Dan Ryan Builders, Inc. v. Nelson

737 S.E.2d 550, 230 W. Va. 281, 2012 WL 5834590, 2012 W. Va. LEXIS 830
CourtWest Virginia Supreme Court
DecidedNovember 15, 2012
DocketNo. 12-0592
StatusPublished
Cited by90 cases

This text of 737 S.E.2d 550 (Dan Ryan Builders, Inc. v. Nelson) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dan Ryan Builders, Inc. v. Nelson, 737 S.E.2d 550, 230 W. Va. 281, 2012 WL 5834590, 2012 W. Va. LEXIS 830 (W. Va. 2012).

Opinion

KETCHUM, Chief Justice:

The United States Court of Appeals for the Fourth Circuit has certified a question to this Court that concerns two areas of state law: the law of contract formation, and the doctrine of unconscionability. The question from the Court of Appeals arises from a contract that contained an arbitration provision which required one party to the contract to arbitrate all of their claims, but allowed the other party to file a lawsuit for some of its claims. A federal district court previously determined that the arbitration provision was not enforceable because it lacked “mutuality of obligation” and “mutuality of consideration.”

The Court of Appeals asks:

Does West Virginia law require that an arbitration provision, which appears as a single clause in a multi-clause contract, itself be supported by mutual consideration when the contract as a whole is supported by adequate consideration?

Dan Ryan Builders, Inc. v. Nelson, 682 F.3d 327 (4th Cir.2012). We conclude that West Virginia’s law of contract formation only requires that a contract as a whole be supported by adequate consideration. Hence, a single clause within a multi-clause contract does not require separate consideration. However, we further conclude that under the doctrine of unconscionability, a trial court may decline to enforce a contract clause— such as an arbitration provision — if the obligations or rights created by the clause unfairly lack mutuality.

[284]*284I.

Factual and Procedural Background

Dan Ryan Builders, Inc. (“DRB”), constructed a new home in Berkeley County, West Virginia. In May 2008, Norman Nelson signed a 56-page contract with DRB for the sale and purchase of that home for $385,000.00. The contract contained an arbitration clause which states, in part, that:

Any dispute arising under or pursuant to this Agreement, or in any way related to the Property and/or with respect to any claims arising by virtue of any representations alleged to have been made by [Dan Ryan Builders] ... shall be settled and finally determined by arbitration and not in a court of law ... The parties hereto specifically acknowledge that they are and shall be bound by arbitration and are barred from initiating any proceeding or action whatsoever in connection with this Agreement.1

In the same arbitration provision, however, DRB reserved the right to seek arbitration or to file an action for damages, if Mr. Nelson “default[ed] by failing to settle on the Property within the time required under [the] Agreement.”

Mr. Nelson alleges that, after he completed the purchase of the house, he found numerous, substantial defects in the house’s construction. In May 2010, Mr. Nelson and his wife Angelia filed a lawsuit against DRB in the Circuit Court of Berkeley County. The lawsuit seeks damages from DRB for allegedly concealing its knowledge of an illegal septic system, of previous basement flooding, and of substandard concrete. It also alleges that DRB negligently designed and constructed the septic system, which resulted in property damages and bodily injury. DRB answered the Nelson’s complaint.2

DRB subsequently filed a petition in the United States District Court for the North[285]*285ern District of West Virginia, pursuant to the Federal Arbitration Act (“the FAA”),3 seeking to compel Mr. and Mrs. Nelson4 to submit their claims to arbitration. The district court stayed litigation of the Berkeley County lawsuit until DRB’s petition could be resolved.

In response to DRB’s petition, the Nelsons argued to the district court that the arbitration provision (which allowed DRB to pursue some claims in court while requiring the Nelsons to arbitrate all of their claims) was unenforceable because it lacked consideration, and because it was unconscionable. The district court declined to rule on the whether the clause was eonscionable, but dismissed DRB’s petition to compel arbitration because the arbitration provision lacked mutuality of consideration. The district court’s order stated:

[T]his Court finds that the arbitration clause in the Agreement of Sale used by DRB in its transaction with the [Nelsons] ... fails for want of mutual consideration. The arbitration clause begins with an appearance of mutuality ... As the clause continues, however, the reader finds that any hope of mutuality can only be described as fleeting____Therefore, ... the instant arbitration clause must fail for want of mutual consideration.

Dan Ryan Builders, Inc. v. Nelson, 2010 WL 5418939, *6 (N.D.W.Va.2010).

DRB appealed the district court’s order to the United States Court of Appeals for the Fourth Circuit, arguing that the arbitration provision did not require separate consideration or mutual obligations. DRB argued that the provision was enforceable because there was otherwise sufficient consideration to support the entire contract. On May 10, 2012, the Court of Appeals noted various West Virginia cases on the law of contracts— particularly cases discussing consideration, mutuality and unconscionability in the context of arbitration — and concluded that our law was unclear on the issues raised by DRB’s appeal. Accordingly, the Court of Appeals certified its question to this Court.

II.

Standard of Review

We review the question from the Court of Appeals de novo. See, Syllabus Point 1, Light v. Allstate Ins. Co., 203 W.Va. 27, 506 S.E.2d 64 (1998) (“A de novo standard is applied by this Court in addressing the legal issues presented by a certified question from a federal district or appellate court.”); Syllabus Point 1, Bower v. Westinghouse Elec. Corp., 206 W.Va. 133, 522 S.E.2d 424 (1999) (“This Court undertakes plenary review of legal issues presented by certified question from a federal district or appellate court.”).

III.

Analysis

Because the parties’ dispute involves a written arbitration agreement evidencing a transaction affecting interstate commerce, they agree that the decision of this Court must be guided, in part, by Section 2 of the Federal Arbitration Act (9 U.S.C. § 2), which states:

A written provision in any maritime transaction or a contract evidencing a transaction involving commerce to settle by arbitration a controversy thereafter arising out of such contract or transaction, or the refusal to perform the whole or any part thereof, or an agreement in writing to submit to arbitration an existing controversy arising out of such a contract, transaction, or refusal, shall be valid, irrevocable, and enforceable, save upon such grounds as exist at law or in equity for the revocation of any contract.

See Syllabus Point 6, Brown v. Genesis Healthcare Corp., 228 W.Va. 646, 724 S.E.2d 250 (2011) (“Brown I ”).5 The federal statute [286]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
737 S.E.2d 550, 230 W. Va. 281, 2012 WL 5834590, 2012 W. Va. LEXIS 830, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dan-ryan-builders-inc-v-nelson-wva-2012.