Paul T. Chastain, Jr. v. Bethlehem Farm, Inc. and Eric Fitts

CourtIntermediate Court of Appeals of West Virginia
DecidedJuly 1, 2024
Docket23-ica-350
StatusPublished

This text of Paul T. Chastain, Jr. v. Bethlehem Farm, Inc. and Eric Fitts (Paul T. Chastain, Jr. v. Bethlehem Farm, Inc. and Eric Fitts) is published on Counsel Stack Legal Research, covering Intermediate Court of Appeals of West Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Paul T. Chastain, Jr. v. Bethlehem Farm, Inc. and Eric Fitts, (W. Va. Ct. App. 2024).

Opinion

IN THE INTERMEDIATE COURT OF APPEALS OF WEST VIRGINIA FILED July 1, 2024 PAUL T. CHASTAIN, JR., ASHLEY N. DEEM, CHIEF DEPUTY CLERK Plaintiff Below, Petitioner INTERMEDIATE COURT OF APPEALS OF WEST VIRGINIA

v.) No. 23-ICA-350 (Cir. Ct. Summers Cnty. Case No. CC-45-2022-C-31)

BETHLEHEM FARM, INC. and ERIC FITTS, Defendants Below, Respondents

MEMORANDUM DECISION

Petitioner Paul T. Chastain, Jr., appeals the July 6, 2023, order of the Circuit Court of Summers County which granted Respondents Bethlehem Farm, Inc., and Eric Fitts’s (collectively “Bethlehem Farm”) motion to dismiss Mr. Chastain’s complaint.1 Mr. Chastain alleged a breach of contract claim against Bethlehem Farm after it failed to complete a project to renovate Mr. Chastain’s home. Bethlehem Farm filed a timely response, and Mr. Chastain filed a timely reply.

This Court has jurisdiction over this appeal pursuant to West Virginia Code § 51- 11-4 (2022). After considering the parties’ arguments, the record on appeal, and the applicable law, this Court finds no substantial question of law and no prejudicial error. For these reasons, a memorandum decision affirming the lower tribunal’s order is appropriate under Rule 21 of the Rules of Appellate Procedure.

Bethlehem Farm is a charitable organization that uses volunteers and donations to help low-income individuals make home improvements. Eric Fitts is the owner and operator of Bethlehem Farm. Mr. Chastain’s home needed renovations to make it more handicapped accessible and he applied to Bethlehem Farm for its assistance in completing the renovations. Mr. Chastain’s application was approved and, as part of the agreement between Mr. Chastain and Bethlehem Farm, the parties executed a document that described the work to be completed by Bethlehem Farm and the terms and conditions under which the work would be performed. The agreement, titled “Contract Form[,]” was signed by both parties on May 11, 2022. Based on the language of the agreement, Bethlehem Farm agreed to demolish and rebuild Chastain’s home. The agreement also estimated the cost of

1 Mr. Chastain is represented by Paul S. Detch, Esq. Bethlehem Farm is represented by Thomas W. White, Esq., and Esha S. Simon, Esq.

1 the project and described the work to be performed. Per the agreement, Mr. Chastain’s costs were capped at $70,000, but it is undisputed that no money was exchanged between the parties.

In his underlying complaint, Mr. Chastain alleged that Bethlehem Farm breached the parties’ agreement and refused to complete the work at his home. He further alleged that Bethlehem Farm solicited donations and gifts for use in making improvements to his property and that Bethlehem Farm refused to provide the donations and gifts to Mr. Chastain when work stopped on the project. Mr. Chastain included the written agreement in the appendix record.2

While this case was pending in circuit court, Bethlehem Farm filed a Motion to Dismiss alleging that the parties’ agreement failed due to a lack of consideration because Mr. Chastain neither paid any money, nor promised to provide anything of value to Bethlehem Farm under the agreement. Bethlehem Farm argued it was making a gift to Mr. Chastain and further that the parties’ agreement failed due to estoppel, as Bethlehem Farm’s volunteers felt threatened and unsafe while working on Mr. Chastain’s property. Mr. Chastain responded to the motion to dismiss by arguing there were disputed issues of fact remaining to be resolved by a jury.

2 The Supreme Court of Appeals of West Virginia has made clear that

[w]hen a movant makes a motion to dismiss a pleading pursuant to Rule 12(b)(6) of the West Virginia Rules of Civil Procedure, and attaches to the motion a document that is outside of the pleading, a court may consider the document only if (1) the pleading implicitly or explicitly refers to the document; (2) the document is integral to the pleading’s allegations; and (3) no party questions the authenticity of the document. If a document does not meet these requirements, the circuit court must either expressly disregard the document or treat the motion as one for summary judgment as required by Rule 12(b)(7).

Syl. Pt. 6, Mountaineer Fire & Rescue Equip., LLC v. City Nat’l Bank of W. Va., 244 W. Va. 508, 854 S.E.2d 870 (2020). Here, this contract is explicitly referred to in the complaint, is integral to Chastain’s allegations, and no party has questioned the authenticity of this document. As a result, this Court may consider the contract without converting this motion to dismiss to one for summary judgment.

2 The circuit court held a hearing on the Motion to Dismiss on March 10, 2023.3 On July 6, 2023, the circuit court granted Bethlehem Farm’s Motion to Dismiss finding that there was a lack of consideration as to the parties’ agreement. Particularly, the circuit court held as follows:

To the best the Court can determine from the pleadings, the alleged contractual relationship was simply an agreement that the Defendant would construct and provide a handicapped accessible structure for the Plaintiff, raising the funds and donations necessary to complete the project on its own. Nowhere does the Plaintiff allege that he gave anything as consideration for the agreement.

It is from this order that Mr. Chastain now appeals.

Because the circuit court’s ruling is based upon a motion to dismiss, our standard of review is de novo. Syl. Pt. 2, State ex rel. McGraw v. Scott Runyan Pontiac-Buick, Inc., 194 W. Va. 770, 461 S.E.2d 516 (1995) (“Appellate review of a circuit court’s order granting a motion to dismiss a complaint is de novo.”). “The trial court, in appraising the sufficiency of a complaint on a Rule 12(b)(6) motion, should not dismiss the complaint unless it appears beyond doubt that the plaintiff can prove no set of facts in support of his claim which would entitle him to relief.” Syl. Pt. 3, Chapman v. Kane Transfer Co., Inc., 160 W. Va. 530, 236 S.E.2d 207 (1977) (citation omitted). With this standard in mind, we turn to the arguments at issue herein.

On appeal, Mr. Chastain asserts two assignments of error. First, he argues the circuit court erred in granting the motion to dismiss based on the finding that Mr. Chastain failed to plead consideration because both parties below were bound by their mutual obligations. Mr. Chastain admits that no money was exchanged between the parties, but argues that despite that fact, he was required to abide by other conditions of the agreement. He states that the agreement required him to ensure the environment was free from drug and alcohol use, free from harassment, and to allow Bethlehem Farm to take photos and videos of the project to use in its social media.

In West Virginia law “[a] claim for breach of contract requires proof of the formation of a contract, a breach of the terms of that contract, and resulting damages.” Sneberger v. Morrison, 235 W. Va. 654, 669, 776 S.E.2d 156, 171 (2015) (citing Syl. Pt. 1, State ex rel. Thornhill Group, Inc. v. King, 233 W.Va. 564, 759 S.E.2d 795 (2014)). “The fundamentals of a legal contract are competent parties, legal subject matter, valuable consideration and mutual assent. There can be no contract if there is one of these essential elements upon which the minds of the parties are not in agreement.” Syl. Pt. 3, Dan Ryan

3 The transcript of this hearing was not included in the appendix record.

3 Builders, Inc. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Newell v. High Lawn Memorial Park Co.
264 S.E.2d 454 (West Virginia Supreme Court, 1980)
Chapman v. Kane Transfer Co., Inc.
236 S.E.2d 207 (West Virginia Supreme Court, 1977)
State Ex Rel. McGraw v. Scott Runyan Pontiac-Buick, Inc.
461 S.E.2d 516 (West Virginia Supreme Court, 1995)
Doganieri v. United States
520 F. Supp. 1093 (N.D. West Virginia, 1981)
SER Thornhill Group v. Charles E. King, Jr., Judge
759 S.E.2d 795 (West Virginia Supreme Court, 2014)
Teri Sneberger v. Jerry Morrison, d/b/a Jerry Morrison Construction
776 S.E.2d 156 (West Virginia Supreme Court, 2015)
Hamer v. . Sidway
27 N.E. 256 (New York Court of Appeals, 1891)
Huff v. Lanes Bottom Bank
158 S.E. 380 (West Virginia Supreme Court, 1931)
Janes v. Felton
129 S.E. 482 (West Virginia Supreme Court, 1925)
Tabler v. Hoult
158 S.E. 782 (West Virginia Supreme Court, 1931)
McCary v. Monongahela Valley Traction Co.
125 S.E. 92 (West Virginia Supreme Court, 1924)
Talbott v. Stemmons' Ex'r
12 S.W. 297 (Court of Appeals of Kentucky, 1889)
Lindell v. Rokes
60 Mo. 249 (Supreme Court of Missouri, 1875)
Dan Ryan Builders, Inc. v. Nelson
737 S.E.2d 550 (West Virginia Supreme Court, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Paul T. Chastain, Jr. v. Bethlehem Farm, Inc. and Eric Fitts, Counsel Stack Legal Research, https://law.counselstack.com/opinion/paul-t-chastain-jr-v-bethlehem-farm-inc-and-eric-fitts-wvactapp-2024.