Wren Reese, Inc. v. Great Lakes Structural Concrete Products, Inc.

362 N.E.2d 269, 50 Ohio App. 2d 168, 4 Ohio Op. 3d 137, 1975 Ohio App. LEXIS 5920
CourtOhio Court of Appeals
DecidedAugust 4, 1975
Docket7937
StatusPublished
Cited by6 cases

This text of 362 N.E.2d 269 (Wren Reese, Inc. v. Great Lakes Structural Concrete Products, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wren Reese, Inc. v. Great Lakes Structural Concrete Products, Inc., 362 N.E.2d 269, 50 Ohio App. 2d 168, 4 Ohio Op. 3d 137, 1975 Ohio App. LEXIS 5920 (Ohio Ct. App. 1975).

Opinion

■Brown, P.-J.

This appeal by plaintiff-appellant, Wren Reese, Inc., is from a judgmént by the Lucas. County Court of Common Pleas in favor of defendant-appellee, Great Lakes Structural Concrete Products, Inc., in a non-jury trial involving an alleged breach of contract by defendant. Plaintiff is a general contractor which had a general contract with the state of Ohio, executed June 15,1973, following a public bidding on May 23, 1973, for the construction of a bridge in Marion, Ohio.

Prior to submitting its bid, on May 23, 1973, plaintiff solicited bids from prospective fabricators for the fabrication of one hundred 36” I-beams, an element of the bridge *169 to'be constructed; The bids were only for fabrication and; did not involve on-site labor. On May 22, 1973, defendant orally submitted to plaintiff a bid of $104,500 for the 'one hundred I-beams. - '

After plaintiff- executed its bridge construction contract with the state, on June 15, 1973, it advised defendant that its “bid was good.” On June 27, 1973, plaintiff wrote tp the; state and requested that the defendant be approved as fabricator for the bridge construction. .. ; ’

On July 6, 1973, the state testing laboratory .called, defendant to determine its production schedule incident to the approval of defendant as a fabricator. Defendant stated production would not start until December 1, 197'3; Since approval of a fabricator requires inspection for' approval, approximately three weeks before the fabricator starts to', fabricate pr.estressed members (as in this case), the state' testing officer stated that the inspection of defendant would be delayed until then. " '

On July 12, 1973, defendant wrote to plaintiff and un-' ilaterally increased its price for the I-beam from $104,500 to $109,750, an increase of $5,250. On July 13,1975, plaintiff wrote to defendant stating it would not accept the' price' increase and would hold defendant to its original contract price of $104,500.

Thereafter,'in August 1973, defendant repudiated the, contract and refused to perform. Plaintiff then shopped for bids from other fabricators and finally executed a contract with Yo.st Company which furnished the I-beams, for a contract price of $119,995. Plaintiff paid' this price to. Yost Company and sought to recover damages for breach' of contract in. the sum of $15,495, the difference between $119,995, which Yost received, and the $104,500, which defendant had originally bid.

The trial court decided that defendant was not'obligated to plaintiff and that the contract between plaintiff and defendant was void because defendant was a. subcontractor and that defendant, as .a subcontractor,., had. pot been' properly qualified for the work 1 sublet . to him before' the subcontract was executed between' *170 plaintiff and defendant. The trial court .concluded that such subcontract qualification of defendant was required by R. C. Chapter 5525, governing public contracts for state highways and bridges. R. C. 5525.06 provides :

“No successful bidder shall enter into a subcontract with any other person, involving the performance of any part of any work upon which such bidder may be engaged for the department of transportation, unless the subcontractor has been properly qualified for the work sublet to him.”

The plaintiff’s three assignments of error are as follows :

“1. Ohio Revised Code Sec. 5525.06 applies to subcontracts. The state of Ohio, Department of Transportation defines a subcontractor as a person who performs work on the job site.. The trial court erred in concluding that defendant, a fabricator, who performed no work on the job site, was a subcontractor and, therefore, subject to O. R. C. Sec. 5525.06.
“2; The trial court erred in finding that O. R. C. Sec. 5525.06 barred recovery. If O. R. C. 5525.06 were a condition precedent to the contract, compliance therewith was waived because appellee repudiated before the condition could be met.
“3. The trial court erred in denying appellant’s Rule 59 motion because its findings were the result of a mistake of law.” •

The assignments of error are well taken. ;We reverse.

. Incident to rendering a general judgment in. favor of defendant and dismissing the complaint, the trial court entered a finding of facts separate from its conclusions of law. The following separate findings of fact and conclusions of law are correctly stated and are amply supported by the record.

.“■This court finds that defendant entered into a contract with plaintiff; that plaintiff relied on that- contract;' and that the defendant was bound to perform. Although no time limit was set by the sub-contractor within which the contractor was.to accept, this court finds that plaintiff did *171 act within a reasonable time according to the custom of the trade at that time, tried to get state approval of the defendant sub-Gontractor-defendant, and that defendant violated the terms of the contract. The court further finds that plaintiff acted within a reasonable time as enunciated in Wargo v. Cox, 26 Ohio App. 1 (1971). This Court further finds that the contract entered into between plaintiff and defendant was subsequent to the enactment of Section 5525.06 O. R. C., supra, effective 10/1/53.

“Conclusions Of Law

“Plaintiff and defendant entered into a contract. On or about May 22, 1973, plaintiff obtained a price bid from defendant and confirmed its bid by letter of May 25, 1973. Defendant was constantly advised that its ‘bid was good.’ Plaintiff acted within a reasonable time to confirm defendant’s bid under the principles of Wargo v. Cox, supra; and accordingly, under the rationale of that decision and the common-law principles as set forth in 17 Am. Jur. 2d, Section 449, and under the authority of Brewing v. Maxwell, 78 Ohio State 54 (1908) and Schmitt v. Schnell, 14 Ohio C. C. 158 (1897), would have been entitled to recover damages from defendant.”

R. C. 5525.06 does not apply to defendant because the defendant corporation on the facts in the record in this ease is a fabricator and not a subcontractor. Nowhere in R. C. 5525.06, nor elsewhere in R. C. Chapter 5525 is there a definition of “subcontractor.” Parties to a contract may agree upon the definition and meaning of terms used in such contracts. The plaintiff and the state, through its Department of Transportation, by incorporating the department’s standard construction and material specifications in their written contract for the bridge construction, defined the meaning of “fabricator” and “subcontractor” as follows :

“Sec. 101.50 Subcontractor. An individual, firm or corporation to whom the Contractor sublets part of the contract to be performed on the job site, who prior to such undertaking receives the written consent of the Director, *172

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
362 N.E.2d 269, 50 Ohio App. 2d 168, 4 Ohio Op. 3d 137, 1975 Ohio App. LEXIS 5920, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wren-reese-inc-v-great-lakes-structural-concrete-products-inc-ohioctapp-1975.