ANR Construction, Inc. v. CPF Construction, LLC

CourtDistrict Court, S.D. West Virginia
DecidedMarch 1, 2022
Docket2:21-cv-00575
StatusUnknown

This text of ANR Construction, Inc. v. CPF Construction, LLC (ANR Construction, Inc. v. CPF Construction, LLC) is published on Counsel Stack Legal Research, covering District Court, S.D. West Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ANR Construction, Inc. v. CPF Construction, LLC, (S.D.W. Va. 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE SOUTHERN DISTRICT OF WEST VIRGINIA

CHARLESTON DIVISION

ANR CONSTRUCTION, INC.,

Plaintiff,

v. CIVIL ACTION NO. 2:21-cv-00575

CPF CONSTRUCTION, LLC,

Defendant.

MEMORANDUM OPINION AND ORDER

Pending before the Court is Plaintiff and Counterclaim Defendant ANR Construction, Inc.’s (“ANR Construction”) Motion to Dismiss Counterclaim Count One (I) for Failure to Plead Fraud with Particularity, and in the Alternative for Judgment as a Matter of Law, or Partial Summary Judgment. (ECF No. 7.) For the reasons more fully explained below, ANR Construction’s motion is DENIED. I. BACKGROUND A. The Complaint The following allegations are drawn from ANR Construction’s original Complaint. Defendant CPF Construction, LLC (“CPF Construction”), an out-of-state entity with a principal place of business in South Carolina, was a subcontractor to a prime contract between the West Virginia Development Office and Thompson Construction Group, Inc., for the permit and construction of 125 “stick built housing units.” (ECF No. 1–1 at ¶¶ 2, 4.) At some point in time prior to March 28, 2019, CPF Construction issued proposed drawings, plans, specifications, and contract documents to ANR Construction, who was to be the subcontractor to the prime contract, to construct the stick-built housing units. (Id. at ¶ 5.) The subcontract between ANR Construction and CPF Construction allegedly totaled $9,222,912.00, as set forth in the parties’ Binder Agreement. (Id.)

However, CPF Construction allegedly was not authorized to conduct business in West Virginia and did not possess a West Virginia contractor’s license until late September 2019. (Id. at ¶ 7.) Prior to March 28, 2019, CPF Construction was allegedly not listed nor identified by Thompson Construction Group, Inc. to the State of West Virginia as a subcontractor expected to perform more than $25,000 worth of work. (Id. at ¶ 8.) Despite lacking these credentials, ANR Construction alleges that CPF Construction sent the proposed project documents “as an inducement for ANR to enter into the Binder Agreement with defendant CPF.” (Id. at ¶ 11.) On or around March 28, 2019, ANR Construction submitted its bid and entered into a Binder Agreement with CPF Construction. (Id. at ¶¶ 13, 15.) Thereafter, and “[d]espite ANR’s performance of its obligations under the Agreement,” CPF Construction allegedly failed to pay

ANR Construction in the amount of $330,980.00. (Id. at ¶ 17.) Subsequently, in September 2019, ANR Construction reportedly discovered that CPF Construction was not licensed in West Virginia and “brought this information to the attention of, among others, Thompson Construction Group, the State of West Virginia, and Defendant CPF[.]” (Id. at ¶ 18.) Following this disclosure, ANR Construction alleges that it “received calls and communication” from Thompson Construction Group and CPF Construction threatening to terminate it from the project. (Id. at ¶ 19.) On October 3, 2019, CPF Construction and Thompson Construction Group “improperly terminat[ed]” the Binder Agreement and have refused to pay the amounts due. (Id. at ¶20.)

2 Plaintiff and Counterclaim Defendant ANR Construction asserts six causes of action. Count One asserts a breach of contract. Count Two alleges a claim for fraud, deceit, misrepresentation, and negligent misrepresentation. Count Three advances a claim for breach of implied in fact contract. Count Four alleges a cause of action for quantum meruit, breach of

implied in law contract, and unjust enrichment. Count Five is a claim for declaratory judgment. Finally, Count Six claims punitive damages and attorney’s fees and costs. (See generally ECF No. 1–1.) ANR Construction filed its complaint in the Circuit Court of Kanawha County, West Virginia on September 27, 2021. (See id.) Thereafter, on October 21, 2021, CPF Construction removed the action to this Court on the basis of diversity jurisdiction, pursuant to 28 U.S.C. § 1332. (ECF No. 1.) On October 27, CPF Construction filed its answer and counterclaim. (ECF No. 3.) B. The Counterclaim The following allegations are drawn from CPF Construction’s counterclaim. CPF

Construction is a South Carolina limited liability company “doing business in West Virginia.” (ECF No. 3 at 8, ¶ 1.) On or around March 28, 2019, CPF Construction entered into the Binder Agreement with ANR Construction, in the amount of $9,222,912 and under which ANR Construction had agreed to construct stick-built homes. (Id. at ¶ 4.) The Binder Agreement itself was “subject to the terms and conditions of the Prime Contract that was part of a State/Federal program to construct/reconstruct low-income housing that was devasted by flooding in West Virginia in 2016 particularly in Kanawha, Fayette and Greenbrier Counties.” (Id. at ¶ 5.) The Binder Agreement and the Prime Contract required subcontractors, such as ANR Construction, to

3 complete all of the work on a home, while the pay schedule called for one-third of the cost of an individual home to be billed at various intervals. (Id. at ¶ 6.) The intermittent billing allegedly assured subcontractors adequate cash flow to continue working on the homes, but also ensured that the subcontractor would finish the construction of the individual units. (Id.)

CPF Construction alleges that it met all of its obligations to ANR Construction under the terms of the Binder Agreement. (Id. at ¶ 8.) CPF Construction alleges, however, that ANR Construction failed to pay their materialmen and subcontractors pursuant to the Binder Agreement, and further failed to complete all of the homes covered by the Agreement. (Id.) CPF Construction alleges that ANR Construction submitted billings and received payments at certain intervals, but instead of using the funds to complete the homes, the funds were instead diverted “for the personal use of [Counterclaim] Defendant ANR’s owner, Randy L. Young, Jr. and [ANR Construction] failed to return to complete the project.” (Id. at ¶ 9.) CPF Construction alleges that, in addition to failing to meet its contractual obligations, ANR Construction did so “in an intentional manner” to secure funds from CPF Construction and

to which funds it was not entitled. (Id. at ¶ 12.) CPF Construction asserts that, “as a result of said fraud,” it will now have to make “double payment” to certain subcontractors and suppliers. (Id. at ¶ 13.) Moreover, CPF Construction asserts that it will also “incur expenses to secure releases of illegal mechanics’ liens placed upon their properties by Counterclaim Defendant ANR.” (Id.) CPF Construction claims that these “illegal liens” are “merely an attempt” by ANR Construction to harm CPF Construction’s reputation and to blackmail it into paying additional monies to ANR Construction. (Id. at ¶ 14.)

4 On these allegations, CPF has asserted two counterclaims. Counterclaim One asserts a cause of action for fraud. (Id. at 10.) Counterclaim Two is a cause of action for breach of contract. (Id. at 12.) ANR Construction filed the instant motion on November 24, 2021. (ECF No. 7.) CPF

Construction timely filed its response in opposition on December 8, 2021. (ECF No. 9.) Thereafter, ANR Construction filed its reply on December 10, 2021. (ECF No. 10.) With the briefing complete, this motion is ripe for adjudication. II. LEGAL STANDARD In general, a pleading must include “a short and plain statement of the claim showing that the pleader is entitled to relief.” Fed. R. Civ. P. 8(a)(2); see McCleary-Evans v. Md. Dep't of Transp., State Highway Admin.,

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Pocahontas Mining Co. v. Oxy USA, Inc.
503 S.E.2d 258 (West Virginia Supreme Court, 1998)
Kidd v. Mull
595 S.E.2d 308 (West Virginia Supreme Court, 2004)
Cordial v. Ernst & Young
483 S.E.2d 248 (West Virginia Supreme Court, 1996)
Adrian King, Jr. v. Jim Rubenstein
825 F.3d 206 (Fourth Circuit, 2016)
Horton v. Tyree
139 S.E. 737 (West Virginia Supreme Court, 1927)
Michael Woods v. City of Greensboro
855 F.3d 639 (Fourth Circuit, 2017)
Wikimedia Foundation v. National Security Agency
857 F.3d 193 (Fourth Circuit, 2017)
John Nanni v. Aberdeen Marketplace, Inc.
878 F.3d 447 (Fourth Circuit, 2017)
Poling v. Pre-Paid Legal Services, Inc.
575 S.E.2d 199 (West Virginia Supreme Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
ANR Construction, Inc. v. CPF Construction, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anr-construction-inc-v-cpf-construction-llc-wvsd-2022.