D & S Machine Products, Inc. v. Thyssenkrupp Bilstein of America, Inc.

434 F. App'x 446
CourtCourt of Appeals for the Sixth Circuit
DecidedJuly 22, 2011
DocketNo. 09-4235
StatusPublished
Cited by1 cases

This text of 434 F. App'x 446 (D & S Machine Products, Inc. v. Thyssenkrupp Bilstein of America, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D & S Machine Products, Inc. v. Thyssenkrupp Bilstein of America, Inc., 434 F. App'x 446 (6th Cir. 2011).

Opinion

ALICE M. BATCHELDER, Chief Judge.

Plaintiff D & S Machine Products appeals an award of summary judgment in favor of defendant ThyssenKrupp Bilstein. We AFFIRM in part, REVERSE in part, and REMAND for further proceedings consistent with this opinion.

I.

ThyssenKrupp Bilstein (“Bilstein”) provides parts for Mercedes Benz automobiles, among others. Bilstein purchased certain component parts from D & S Machine Products: M-class parts and non-M-class parts (the “M-class” referring to Mercedes M-class automobiles). For the non-M-class parts, Bilstein issued a purchase order to D & S, which serves as the fully integrated contract — this is not in dispute. For the M-class parts, there is some dispute as to what constitutes the actual contract. Ultimately, however, this dispute does not affect the resolution of this appeal.1

D & S sued Bilstein in diversity in federal court in Ohio, claiming: (1) breach of contract for the M-class parts; (2) breach of contract for the non-M-class parts; and (3) fraud in the inducement (i.e., by contracting for the M-class parts, Bilstein had allegedly induced D & S to purchase an expensive piece of machinery). Bilstein moved for summary judgment on all three claims. The district court granted summary judgment to Bilstein on the fraud-in-the-inducement claim on the basis that it was indistinguishable from the breach-of-contract claim, and D & S did not appeal [448]*448that decision. The district court originally denied summary judgment on the breach-of-contract claims, but later reconsidered and granted Bilstein summary judgment on all claims. D & S appealed.

II.

Because this is an appeal of a grant of summary judgment, we conduct a de novo review, Walton v. Ford Motor Co., 424 F.3d 481, 485 (6th Cir.2005), and draw all reasonable inferences in favor of D & S, the non-moving party, see Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 255, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). And accepting D & S’s version of the facts in toto, we must conclude that Bilstein is entitled to judgment as a matter of law. See Fed.R.Civ.P. 56(c).2

According to D & S, beginning in the spring to early summer of 2005, these two parties had an oral contract for the M-class parts.3 D & S describes the contract this way:

Subject matter: D & S would produce the M-Class parts initially using slower and less cost-effective CNC machines, and then, on a faster and more efficient Hydromat machine.
Price: Bilstein would temporarily pay D & S higher per-part rates while D & S produced the M-Class parts on CNC machines [i.e., the ‘CNC prices’], but pricing would drop to ‘production prices’ [i.e., the ‘Hydromat prices’] after production was transitioned to the Hydro-mat [machine].
Start date: D & S would start producing parts immediately.
Quantity: D & S had a contract for the life of the part or alternatively for at least five years.
Equipment: D & S agreed to purchase a Hydromat machine in exchange for the promise of Bilstein using D & S for five years or life of the program.

Appellant’s Brief, p. 33 (record citations omitted). D & S began to produce the parts using the CNC machines and Bil-stein paid for those parts at the CNC prices. D & S also purchased the Hydro-mat machine, as promised, and by January 2006 was producing the parts using the Hydromat machine and charging Bilstein the lower Hydromat prices. On February 9, 2006, D & S sent Bilstein an email confirming the new prices. This practice lasted for approximately six weeks.

On March 23, 2006, “Bilstein presented D & S with an ultimatum — produce the M-Class parts at [even lower] pricesf, specifically prices] that D & S had rejected on two previous occasions, or Bilstein would resource the parts to a European supplier.” Appellant’s Reply Brief, p. 4. D & S rejected this ultimatum and, on April 20, 2006, wrote to Bilstein: “Due to th[is] threat ..., D & S will stop producing the [M-class parts] as of April 21, 2006 and discontinue shipment of these products until this matter is resolved and Bilstein agrees to uphold the original agreement.”4

[449]*449But D & S did not discontinue shipment of these M-class parts; D & S continued to ship the parts but invoiced Bilstein at the former, higher CNC prices. Bilstein paid the invoices at the Hydromat prices. On June 30, 2006, D & S sent an email to Bilstein asserting that Bilstein’s failure to pay the CNC prices rendered it in breach of contract and warned that it would not ship any more parts unless Bilstein paid the difference in full by July 7, 2006. Bil-stein did not pay the difference and D & S did not ship any more parts. Bilstein asked D & S to retract its repudiation and when D & S did not respond, Bilstein said it considered the agreement terminated.

On October 23, 2006, Bilstein wrote to D & S canceling the non-M-class contracts because “Bilstein can no longer reasonably rely on D & S as a supplier.” D & S filed suit on October 26, 2006, claiming that Bilstein breached the M-class parts contract by failing to pay the CNC prices and by obtaining another supplier when D & S refused to ship parts at the Hydromat prices. D & S later added a claim that Bilstein also breached the non-M-class parts contract by terminating it in bad faith (i.e., in retaliation for D & S’s refusal to capitulate to its request for lower M-class part prices).

In granting summary judgment to Bil-stein, the district court concluded that D & S was at fault for breaching the contract “when it unilaterally raised the price of the parts and then stopped shipment on June 30, 2006.” The court reasoned:

The problem with D & S’s actions was that even if the agreement between the parties was for the life of the part [as D & S contends], there was no basis for D & S to revert to the higher, CNC prices for the parts. The evidence in the record — both the documents and the oral testimony — reveal[s] that the parties agreed that the CNC pricing was temporary and that the prices would be lowered once the Hydromat was tooled. Thus, even if Bilstein had [improperly] terminated the contract in the spring of 2006 (which it did not) and if such a termination had entitled D & S to a remedy, that remedy would have involved damages based on the ‘current manufacturing’ [i.e.,] lower Hydromat price, not the temporary CNC price.

On appeal, D & S does not address this reasoning or even attempt to explain or justify its insistence on the CNC prices. In fact, in its reply brief, D & S specifically disclaimed any reliance on the CNC pricing (though without addressing the foregoing), asserting:

6. D & S does not claim on appeal that it is entitled to enforce the CNC prices for the .duration of the life of the part.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
434 F. App'x 446, Counsel Stack Legal Research, https://law.counselstack.com/opinion/d-s-machine-products-inc-v-thyssenkrupp-bilstein-of-america-inc-ca6-2011.