ANR Construction, Inc. v. CPF Construction, LLC

CourtDistrict Court, S.D. West Virginia
DecidedJune 4, 2024
Docket2:21-cv-00575
StatusUnknown

This text of ANR Construction, Inc. v. CPF Construction, LLC (ANR Construction, Inc. v. CPF Construction, LLC) is published on Counsel Stack Legal Research, covering District Court, S.D. West Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ANR Construction, Inc. v. CPF Construction, LLC, (S.D.W. Va. 2024).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE SOUTHERN DISTRICT OF WEST VIRGINIA

CHARLESTON DIVISION

ANR CONSTRUCTION, INC.,

Plaintiff,

v. CIVIL ACTION NO. 2:21-cv-00575

CPF CONSTRUCTION, LLC,

Defendant.

MEMORANDUM OPINION AND ORDER

Pending before the Court is Defendant CPF Construction, LLC’s motion for summary judgment. (ECF No. 92.) For the reasons more fully explained below, the motion is GRANTED in part and DENIED in part. I. BACKGROUND A. Facts1 On June 23, 2016, West Virginia experienced a series of state-wide thunderstorms that dumped roughly 10 inches of rainfall within a 24-hour timeframe.2 Widespread flash-flooding

1 The parties agree that this case is best understood when viewed against the backdrop of West Virginia’s recovery efforts following the 2016 flood. That said, the record before the Court is silent on much of that background and the parties take much of it for granted. As a result, the Court takes a moment to fill in these gaps and provide the reader with the context that gave rise to this litigation. The Court notes that the flooding disaster of 2016 was so catastrophic and well-known in southern West Virginia that the Court also can and will take judicial notice of all of this indisputable background information. 2 Remembering the 2016 Flood Five Years On, W. Va. Dep’t of Transp. (June 23, 2021), https://transportation.wv.gov/communications/PressRelease/Pages/Remembering-the-2016-flood-five-years- on.aspx. 1 followed.3 As a result, thousands of homes had been flooded, destroyed, and even swept away.4 Thousands more were without power.5 Twenty-three people were killed.6 A state of emergency was soon declared, and West Virginians began picking up the pieces and rebuilding.7 In the months that followed, the State received $149 million in federal funding, all of which was earmarked for flood relief.8 The State used these funds to start the RISE Housing

Program (“RISE program”), which it introduced in 2017.9 As relevant here, the RISE program helped West Virginians rebuild their homes by providing the necessary labor and funding.10 The RISE program had a defined structure. At the top was the West Virginia National Guard (“National Guard”), who oversaw the program.11 Below the National Guard were four different general contractors, who the State hired to divide up and build the 1,00012 or so houses.13 Thompson Construction, Inc. (“Thompson”) was among those general contractors.14 Thompson,

3 The Historic and Devastating Floods of June 23rd 2016, Nat’l Weather Serv., https://www.weather.gov/rnk/2016_06_23_Flood (last visited May 31, 2024). 4 Remembering the 2016 Flood Five Years On, supra note 2. 5 See The Historic 2016 Late June Flooding Event in West Virginia, Nat’l Weather Serv., https://www.weather.gov/rlx/2016-historic-june- flooding#:~:text=Event%20Summary&text=Sadly%2C%20flash%20flooding%20across%20the,over%20the%20Oh io%20Valley%20Region (last visited June 4, 2024). 6 Id. 7 Carrie Hodousek, Tomblin Issues State of Emergency for 44 Counties, W. Va. MetroNews (June 23, 2016, 10:05 PM), https://wvmetronews.com/2016/06/23/tomblin-issues-state-of-emergency-for-44-counties/. 8 See New Rise WV Funding to Help Those Impacted by June 2016 Flood, Ready WV, https://ready.wv.gov/news/Pages/New-funding.aspx (last visited May 31, 2024). 9 RISE West Virginia Disaster Recovery Program Kickoff, W. Va. Exec. (Aug. 2, 2017), https://wvexecutive.com/rise- west-virginia-disaster-recovery-program-kickoff/. 10 Id. 11 RISE West Virginia Program Update on Four-Year Anniversary of 2016 Flood, W. Va. Nat’l Guard (June 23, 2020), https://www.wv.ng.mil/News/Article/2229941/rise-west-virginia-program-update-on-four-year-anniversary- of-2016-flood/. 12 Steven Allen Adams, RISE West Virginia: Making Heads and Tails of the Botched Flood Relief Effort, Parkersburg News & Sentinel (July 1, 2018), https://www.newsandsentinel.com/news/local-news/2018/07/rise-west-virginia- making-heads-and-tails-of-the-botched-flood-relief-effort/. 13 RISE WV Announces Contractors for June 2016 Flood Recovery, W. Va. Exec. (Nov. 1, 2017), https://wvexecutive.com/rise-wv-announces-contractors-june-2016-flood-recovery/. 14 Id. 2 however, needed a subcontractor, and it later hired Defendant for that role. (ECF No. 96-1 at 25:1–14.) But Defendant apparently needed its own subcontractor to actually build its allotted houses. Defendant chose Plaintiff—a small West Virginia construction company with a half- dozen or so employees—and Defendant soon began recruiting Plaintiff to join the RISE program.

(Id. at 10:12–11:7, 12:18–13:2.) Defendant’s recruiting efforts proved successful, and the two parties struck a deal on March 28, 2019. (ECF No. 96-3.) They memorialized their agreement in a 10-page binder agreement (“binder agreement” or “the contract”), which outlined their respective obligations. (Id.) As relevant here, the binder agreement provided that Plaintiff would build 125 stick-built homes. (Id. at 2.) However, this number was not set in stone. Defendant retained the right to increase or decrease the number of houses at any time. (Id.) As for payment, the parties agreed that Defendant would pay Plaintiff in three roughly equal installments.15 (Id. at 5–6.) The first third would be due once Plaintiff completed the foundation on each house, the second portion would be due once the house was “roughed in,” and the final payment would be due once the house was

finished. (Id.) The binder agreement also contained an insubordination clause, which, as the name suggests, gave Defendant the right to remove Plaintiff if Plaintiff became insubordinate. (Id. at 7.) Importantly, however, the binder agreement contained no timetable as to when any one house or set of houses needed to be finished. (See generally id.) Nor did it contain a clause saying time was of the essence. The contract was entirely silent as to Plaintiff’s allotted time to perform.

15 The amounts varied slightly, depending on which phase of the house Plaintiff completed. (See ECF No. 96-1 at 37:2–14.) 3 The parties may have signed their contract in late March, but Plaintiff had to wait a while before it could begin work. (ECF No. 96-2 at 21:5–10.) This delay occurred for two main reasons. First, another contractor had yet to finish tearing down the houses that Plaintiff was assigned to rebuild. (ECF No. 96-1 at 29:3–7.) Second, once those old homes were torn down,

the lots still needed to be cleared and surveyed. (ECF No. 96-2 at 21:20–22:7.) This prep work took five or six weeks in all, so Plaintiff could not begin until mid-May.16 (See ECF No. 96-2 at 22:1–3.) Plaintiff promptly began work then but soon experienced setbacks beyond its control. For example, when Plaintiff began working on the footers and foundations at multiple homes, it discovered debris—such as bicycles and old housing materials—buried underground. (ECF No. 96-1 at 95:21–96:22.) As it turned out, the other contractor did not haul off this debris, but instead buried it on-site. (Id.) So Plaintiff had to haul off the debris itself before it could even begin working on the footer and foundation. (Id. at 98:9–99:1.) Even when Plaintiff was able to make progress, Thompson—who was higher up the food chain—would sometimes assign Plaintiff extra

tasks that took men away from building homes. According to Randy Young, Plaintiff’s owner, Thompson would “ask” Plaintiff’s employees to go trim trees somewhere or put a roof on a shed. (See, e.g., id. at 47:18–48:12.) This, of course, did nothing to help build a house. But, as Mr. Young explained in his deposition, when the “boss man tells you to do it, you do it.” (Id. at 49:13.) Despite these setbacks and impromptu side-jobs, Plaintiff progressed on the houses, and matters seemed to be going well. By the end of September, Plaintiff had built three houses

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Adickes v. S. H. Kress & Co.
398 U.S. 144 (Supreme Court, 1970)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Faith United Methodist Church & Cemetery of Terra Alta v. Morgan
745 S.E.2d 461 (West Virginia Supreme Court, 2013)
Gaddy Engineering Co. v. Bowles Rice McDavid Graff & Love, LLP
746 S.E.2d 568 (West Virginia Supreme Court, 2013)
Moseley v. Branker
550 F.3d 312 (Fourth Circuit, 2008)
Arnold v. Palmer
686 S.E.2d 725 (West Virginia Supreme Court, 2009)
St. Luke's United Methodist Church v. CNG DEVELOPMENT CO.
663 S.E.2d 639 (West Virginia Supreme Court, 2008)
E. Shepherdstown Developers, Inc. v. J. Russell Fritts, Inc.
398 S.E.2d 517 (West Virginia Supreme Court, 1990)
Howell v. Appalachian Energy, Inc.
519 S.E.2d 423 (West Virginia Supreme Court, 1999)
Kidd v. Mull
595 S.E.2d 308 (West Virginia Supreme Court, 2004)
Croston v. EMAX OIL CO., a VIRGINIA CORP.
464 S.E.2d 728 (West Virginia Supreme Court, 1995)
Cotiga Development Co. v. United Fuel Gas Co.
128 S.E.2d 626 (West Virginia Supreme Court, 1962)
Hatfield v. Health Management Associates of West Virginia, Inc.
672 S.E.2d 395 (West Virginia Supreme Court, 2008)
Heartland, L.L.C. v. McIntosh Racing Stable, L.L.C.
632 S.E.2d 296 (West Virginia Supreme Court, 2006)
Fifth Third Bank v. McClure Properties, Inc.
724 F. Supp. 2d 598 (S.D. West Virginia, 2010)
Clawson v. FedEx Ground Package System, Inc.
451 F. Supp. 2d 731 (D. Maryland, 2006)
Teri Sneberger v. Jerry Morrison, d/b/a Jerry Morrison Construction
776 S.E.2d 156 (West Virginia Supreme Court, 2015)
Love-Lane v. Martin
355 F.3d 766 (Fourth Circuit, 2004)
Virginian Export Coal Co. v. Rowland Land Co.
131 S.E. 253 (West Virginia Supreme Court, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
ANR Construction, Inc. v. CPF Construction, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anr-construction-inc-v-cpf-construction-llc-wvsd-2024.