstate commerce. 15 U.S.C. § 717f(e)(l)(A). FERC may place any reasonable conditions on the issuance of such a certificate “as the public convenience and necessity may require.” Id. § 717f(e). This court has jurisdiction to review challenges to certificates granted under the NGA, but petitioning parties must first seek rehearing before the Commission and may not raise any argument before this court that was not raised on rehearing. See 15 U.S.C. § 717r(b). Letter orders issued by FERC are also subject to review in this court subject to the same rehearing requirement. See 18 C.F.R. § 385.1902.

In addition to the requirements of the NGA, § 401 of the CWA requires “[a]ny applicant for a Federal license or permit to conduct any activity including ... the construction or operation of facilities, which may result in any discharge into the navigable waters,” to “provide the licensing or permitting agency a certification from the State in which the discharge originates or will originate.” 33 U.S.C. § 1341(a)(1). The state must certify “that any such discharge will comply” with the CWA’s effluent limitations and other pollutant control requirements, including state-administered water quality standards. Id. The state may certify that there are no applicable limitations or standards for the discharge activity, or it may deny certification or waive the certification requirement. Id. But “[n]o license or permit shall be granted until the certification ... has been obtained or has been waived.” Id. Any limitation in a § 401 certification “shall become a condition” of the federal license or permit requiring such certification. Id. § 1341(d).

Section 401 is an important part of the CWA, in which “Congress sought to expand federal oversight of projects affecting water quality while also reinforcing the role of States as the prime bulwark in the effort to abate water pollution.” Alcoa Power Generating Inc. v. FERC, 643 F.3d 963, 971 (D.C. Cir. 2011) (citation and in *394 ternal quotation marks omitted). The state certification authority under § 401 is “ ‘[o]ne of the primary mechanisms’ through which [states] may exercise this role, as it provides them with ‘the power to block, for environmental reasons, local water projects that might otherwise win federal approval.’” Id. (quoting Keating v. FERC, 927 F.2d 616, 622 (D.C. Cir. 1991)).

The last statute at issue in this case is NEPA, which was enacted in part to “promote efforts which will prevent or eliminate damage to the environment and biosphere ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Steele v. United States
District of Columbia, 2023
DEP v. S. & E. Gerhart & Sunoco Pipeline, L.P.
Commonwealth Court of Pennsylvania, 2021
Hamed Almaqrami v. Michael Pompeo
933 F.3d 774 (D.C. Circuit, 2019)
Matter of National Fuel Gas Supply Corp. v. Schueckler
2018 NY Slip Op 7550 (Appellate Division of the Supreme Court of New York, 2018)
N.J. Conservation Found. v. Fed. Energy Regulatory Comm'n
353 F. Supp. 3d 289 (D. New Jersey, 2018)
Twp. of Bordentown v. Fed. Energy Regulatory Comm'n
903 F.3d 234 (Third Circuit, 2018)
Government of the Province of Manitoba v. Norton
273 F. Supp. 3d 145 (District of Columbia, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
857 F.3d 388, 2017 WL 2231097, 84 ERC (BNA) 1629, 2017 U.S. App. LEXIS 8930, Counsel Stack Legal Research, https://law.counselstack.com/opinion/delaware-riverkeeper-network-v-federal-energy-regulatory-commission-cadc-2017.