Curry v. Tucker

616 P.2d 8, 1980 Alas. LEXIS 602
CourtAlaska Supreme Court
DecidedSeptember 5, 1980
Docket4249
StatusPublished
Cited by21 cases

This text of 616 P.2d 8 (Curry v. Tucker) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Curry v. Tucker, 616 P.2d 8, 1980 Alas. LEXIS 602 (Ala. 1980).

Opinions

OPINION

Before RABINOWITZ, C. J., and CON-NOR, BOOCHEVER *, BURKE and MATTHEWS, JJ.

BURKE, Justice.

In this action for breach of contract, the primary question to be determined is whether the vendee’s conduct in breaching two real estate contracts justified the trial court’s application of the extreme remedy of forfeiture. We conclude that under the circumstances of this case the declaration of forfeiture was appropriate.

In late 1967, David Curry was in severe financial trouble. He had recently been forced to close his business and had lost his homestead through foreclosure. He sought assistance from his friend and former employer George Tucker who, along with his wife, Carol, was then the developer of Crestbrook subdivision. Mr. Tucker agreed to allow Curry to store equipment on lot 9 of the subdivision and to live rent free in a dilapidated fourplex on the adjacent lot 10. The money and materials necessary to make the building habitable were advanced by Tucker.

Sometime in 1968, Curry decided he wanted to purchase and develop the property. He approached Tucker with this plan and, after extensive discussion, they entered into an oral contract for the sale of lots 9 and 10. Curry was to pay $4,875 for lot 9 and $14,500 for lot 10 in monthly installments of $100 and $250 respectively, with each contract accruing interest at 8%. To further assist Curry in getting back on his feet, Tucker agreed to help Curry obtain the materials necessary for him to finish the fourplex. Between 1968 and November 1970, Tucker advanced Curry $6,688.08 to cover property taxes, utilities, insurance, materials, labor and Curry’s bank payments on a prior unrelated loan. During this period Curry was employed, yet made no payments under the oral contracts for 1968 or 1969.

On November 13, 1970, at Curry’s request, the oral contracts were reduced to writing. As of this date, Curry had paid Tucker $4,000. Of this amount, $2,200 was used to repay Tucker for bank payments made on Curry’s behalf in satisfaction of the prior loan. The remaining $1,800 was treated as a down payment on the lots, $1,000 on lot 10 and $800 on lot 9. It was further agreed that the purchase price of lot 10 would be increased by the $4,488.08 still owed for the advances between 1968-1970. In all other respects the written contracts reflected the terms of the prior oral contract. Thus, as of November 1970, Curry owed Tucker a total of $22,063.08 under the written contracts. The contracts were signed and escrow instructions were drawn up but, at Curry’s request, the contracts were not recorded and the escrow instructions were not utilized.

By April 1971, the focus of Curry’s plans had changed. Rather than immediately completing the fourplex, he now wanted to build an apartment and a large garage from which he could operate a business. Curry requested that Tucker provide the necessary financing. Tucker agreed to provide additional advances subject to a 10% overhead charge to cover his .office expenses. The purchase price of lot 10 was to be further modified to include all such advances or charges. Pursuant to his promise, Tucker provided additional advances of $11,111.08 during 1971. Curry, however, made no payments throughout 1971. Thus, as of the end of 1971, Curry’s obligations under the contracts, including interest and overhead, totalled $36,197.39.

In 1972, Curry expressed a renewed interest in completing the fourplex. He once [11]*11again approached Tucker for assistance, proposing that if Tucker could fund the project himself, or obtain a loan from a bank, Curry would provide all of the necessary labor and make the bank payments. Tucker ultimately agreed to obtain the maximum possible loan of $65,000 on the condition that the proceeds of the loan be used first to pay Tucker the amount then due under the contracts. The balance of the loan was then to be distributed to Curry by Tucker as the work progressed and materials were needed. Curry was to repay the loan by making monthly payments of $622 to Tucker who would remit them to the bank. Curry did not, however, make any such payments. As a result, Tucker was forced to meet the obligations himself. Furthermore, during the remainder of 1972, Tucker provided additional advances of $17,248.57 to cover not only materials but also labor, cash loans, insurance, taxes and utilities. The fourplex remained uncompleted, however, primarily because Curry had diverted substantial labor and material into a 1,715 square foot one bedroom apartment above the garage for his personal use rather than into the fourplex as had been agreed. As a result of these additional advances, the total owed under the contracts at the end of 1972, including interest and overhead, was $60,018.68. .

In mid-December of 1972 through September 1973, Curry was employed by Tucker. It was agreed that Curry would receive only a portion of his earnings with the balance being credited against his contractual obligations. Pursuant to this agreement, $7,007.47 in earnings was credited against the interest which had accrued on Curry’s debt. At trial it was established that Curry was entitled to an additional credit of $73.00. Despite this arrangement it was necessary for Tucker to make additional expenditures of $7,253.60 on the lots during 1973. Thus, the total owed on the contracts at the end of 1973, including interest and overhead, was $65,343.89.

By early 1973, the bank payments, taxes and insurance had become a serious burden to Tucker who was having cash flow problems. Tucker discussed various solutions with Curry including selling the property, taking a partner or seeking credit elsewhere. Curry rejected all of these suggestions. As Tucker’s cash problems worsened in the summer of 1973, the prospect of a Chapter XI proceeding became likely. Tucker once again discussed the situation with Curry and offered to deed the property over to him, or anyone he chose, if he assumed the bank payments as he had agreed. Curry declined this offer, first because he still did not want the property in his name and then because he did not believe he owed as much as was due on the loan.

On October 31, 1973, Tucker initiated a proceeding for an arrangement under Chapter XI. Shortly thereafter Curry approached Tucker seeking additional funds. When Tucker informed Curry that he was unable to advance any more money or materials Curry became agitated. An argument ensued with Curry refusing to accept the amount of his obligations or to look at the books. This was essentially the final discussion between the parties prior to litigation.

Curry has made no attempt since 1973 to make any payments on his obligations. Tucker has thus been burdened with all of the necessary expenditures. The total amount due under the contracts as of the date of trial was $99,361.16, consisting of $71,468.48 in direct costs including the original sales price, $4,940.74 in overhead charges and $22,951.94 in unpaid interest charges. The total paid by Curry under the contracts was $8,880.47. Curry has never offered to tender the amount due under the contracts.

In July 1975, Tucker moved to regain possession of the lots by serving Curry with a Notice to Quit and Vacate pursuant to clause seven of the contracts. When Curry refused to vacate, the Tuckers filed this action seeking to recover possession of the lots. Curry denied the allegations in the complaint, maintaining that it was Tucker who had breached the contracts by failing to provide Curry with money and material [12]*12sufficient to complete the buildings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Antonnette N. v. Torey M.
Alaska Supreme Court, 2024
Barton D. v. Catalina D
Alaska Supreme Court, 2023
Levi R. v. Mallory R.
Alaska Supreme Court, 2022
Heather R. v. Justin L.
Alaska Supreme Court, 2021
Jill Y. v. Casey Y.
463 P.3d 833 (Alaska Supreme Court, 2020)
Solomon v. Solomon
420 P.3d 1234 (Alaska Supreme Court, 2018)
Duenas-Rendon v. Wells Fargo Bank, N.A.
354 P.3d 1037 (Alaska Supreme Court, 2015)
Stanhope v. Stanhope
306 P.3d 1282 (Alaska Supreme Court, 2013)
State v. Ayala
New Mexico Court of Appeals, 2011
Allen v. Vaughn
161 P.3d 1209 (Alaska Supreme Court, 2007)
Daniel v. O'DELL
921 P.2d 185 (Idaho Court of Appeals, 1996)
Gudenau v. Bierria
868 P.2d 907 (Alaska Supreme Court, 1994)
Demoski v. New
737 P.2d 780 (Alaska Supreme Court, 1987)
Strack v. Miller
645 P.2d 184 (Alaska Supreme Court, 1982)
Dillingham Commercial Co., Inc. v. Spears
641 P.2d 1 (Alaska Supreme Court, 1982)
Hendrickson v. Freericks
620 P.2d 205 (Alaska Supreme Court, 1981)
Curry v. Tucker
616 P.2d 8 (Alaska Supreme Court, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
616 P.2d 8, 1980 Alas. LEXIS 602, Counsel Stack Legal Research, https://law.counselstack.com/opinion/curry-v-tucker-alaska-1980.