Danis-Shook Joint Venture Xxv v. Secretary of Labor

319 F.3d 805, 2002 CCH OSHD 32,645, 19 OSHC (BNA) 2166, 2003 U.S. App. LEXIS 3001, 2003 WL 359156
CourtCourt of Appeals for the Sixth Circuit
DecidedFebruary 20, 2003
Docket01-4038
StatusPublished
Cited by17 cases

This text of 319 F.3d 805 (Danis-Shook Joint Venture Xxv v. Secretary of Labor) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Danis-Shook Joint Venture Xxv v. Secretary of Labor, 319 F.3d 805, 2002 CCH OSHD 32,645, 19 OSHC (BNA) 2166, 2003 U.S. App. LEXIS 3001, 2003 WL 359156 (6th Cir. 2003).

Opinion

OPINION

BOYCE F. MARTIN, JR., Chief Circuit Judge.

This case arises from an appeal of a decision by the Occupational Safety and Health Review Commission regarding a drowning accident at a work site in Beav-ercreek, Ohio. That decision reversed in part and affirmed in part the decision of the administrative law judge in this matter. Danis-Shook, the petitioner, claims that the judgment of the Review Commis *808 sion was arbitrary, capricious and an abuse of discretion. The Review Commission found that Danis-Shook had violated two sections of the Occupational Safety and Health Act. First, the Commission found that Danis-Shook violated 29 C.F.R. § 1926.21(b)(2) in failing to instruct employees in the recognition and avoidance of the hazards associated with entering a basin filled with accumulated water. Second, the Commission found that Danis-Shook had knowledge of the failure of its employee to use personal protective equipment in violation of 29 C.F.R. § 1926.95(a), and Danis-Shook’s unpreventable supervisory misconduct defense failed. In essence, the Review Commission found that Danis-Shook made some efforts to insure safety but that its enforcement of safety rules was not sufficiently aggressive and its safety instructions not clear and definite.

In April of 1996, Danis Industries and Shook, Inc., entered into a joint venture for the expansion of the Beavercreek wastewater treatment plant in Ohio. As part of the expansion work, Danis-Shook constructed two identical equalization basins to provide added capacity for storage of sewage following storm surges. The basins are above ground and round, uncovered, concrete basins. They have a diameter of approximately two hundred feet, and they are about twenty feet high. The floors of the basins slope toward the center at about one half inch per foot. At the center of the basins is a drain pipe, forty-two inches in diameter. The pipe drops straight down six feet before reaching an elbow joint, where it thereafter proceeds horizontally, underground, to the pump station.

During the construction of the basins, Danis-Shook covered the drain pipes with plywood covers less than one inch-thick. Wooden boards were secured underneath each of the two plugs. Danis-Shook installed the plugs to prevent falling injuries while the basins were still under construction. The basins were completed in the fall of 1997, but the pump station was not yet completed. To prevent water from draining from the basins to the station, Danis-Shook left the plugs in place through the winter. The company also caulked around the plugs to prevent leakage.

When the pump station was finished in April of 1998, the basins still needed more work, including placing brackets on the walls for supporting aeration pipes. Rainwater and snowmelt from the winter had accumulated in the basins however, to between twelve and thirty inches deep, and the basins needed to be drained. To drain them, a laborer wearing waders, life vest, harness and lifeline entered the water and drilled three holes in each plywood plug. The water began to drain, but the basins did not empty completely.

About two weeks after Danis-Shook drilled the holes, the pipefitters on the project finished their work on the pump station and began working in Basin 2. The pipefitters’ foreman was James Wagner, Sr., and he had a crew of two men, one of whom was his son. There were still several inches of water in the bottom of Basin 2, so the crew did as much work around the dry upper edges of the sloped floor as possible. The work did not involve going in the water at all. Because they could go no further in Basin 2 until the remainder of the water was gone, Foreman Wagner made a decision to begin working on Basin 1 on April 22, 1998. While the two crew members worked on assembling tools and cleaning the wall castings, Foreman Wagner, wearing waders, walked into the accumulated water in Basin 1. The water was more than thirty-two inches deep at the drain. The foreman wanted to see why the pipe was not draining. His crew watched *809 him pull a piece of plastic sheeting away from the plug. Next, Foreman Wagner used a long metal piece of equipment to slide over the plug, “thumping” the bar on the plug. The plug dislodged, and Foreman Wagner was sucked down the drain and drowned.

Within an hour and a half of the accident, an Occupational Safety and Health Administration safety specialist was at the construction site to make observations and conduct interviews. On the basis of the information she gathered, the Secretary of Labor issued a “serious citation” to Danis-Shook. She alleged “serious violations:” of 1) Section 5(a)(1) of the Occupational Safety and Health Act for failing to provide a workplace free of recognized hazards by exposing employees who entered the accumulated water in the basin to a potential engulfment hazard; 2) 29 C.F.R. § 1926.21(b)(2) for failing to instruct employees in the recognition and avoidance of hazards associated with entering a basin filled with accumulated water; and 3) 29 C.F.R. § 1926.95(a) for failing to require employees entering the water in the basin to wear appropriate personal protective equipment such as safety harnesses and lifelines. The administrative law judge vacated the first citation, and that holding was not appealed. The judge also vacated the citation for failing to instruct in violation of Section 1926.21(b)(2). The judge found the citation was appropriate for Section 1926.95(a), and he rejected Danis-Shook’s affirmative defense that Foreman Wagner engaged in unpreventable supervisory misconduct. The Review Commission found violations for both sections.

The Supreme Court has defined the duties of the Review Commission, saying, “The Commission is assigned to ‘earr[y] out adjudicatory functions’ under the Act.” Martin v. Occupational Safety and Health Review Comm’n, 499 U.S. 144, 147, 111 S.Ct. 1171, 113 L.Ed.2d 117 (1991) (internal citations omitted). The Court went on to say, “Initial decisions are made by an administrative law judge, whose ruling becomes the order of the Commission unless the Commission grants discretionary review.” Id. at 148, 111 S.Ct. 1171 (internal citations omitted). “[W]hen the Commission reverses the factual findings of the ALJ, who had the unique opportunity of observing the demeanor of the witnesses and accepting or rejecting their testimony based on'those observations, the Commission must articulate reasons for its failure to credit those findings.” Brock v. L.E. Myers Co., High Voltage Div., 818 F.2d 1270, 1277 (6th Cir.), cert. denied, 484 U.S. 989, 108 S.Ct. 479, 98 L.Ed.2d 509 (1987).

The Review Commission’s duties are not identical to ours in reviewing its decision.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

New River Electrical Corp. v. OSHC
25 F.4th 213 (Fourth Circuit, 2022)
Angel Brothers Enterprises v. Walsh
18 F.4th 827 (Fifth Circuit, 2021)
Potelco Inc. v. Dept Of Labor & Industries
Court of Appeals of Washington, 2016
Potelco, Inc. v. Department of Labor & Industries
377 P.3d 251 (Court of Appeals of Washington, 2016)
Mountain States Contractors v. Thomas Perez
825 F.3d 274 (Sixth Circuit, 2016)
Comtran Group, Inc. v. U.S. Department of Labor
722 F.3d 1304 (Eleventh Circuit, 2013)
Eagle Services Corp. v. H2O Industrial Services, Inc.
532 F.3d 620 (Seventh Circuit, 2008)
W.G. Yates & Sons Construction Co. v. Safety
459 F.3d 604 (Fifth Circuit, 2006)
Complete Gen Contr v. OSHRC
Sixth Circuit, 2005

Cite This Page — Counsel Stack

Bluebook (online)
319 F.3d 805, 2002 CCH OSHD 32,645, 19 OSHC (BNA) 2166, 2003 U.S. App. LEXIS 3001, 2003 WL 359156, Counsel Stack Legal Research, https://law.counselstack.com/opinion/danis-shook-joint-venture-xxv-v-secretary-of-labor-ca6-2003.