Danny Ray Franks v. Roger Bilbrey

CourtCourt of Appeals of Tennessee
DecidedSeptember 30, 2022
DocketM2021-00766-COA-R3-CV
StatusPublished

This text of Danny Ray Franks v. Roger Bilbrey (Danny Ray Franks v. Roger Bilbrey) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Danny Ray Franks v. Roger Bilbrey, (Tenn. Ct. App. 2022).

Opinion

09/30/2022 IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE July 6, 2022 Session

DANNY RAY FRANKS, ET AL. v. ROGER BILBREY, ET AL.

Appeal from the Chancery Court for Overton County No. 2019-CV-49 Ronald Thurman, Chancellor

No. M2021-00766-COA-R3-CV

This appeal concerns an alleged breach of contract. Danny Ray Franks (“Mr. Franks”) and his spouse Angela May Franks (“Ms. Franks”) (“Plaintiffs,” collectively) hired Roger Bilbrey (“Mr. Bilbrey”) and Bilbrey’s Construction, Inc. (“Defendants,” collectively) to build a “barndominium,” a metal building that looks like a barn with a stained-concrete floor, garage, and living quarters. The parties’ contract (“the Agreement”), which was drafted by Mr. Bilbrey, provided that work would start immediately and be completed by Thanksgiving of 2018. However, the project was not completed by that date. Some five months later, the project still was unfinished. Plaintiffs then fired Defendants. Plaintiffs sued Defendants in the Chancery Court for Overton County (“the Trial Court”) for breach of contract. The Trial Court ruled in Plaintiffs’ favor. Defendants appeal. We hold that time was of the essence under the Agreement. We further find that Defendants committed a material breach of the Agreement by failing to timely complete Plaintiffs’ barndominium. We affirm.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed; Case Remanded

D. MICHAEL SWINEY, C.J., delivered the opinion of the court, in which FRANK G. CLEMENT, JR., P.J., M.S., and W. NEAL MCBRAYER, J., joined.

Nolan R. Goolsby and Bradford G. Wood, Jr., Cookeville, Tennessee, for the appellants, Roger Bilbrey and Bilbrey’s Construction, Inc.

Matthew J. McClanahan, Crossville, Tennessee, for the appellees, Angela May Franks and Danny Ray Franks. OPINION

Background

In July 2019, Plaintiffs sued Defendants in the Trial Court for breach of contract. Plaintiffs alleged that they hired Defendants in May 2018 to construct a “barndominium,” a metal building that looks like a barn with a stained-concrete floor, garage, and living quarters. Plaintiffs, who were from Texas, planned to move to Tennessee and live in the barndominium. The original contract price was $140,000. Mr. Bilbrey drafted the Agreement, which was a very basic handwritten contract between the parties. It set out the project’s specifications. It also stated “[c]ompletion By Thanksgiving 2018” and “[s]tart im[m]ediately.” In their complaint, Plaintiffs alleged as follows, in part:

15. As of the date of this Complaint, the construction is still not completed, and the Plaintiffs have had to expend additional money to hire a different construction company and additional subcontractors to complete the work and make repairs to Bilbrey’s work that was completed in an insufficient and negligent manner. 16. Defendants did not construct the barndominium in a good and workmanlike manner but performed the services required of them in a careless, negligent, and unworkmanlike manner. 17. Defendants intentionally breached the contract as set out in Exhibit B. 18. Defendants failed to complete construction or negligently constructed including, but not limited to, the following:

a. failed to install a water heater, b. failed to stain the flooring of the barndominium, c. failed to complete the installation of the doors and trim work, d. failed to complete installation of electrical wires for inspection, e. improperly placed smoke detector, f. failed to install up-to-code electrical outlets, g. failed to install the metal roof properly causing water leaks, and h. failed to properly install the refrigerator water valve ($1,000.00 insurance deductible).

19. As a result of the defective and unworkmanlike manner in which the Defendants constructed the barndominium, Plaintiffs have been compelled to hire additional contractors including but not limited to[:] electricians,

-2- plumbers, roofers, and general construction companies to repair the premises to a working and livable condition. 20. Plaintiffs have expended money for additional materials, labor, insurance deductibles for water leaks caused by the negligent roof installation, and are continuing work to complete the construction as a result of the Defendants’ breach and negligence. 21. Plaintiffs’ construction and repair of the barndominium continues, and the additional costs to complete construction is ongoing. 22. Due to the Defendants’ unnecessary delay and total failure to complete the construction of the Plaintiffs’ home, Plaintiffs have incurred additional living expenses for rent and storage of their belongings.

Plaintiffs demanded a judgment against Defendants for restoring and completing the barndominium and consequential damages along with prejudgment interest; judgment for additional living and rental expenses along with prejudgment interest; post-judgment interest; attorney’s fees; discretionary costs; and any other general relief deemed appropriate. In August 2019, Defendants filed an answer and counterclaim. In their answer, Defendants asserted the following in response to Plaintiffs’ specific allegations:

a. The plaintiffs never supplied the water heater as required by the contract. b. The plaintiffs changed their minds about the concrete floor, wanted a floating floor installed and hired another contractor to install a floating floor. c. The doors and trim were never installed by Defendants because Plaintiff Angela May Franks fired Defendants on April 25, 2019 before the barndominium was completed sufficiently to install the doors and trim. d. The electrical work was never completed by Defendants because Plaintiff Angela May Franks fired Defendants on April 25, 2019 before the barndominium was completed sufficiently to complete the electrical work; the electrical work passed the “rough-in” inspection. e. The smoke detector was never installed by Defendants because Plaintiff Angela May Franks fired Defendants on April 25, 2019 before the barndominium was completed sufficiently to complete the installation of the smoke detector; the smoke detector passed the “rough-in” inspection. f. The final electrical outlets was never installed by Defendants because Plaintiff Angela May Franks fired Defendants on April 25, 2019 before the barndominium was completed sufficiently to complete the installation of the final electrical outlets; the electrical outlets passed the “rough-in” inspection.

-3- g. Deny. The Plaintiff Angela May Franks fired Defendants on April 25, 2019 before there were any holes cut into the metal roof. h. Deny.

In their counterclaim, Defendants asserted claims of breach of contract and quantum meruit against Plaintiffs.

This case was tried in May 2021. We review the pertinent testimony, beginning with that of Ms. Franks. Ms. Franks said that she first heard about Mr. Bilbrey from a man who was doing excavation work for her. According to Ms. Franks, Mr. Bilbrey told her that he had been constructing metal structure buildings for twenty years. Ms. Franks told him what she wanted in the house, and Mr. Bilbrey reduced their discussion to a handwritten contract, the Agreement. The Agreement provides:

1 - 36 x 60 x 9 full[y] insulated w/ double bubble all over. 12 FT x 60 FT. Covered Porches on Front and Back with No concrete. 36 x 40 Living area with Stained Concrete Floors, Standard 6 panel doors, and Drywall, ceilings and walls. Living quarters Framed per Customer print. Walls insulated w/ R-13 and ceiling R-30 Blow in. White vinyl windows. 12 x 8 garage door on shop side[.] Custome[r] Furnishes all, Fixtures on electrical and plumbing and cabinets and countertops and vanities and tubs and showers. Completion By Thanksgiving 2018. Start im[m]ediately.

Ms. Franks also gave Mr. Bilbrey a drawing. The cost for the project was $140,000. Plaintiffs wired Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

84 Lumber Co. v. Smith
356 S.W.3d 380 (Tennessee Supreme Court, 2011)
Randall D. Kiser v. Ian J. Wolfe
353 S.W.3d 741 (Tennessee Supreme Court, 2011)
Madden Phillips Construction, Inc. v. GGAT Development Corp.
315 S.W.3d 800 (Court of Appeals of Tennessee, 2009)
State of Tennessee v. Joey DeWayne Thompson
285 S.W.3d 840 (Tennessee Supreme Court, 2009)
Barnes v. Barnes
193 S.W.3d 495 (Tennessee Supreme Court, 2006)
Berryhill v. Rhodes
21 S.W.3d 188 (Tennessee Supreme Court, 2000)
Whitehaven Community Baptist Church v. Holloway
973 S.W.2d 592 (Tennessee Supreme Court, 1998)
Shepherd v. Perkins Builders
968 S.W.2d 832 (Court of Appeals of Tennessee, 1997)
Allstate Insurance Co. v. Watson
195 S.W.3d 609 (Tennessee Supreme Court, 2006)
McClain v. Kimbrough Const. Co., Inc.
806 S.W.2d 194 (Court of Appeals of Tennessee, 1990)
Adams TV of Memphis, Inc. v. ComCorp of Tennessee, Inc.
969 S.W.2d 917 (Court of Appeals of Tennessee, 1997)
Union Carbide Corp. v. Huddleston
854 S.W.2d 87 (Tennessee Supreme Court, 1993)
Archer v. Archer
907 S.W.2d 412 (Court of Appeals of Tennessee, 1995)
Bowden v. Ward
27 S.W.3d 913 (Tennessee Supreme Court, 2000)
Wells v. Tennessee Board of Regents
9 S.W.3d 779 (Tennessee Supreme Court, 1999)
Hanover Insurance Company v. Haney
425 S.W.2d 590 (Tennessee Supreme Court, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
Danny Ray Franks v. Roger Bilbrey, Counsel Stack Legal Research, https://law.counselstack.com/opinion/danny-ray-franks-v-roger-bilbrey-tennctapp-2022.