Craftsman Builder's Supply, Inc. v. Butler Manufacturing Co.

1999 UT 18, 974 P.2d 1194, 364 Utah Adv. Rep. 22, 1999 Utah LEXIS 23, 1999 WL 112230
CourtUtah Supreme Court
DecidedMarch 5, 1999
Docket970345
StatusPublished
Cited by71 cases

This text of 1999 UT 18 (Craftsman Builder's Supply, Inc. v. Butler Manufacturing Co.) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Craftsman Builder's Supply, Inc. v. Butler Manufacturing Co., 1999 UT 18, 974 P.2d 1194, 364 Utah Adv. Rep. 22, 1999 Utah LEXIS 23, 1999 WL 112230 (Utah 1999).

Opinions

RUSSON, Justice:

¶ 1 Craftsman Builder’s Supply, Inc., appeals from the district court’s entry of summary judgment barring its claims against defendants. Craftsman sued Butler Manufacturing Company and U.S. Construction, Inc., for damages arising out of the collapse of Craftsman’s building. The district court held that Utah Code Ann. § 78-12-25.5 (1996) (the “builders statute of repose”) barred Craftsman’s causes of action. We affirm.

BACKGROUND

¶2 In 1977, Craftsman entered into a contract with U.S. Construction wherein U.S. Construction agreed to locate and erect a prefabricated metal building for Craftsman. Pursuant to the specifications provided by Craftsman, the roof of the building was to withstand forty pounds per square foot. U.S. Construction ordered the building from Butler and erected it in 1978. Fifteen years later, on February 25, 1993, the roof of the building collapsed under the weight of snow.

¶ 3 On February 24, 1995, Craftsman sued Butler, seeking damages under theories of products liability, breach of express warranty, breach of implied warranty of [1196]*1196merchantability, and negligence. Craftsman later amended its complaint, adding U.S. Construction as a defendant. Thereafter, U.S. Construction moved for summary judgment, arguing that Craftsman’s claims were barred by the applicable statutes of limitation and by the builders statute of repose. The district court agreed and, on August 19, 1996, granted U.S. Construction’s motion.

¶ 4 First, the court held that the products liability action was filed within the two-year products liability statute of limitations. The products liability statute requires the action to be brought within two years from the time that both the harm and its cause were discovered or should have been discovered. See Utah Code Ann. § 78-15-3 (1996). Because the court found no evidence that Craftsman should have discovered its action prior to February 25, 1993, the products liability action filed on February 24, 1995, was within the limitations period.

¶ 5 Second, the court held that the contract to locate and erect a prefabricated metal building was predominantly a contract for the sale of goods and, as a result, the Uniform Commercial Code’s (“UCC”) four-year statute of limitations applied. Id. § 70A-2-725 (Supp.1998). Section 70A-2-725 provides in part:

(2) A cause of action accrues when the breach occurs, regardless of the aggrieved party’s lack of knowledge of the breach. A breach of warranty occurs when tender of delivery is made, except that where a warranty explicitly extends to future performance of the goods and discovery of the breach must await the time of such performance the cause of action accrues when the breach is or should have been discovered.

Craftsman argued that the transaction was for the sale of services and, thus, the UCC statute of limitations should not apply, but that even if it did apply, the written specifications that the roof was to withstand forty pounds per square foot constituted a warranty explicitly extending to future performance. Therefore, Craftsman asserted, its warranty causes of action did not accrue until 1993 when the building collapsed. The court rejected this argument and held that the references in the building’s specifications to “a live load of 40” and “40#psf LL” did not “create a credible issue of material fact that an explicit warranty was given” and that, as a result, the warranty claims were barred.

¶ 6 Third, the court held that under Utah Code Ann. § 78-12-25(3), an action for negligence must be brought within four years from the date on which the negligent act giving rise to the claim occurred and that any negligent act by U.S. Construction occurred in 1978; .thus, the negligence claim was barred.

¶ 7 Fourth, the court held that in any event, all the claims, including the products liability claim, were subsumed and barred by the builders statute of repose. See § 78-12-25.5 (1996).

¶ 8 On October 23, 1996, Butler moved for summary judgment, arguing, as U.S. Construction did, that Craftsman’s claims were barred by the applicable statutes of limitation and by the builders statute of repose. Craftsman opposed the motion, arguing that the builders statute of repose was unconstitutional under article I, section 11 of the Utah Constitution (the “open courts” clause). In granting Butler’s motion, the court ruled that the applicable statutes of limitation and the builders statute of repose barred Craftsman’s claims as set forth in its ruling on U.S. Construction’s motion. The court also held that the builders statute of repose was constitutional.

¶ 9 Craftsman now appeals. First, Craftsman argues that the builders statute of repose violates the open courts clause and thus cannot operate to bar any of its claims. Craftsman further argues that the applicable statutes of limitation cannot bar its claims for the following reasons: (1) The warranty claims are not barred because the contract was for services, not goods, and, thus, the UCC statute of limitations does not apply. Alternatively, if the UCC statute applies, then the specification that the building’s roof withstand forty pounds per square foot constituted an express warranty which extended to future performance; thus, the express warranty claim falls within the discovery rule provision of the UCC statute of limitations [1197]*1197and is not barred. (2) The negligence cause of action is not barred because it did not accrue, and its four-year statute of limitations did not start to run, until the building collapsed in 1993 and Craftsman suffered damage. (3) The products liability claim is not barred because, as the court had previously held, it was filed within the two-year statute of limitations for products liability claims.

¶ 10 Second, Craftsman argues that even if the builders statute of repose is constitutional, then (1) it does not bar Craftsman’s claims because the plain language of the statute provides that the periods of repose are “subject to” a discovery rule, and Craftsman brought its claims within two years after discovery; (2) it does not bar Craftsman’s breach of express warranty claim because the alleged warranty that the roof withstand forty pounds per square foot extended beyond six years and was thus preserved under the terms of the statute; and (3) it does not bar Craftsman’s products liability claim because the products liability statute of limitations is more specific and should apply instead of the broader builders statute of repose.

¶ 11 Therefore, the threshold issue before us is whether the builders statute of repose is constitutional under the open courts clause. Because we hold that the statute is constitutional, the remaining issues we must address are (1) whether the repose periods are “subject to” a discovery rule; (2) whether there was a warranty extending beyond six years, thus rendering the statute of repose inapplicable to the express warranty claim; and (3) whether the products liability statute of limitations should apply instead of the builders statute of repose, because the products liability statute is the more specific statute.

STANDARD OF REVIEW

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bingham v. Gourley
2024 UT 38 (Utah Supreme Court, 2024)
Ag Valley Co-op v. Servinsky Engr.
974 N.W.2d 324 (Nebraska Supreme Court, 2022)
Commonwealth v. Claycomb
566 S.W.3d 202 (Missouri Court of Appeals, 2018)
Jensen v. Intermountain Healthcare, Inc.
2018 UT 27 (Utah Supreme Court, 2018)
Petersen v. Utah Labor Comm'n
2017 UT 87 (Utah Supreme Court, 2017)
Waite v. Utah Labor Comm'n
2017 UT 86 (Utah Supreme Court, 2017)
Brenda Robinson v. Boston Scientific Corporation
647 F. App'x 184 (Fourth Circuit, 2016)
In Re Adoption of B.Y.
2015 UT 67 (Utah Supreme Court, 2015)
Willis v. DeWitt
2015 UT App 123 (Court of Appeals of Utah, 2015)
Steinberg v. Community Housing Services-Capital Villa, Ltd.
2014 UT App 102 (Court of Appeals of Utah, 2014)
Jenkins v. Jordan Valley Water Conservancy District
2012 UT App 204 (Court of Appeals of Utah, 2012)
American Bush v. City of South Salt Lake
2006 UT 40 (Utah Supreme Court, 2006)
Weston v. McWilliams & Associates, Inc.
716 N.W.2d 634 (Supreme Court of Minnesota, 2006)
Tindley v. Salt Lake City School District
2005 UT 30 (Utah Supreme Court, 2005)
Wood v. University of Utah Medical Center
2002 UT 134 (Utah Supreme Court, 2002)
Laney v. Fairview City
2002 UT 79 (Utah Supreme Court, 2002)
Campbell v. State Farm Mutual Automobile Insurance Co.
2001 UT 89 (Utah Supreme Court, 2001)
Clark v. Clark
2001 UT 44 (Utah Supreme Court, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
1999 UT 18, 974 P.2d 1194, 364 Utah Adv. Rep. 22, 1999 Utah LEXIS 23, 1999 WL 112230, Counsel Stack Legal Research, https://law.counselstack.com/opinion/craftsman-builders-supply-inc-v-butler-manufacturing-co-utah-1999.