DeBry v. Cascade Enterprises

879 P.2d 1353, 242 Utah Adv. Rep. 17, 1994 Utah LEXIS 50, 1994 WL 316962
CourtUtah Supreme Court
DecidedJuly 1, 1994
Docket910216, 910284 and 910308
StatusPublished
Cited by33 cases

This text of 879 P.2d 1353 (DeBry v. Cascade Enterprises) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
DeBry v. Cascade Enterprises, 879 P.2d 1353, 242 Utah Adv. Rep. 17, 1994 Utah LEXIS 50, 1994 WL 316962 (Utah 1994).

Opinion

STEWART, Associate Chief Justice:

Plaintiffs Robert and Joan DeBry appeal from a jury verdict awarding the defendants $62,500 on a promissory note and $125,000 in punitive damages for fraudulent acts committed by the DeBrys. The defendants cross-appeal.

I. FACTS

The plaintiffs purchased an office budding constructed by defendant Cascade Construction Company, a general partnership, whose partners are Del Bartel, Dale Thurgood, and Lee Bartel. The budding was sold to the plaintiffs by Cascade Enterprises, a general partnership, whose sole partners are Del Bartel ánd Dale Thurgood. Both partnerships and all the partners were named defendants.

The DeBrys executed an earnest money agreement to purchase the office budding whde the budding was stdl under construction. The parties closed the sale on December 13, 1986, even though the budding was not finished and the parties disagreed about the quality of the workmanship and the cost of additions and changes made to the original building plans.

On December 10, 1985, the parties executed a nonmerger and escrow agreement that provided for the DeBrys to execute a promissory note in the amount of $62,500 in favor of Dale Thurgood and Del Bartel. The note, secured by a trust deed, represented part of the purchase price and was to be placed in escrow. The note stated that it was subject to “that certain Escrow Agreement dated December 10th, 1985.” According to the De-Brys, the note was intended to fund a two-year warranty on workmanship and materials by the defendants and “to provide a fund out of which unresolved matters concerning credits, allowances, and extras [could] be resolved.” However, a document entitled “Escrow Instructions,” also dated December 10, 1985, stated that the note and trust deed were to be held as security to guarantee that the defendants would clear any mechanic’s liens recorded against the property. The escrow instructions provided that the note and trust deed would be transferred to the defendants when the lien period expired if no *1356 hens had been filed on the property. Dale Thurgood and Del Bartel assigned the note and trust deed to Utah Title to be held in escrow. After ninety days; Utah Title returned the original note and deed to the defendants but did not reassign those documents.

Prior to closing, the defendants obtained a temporary thirty-day occupancy permit from Salt Lake County. The permit was issued with the understanding that the building would be completed and brought into compliance with the uniform building code before the temporary permit expired. After closing, the DeBrys discovered that the County had no record of having issued a bufiding permit to the defendants. The County later refused to issue a permanent occupancy permit because the defendants had not obtained a building permit and the building did not comply with the uniform building code. The DeBrys discharged the defendants and hired other contractors to complete the work. Eventually, the County ordered the DeBrys to vacate the building because it was not in compliance with the building code.

The DeBrys sued Cascade Enterprises, Cascade Construction, Thurgood, and Del and Lee Bartel for negligence, breach of warranty, breach of contract, and fraud in constructing the building. 1 Cascade Enterprises, Thurgood, and Del Bartel counterclaimed, alleging that the promissory note held in escrow was due and owing and that the DeBrys had committed fraud against them. The defendants retained counsel to represent them during the first eleven months of the lawsuit. Because it became apparent to the defendants that the litigation would be protracted and prohibitively expensive, they discharged their attorneys. The trial court ruled that Thurgood and Bartel could not represent the partnerships. Thereafter, Thurgood and Del and Lee Bar-tel represented themselves and their respective partnership interests.

Largely because of the manner in which the DeBrys and their attorneys have litigated this lawsuit, a relatively simple case has been transformed into an unnecessarily protracted and complicated lawsuit. In the four and a half years preceding trial, the DeBrys amended their complaint nine times, changed attorneys several times, caused one judge to be recused and moved twice to disqualify the trial judge who ultimately sat, obtained at least one continuance of the trial date, and filed numerous motions, many of them repetitive. The court file alone now contains twenty-eight volumes "with over 13,000 pages.

After a scheduling conference on August 19,1988, two and a half years after the initial complaint had been filed, the trial court issued a scheduling order directing the DeBrys to “designate their expert witnesses on or before January 2, 1989.” On October 12, 1988, the DeBrys filed a supplemental response to the defendants’ interrogatories, stating that the DeBrys “had retained [eleven experts] to assist plaintiffs in the litigation.” Their answer did not state which, if any, of the listed experts they intended to call as witnesses at trial. The DeBrys did not file any other document before January 2,1989, that could be construed as a designation of their expert witnesses.

In February 1989, the DeBrys moved to designate as “additional” expert witnesses contractors who had performed emergency repair work on the roof of the building after the January 2 deadline. The motion did not name the additional witnesses or any of the expert witnesses listed in the October supplemental answers to interrogatories. On May 4, 1989, three days after the date set by the court for the completion of discovery, the DeBrys filed a supplemental designation of witnesses, listing for the first time the names of the expert witnesses that they intended to call at trial. The document also requested permission to designate additional witnesses out of time.

In a February 1990 hearing, the trial judge ruled that the DeBrys could not call expert *1357 witnesses who had not been designated prior to the January 2,1989, deadline. Two weeks before trial, counsel for the DeBrys argued to the trial court that they had designated their expert witnesses in the supplemental answers to interrogatories filed in October 1988. The trial court held that the supplemental answers were not a proper designation and that if the DeBrys could not produce a clear written designation of expert witnesses that had been filed at least by the end of February 1989, they could not call their expert witnesses. On the second day of trial, the court again ruled that the DeBrys had not complied with the scheduling order and excluded all of the DeBrys’ expert witnesses.

After a thirty-day trial, the jury, by way of jury interrogatories, found that the defendants had breached an implied warranty to construct the building in compliance with the uniform building code and awarded $5,000 to the DeBrys for repairs already made and an additional $47,625 for future repairs, including $30,000 for masonry defects. The jury also found that the defendants negligently failed to comply with the uniform building code in constructing the building. The jury rejected the DeBrys’ claim that the defendants committed fraud on the DeBrys.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
D. Utah, 2026
Wakefield v. Gutzman
2024 UT App 76 (Court of Appeals of Utah, 2024)
Bad Ass Coffee v. Royal Aloha
2020 UT App 122 (Court of Appeals of Utah, 2020)
USA Power, LLC v. PacifiCorp
2016 UT 20 (Utah Supreme Court, 2016)
USA Power v. Pacificorp
2016 UT 20 (Utah Supreme Court, 2016)
Schreib v. Whitmer
2016 UT App 61 (Court of Appeals of Utah, 2016)
Brown v. Babbitt
2015 UT App 161 (Court of Appeals of Utah, 2015)
State ex rel. M.H. v. State
2014 UT 26 (Utah Supreme Court, 2014)
In re M.H.
2014 UT 26 (Utah Supreme Court, 2014)
R.O.A. General, Inc. v. Chung Ji Dai
2014 UT App 124 (Court of Appeals of Utah, 2014)
Warner v. Warner
2014 UT App 16 (Court of Appeals of Utah, 2014)
Farm Bureau Life Insurance v. American National Insurance
408 F. App'x 162 (Tenth Circuit, 2011)
Neff v. Neff
2011 UT 6 (Utah Supreme Court, 2011)
Lawrence v. INTERMOUNTAIN, INC.
2010 UT App 313 (Court of Appeals of Utah, 2010)
State v. Chavez-Espinoza
2008 UT App 191 (Court of Appeals of Utah, 2008)
Normandeau v. HANSON EQUIPMENT, INC.
2007 UT App 382 (Court of Appeals of Utah, 2007)
CLD Construction, Inc. v. City of San Ramon
16 Cal. Rptr. 3d 555 (California Court of Appeal, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
879 P.2d 1353, 242 Utah Adv. Rep. 17, 1994 Utah LEXIS 50, 1994 WL 316962, Counsel Stack Legal Research, https://law.counselstack.com/opinion/debry-v-cascade-enterprises-utah-1994.