Southeast Land Development, Ltd. v. Primrose Management, L.L.C.

2011 Ohio 2341, 952 N.E.2d 563, 193 Ohio App. 3d 465
CourtOhio Court of Appeals
DecidedMay 16, 2011
Docket5-10-04 and 5-10-11
StatusPublished
Cited by25 cases

This text of 2011 Ohio 2341 (Southeast Land Development, Ltd. v. Primrose Management, L.L.C.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southeast Land Development, Ltd. v. Primrose Management, L.L.C., 2011 Ohio 2341, 952 N.E.2d 563, 193 Ohio App. 3d 465 (Ohio Ct. App. 2011).

Opinion

Willamowski, Judge.

{¶ 1} These appeals are brought by plaintiff-appellant, Southeast Land Development, Ltd. (“Southeast”), from judgments of the Court of Common Pleas of Hancock County. For the reasons set forth below, the judgments are affirmed in part and reversed in part.

{¶ 2} On March 17, 2005, Southeast accepted an offer from Primrose Management, L.L.C. (“Primrose”) to purchase ten acres of undeveloped real estate in Hancock County for $500,000. Closing was to be within 120 days of either the approval of the planned-use development (“PUD”) or the rezoning of the property, whichever was later. As part of the purchase agreement, Southeast agreed to provide the following infrastructure improvements to the property on or before May 31, 2006.

A. A dedicated right-of-way and improved street including approved curb cuts, to be located along the south lot fine of the property.
B. Infrastructure, including a lift station, of sufficient size and capacity for Buyer’s intended use of the Property, connected to the sanitary sewer system of the City of Findlay, Ohio, shall be available at the lot line of the Property. Buyer shall be responsible for any connection of tap fees.
C. Infrastructure of sufficient size and capacity for Buyer’s intended use of the Property, connected to the water system of the City of Findlay, Ohio, shall be available at the lot line of the Property. Buyer shall be responsible for any connection or tap fees.
D. Infrastructure of sufficient size and capacity for electrical and gas service for Buyer’s intended use of the Property, connected to the appropriate utility provider, shall be available at the lot line of the Property. Buyer shall be responsible for any connection fees.
*470 E. Prior to September 1, 2005, or commencement of construction, which ever [sic] is latter [sic]. Seller shall provide temporary electrical and water service at the lot line of the Property, of sufficient size and capacity, so that Buyer can construct its Senior Retirement Community Project.
F. Seller must act in a diligent, reasonable, and good faith manner in completing the installation of the infrastructure improvements. Seller shall continuously monitor the progress of the construction of Buyer’s Senior Retirement Community facility so that the infrastructure improvements are completed in a timely manner in accordance with this agreement.

The contract also provided that Southeast had the right to retain any excess soil and that it had 30 days from Primrose’s written notice of excess soil to remove the soil before the right terminated. Primrose assigned the contract to Findlay Retirement, L.L.C., on February 2, 2006.

{¶ 3} On February 20, 2006, the contract was modified. The modifications indicated that the electrical service had been made available at the lot line and that Southeast had therefore satisfied that requirement of the contract. The time for providing water service was extended to August 1, 2006, but required Southeast to provide a temporary holding tank if it was not provided by June 1, 2006. The time for the roadway curbs, sewer service, and gas service was extended until October 1, 2006. The modification also provided that the closing date would be February 17, 2006, and that time was not of the essence. 1 The closing actually occurred on March 9, 2006.

{¶ 4} In April 2006, Primrose began working the site for its retirement-home project. On or about May 4, 2006, Matt Carpenter, the assistant chief engineer for the city of Findlay, issued a “stop work” order. The reasons for the order were that no bonds had been posted by any party. A meeting was held on May 17, 2006, to determine what steps to take. After the meeting, Jim Thares, the owner and president of Primrose, determined that Luke Theis, a part owner of Southeast, was noncommittal about continuing with the PUD. He then requested that Todd Jenkins, an engineer project manager for Peterman Associates, prepare plans for an independent project. These plans were then submitted to the city of Findlay for approval on June 1, 2006. These plans were approved at the end of June 2006, and Primrose posted the necessary construction bonds in July 2006. Southeast did not post its bond. Primrose then proceeded with its independent project.

{¶ 5} In June or July 2006, Primrose’s excavator wanted to remove the excess soil from the site. He placed two phone calls to Theis to see if he wanted the soil. *471 Theis told him he would check and get back to him. Within the next couple of days, the excavator removed the excess soil and gave it to a third party.

{¶ 6} On November 28, 2006, Southeast filed a complaint for breach of contract against Primrose. Southeast alleged that Primrose had breached the agreement by filing its own plans to construct the utilities and changing the layouts and by giving away the soil, which the contract specifically stated was Southeast’s property. On January 2, 2007, Primrose filed its answer and a counterclaim alleging that Southeast had anticipatorily breached the contract. On January 30, 2007, Southeast filed its answer to the counterclaim. A trial was held on the issues from April 28 through April 30, 2008. Both parties filed their posttrial briefs on September 2, 2008. On June 5, 2009, the trial court entered judgment in favor of Primrose on all claims. Southeast filed its notice of appeal from this judgment on July 2, 2009. On January 15, 2010, the trial court granted Primrose’s application for attorney fees. Southeast filed its notice of appeal from this judgment on February 16, 2010. The two appeals were combined for argument purposes, and the following assignments of error are raised.

First Assignment of Error

The trial court erred in finding that [Southeast] committed an “anticipatory repudiation” of the Agreement.

Second Assignment of Error

The trial court erred in finding that [Southeast’s] own actions constitute an absolute defense to [Southeast’s] breach of contract claims asserted against [Primrose].

Third Assignment of Error

The trial court erred in failing to award reasonable attorneys’ fees in this matter to [Primrose].

{¶ 7} In the first assignment of error, Southeast alleges that the trial court erred in finding that it committed an anticipatory breach of the contract. Southeast argues that the evidence does not support the claim of anticipatory breach. “Judgments supported by some competent, credible evidence going to all the essential elements of the case will not be reversed by a reviewing court as being against the manifest weight of the evidence.” C.E. Morris Co. v. Foley Constr. Co. (1978), 54 Ohio St.2d 279, 8 O.O.3d 261, 376 N.E.2d 578, at syllabus.

The civil manifest weight of the evidence standard “affords more deference to the fact-finder” than is afforded in criminal cases. State v. Wilson, 113 Ohio St.3d 382, 2007-Ohio-2202, 865 N.E.2d 1264, ¶ 26.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kern v. Mishler
2025 Ohio 1698 (Ohio Court of Appeals, 2025)
David Rentals, L.L.C. v. Virginia Woods, L.L.C.
2024 Ohio 1446 (Ohio Court of Appeals, 2024)
Universal Steel Bldgs. Corp. v. Dues
2024 Ohio 698 (Ohio Court of Appeals, 2024)
State v. Bush
2023 Ohio 4473 (Ohio Court of Appeals, 2023)
State ex rel. Squire v. Phipps
2023 Ohio 3950 (Ohio Court of Appeals, 2023)
Investor Support Serv., L.L.C. v. Dawoud
2021 Ohio 2293 (Ohio Court of Appeals, 2021)
Kennedy v. Harb
S.D. Ohio, 2021
MRI Software, L.L.C. v. W. Oaks Mall FL, L.L.C.
2018 Ohio 2190 (Ohio Court of Appeals, 2018)
Western-Southern Life Asuc Co. v. George Kaleh
879 F.3d 653 (Fifth Circuit, 2018)
Watson Water Company, Inc. v. Indiana-American Water Company, Inc.
85 N.E.3d 840 (Indiana Court of Appeals, 2017)
Atlas Noble, LLC v. Krizman Enterprises
692 F. App'x 256 (Sixth Circuit, 2017)
Lowery v. Ridgeway
2015 Ohio 5051 (Ohio Court of Appeals, 2015)
Broad Street Energy Company v. Endeavor Ohio, LLC
806 F.3d 402 (Sixth Circuit, 2015)
Koonce v. Liverpool Express, Inc.
2015 Ohio 50 (Ohio Court of Appeals, 2015)
P & J Design Servs., Inc. v. Linton
2014 Ohio 2848 (Ohio Court of Appeals, 2014)
Sunesis Trucking Co., Inc. v. Thistledown Racetrack, L.L.C.
2014 Ohio 2411 (Ohio Court of Appeals, 2014)
EAC Properties, L.L.C. v. Brightwell
2014 Ohio 2078 (Ohio Court of Appeals, 2014)
Snapp v. Castlebrook Builders, Inc.
2014 Ohio 163 (Ohio Court of Appeals, 2014)
Crowe Ents., Inc. v. Amicon Med. Group, Inc.
2014 Ohio 11 (Ohio Court of Appeals, 2014)
Grove v. Gamma Ctr., Inc.
2013 Ohio 1734 (Ohio Court of Appeals, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
2011 Ohio 2341, 952 N.E.2d 563, 193 Ohio App. 3d 465, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southeast-land-development-ltd-v-primrose-management-llc-ohioctapp-2011.