HALL, Chief Justice:

This is a consolidated appeal from a jury verdict entered in favor of plaintiff Daniel B. McCorvey in a personal injury action brought against the Utah Department of Transportation (“UDOT”) and LeGrand Johnson Construction Company (“Le-Grand”).1 We affirm.

I. FACTS

“Where evidence is in conflict in a jury trial, we assume that the jury believed those facts that support its verdict, and we view the facts and the reasonable inferences that arise from those facts in a light most supportive of the jury’s verdict.”2 We recite the facts accordingly.

On August 7, 1986, McCorvey was paralyzed when his car left the road and rolled in the median on Interstate 15 near Cove Fort, Utah. The accident occurred in a construction area where the road was being resurfaced by a process referred to as “chip sealing.” Chip sealing involves applying an oil-based emulsion onto the highway and then placing gravel on top of the emulsion. The gravel is then pressed into the emulsion by huge rollers. Next, the surface is swept, or “broomed,” to remove any excess gravel. Finally, normal highway traffic is used to further imbed the gravel into the new surface. During the process, excess chips are used so that the gravel will be as dense as possible.

UDOT, which maintains Utah’s interstate highways, retains independent contractors to do much of the necessary highway repair. LeGrand was awarded the contract to resurface the project at issue in this case. Although LeGrand was responsible for the actual resurfacing on the project, UDOT supplied the traffic control plan and was ultimately responsible for motorist safety.3

[43]*43The 15-mile construction project began approximately 10 miles north of the accident site in the two southbound lanes. Under the traffic control plan, one lane would be closed during the chip spreading process. The plan . called for placement of two “early warners,” large electric signs with arrows directing traffic from one lane into another, that would guide traffic into the lane that was not being chipped. The early warner signs would have “speed limit 25 miles per hour” signs affixed to them. Several “no passing” signs would line the project, and “loose gravel” signs would greet motorists at the beginning of the project.

At the time the accident occurred, Le-Grand had resurfaced most of the 15 miles. However, it neglected to broom the right-hand outside lane near the accident site. Consequently, the right lane was still covered with excess gravel that was in turn thrown into the left inside lane by passing motorists. The left lane, which was already broomed, still had a significant amount of gravel on it, especially close to the median to the left of the lane.

On the day of the accident, McCorvey was traveling south on 1-15 with a friend, Paul Page, in a 1986 Honda Civic. McCorvey testified that he first encountered construction several miles north of the accident scene where LeGrand was resurfacing a rest area. He slowed and passed through that area without event. He was in the left lane resuming normal highway speed when he hit a section of road that was covered with thick gravel. When he encountered the gravel, he downshifted and reduced his speed to approximately 45 miles per hour.

McCorvey began to lose control of the Honda almost immediately. He testified that the left lane had deep grooves in which it was possible to travel but that ridges of gravel lined the grooves, making it difficult to maneuver. The unswept right lane was worse, with gravel across the entire lane. The Honda’s tires were throwing excess chips from the road up into the air. As McCorvey proceeded south, a twelve-passenger Suburban van approached him from behind. The van was driven by P. Wayne Wright and contained four adults and six children.

Gravel thrown by the Honda’s tires broke the windshield of the Suburban, prompting Wright to attempt to pass the Honda in the right-hand outside lane. As Wright came abreast of McCorvey, the Suburban threw up a large amount of gravel, showering the Honda on its right side. McCorvey testified that he hit a big patch of gravel and lost control of his car as he attempted first to accelerate to stay ahead of the Wrights and then to slow down and drop back.

The Honda left the highway and entered the median, traveling between 52 and 62 miles per hour. McCorvey panicked and attempted to steer back onto the road, which caused the car to roll at least twice. McCor-vey and his passenger were ejected, and both suffered paralyzing injuries.

All of the witnesses who were traveling the same stretch of road at the time of the accident testified that both lanes were open for travel and that they had not seen any traffic control signs for several miles. Moreover, McCorvey’s testimony indicated that LeGrand employees may have placed “do not pass” and early warner signs on the road after the accident to make it appear as if they were there when the crash occurred.

The witnesses also agreed that there should have been more control of the project so that cars could not pass and that the right lane should have been closed. All the cars in which the witnesses were traveling suffered chipped paint and broken windshields from flying gravel, and all the drivers were extremely irate about the road conditions.

McCorvey’s experts testified that the crash was caused by the excess gravel on the road and the inadequate signing on the project. One expert cited the combination of contradictory signing, such as the use of both 25- and 55-mile-per-hour speed limit signs in the construction zone,4 the prior “no passing” signs, and the fact that both lanes were open to traffic as the cause of the accident. The lack of warning and guidance on the dangerous road caused drivers to react in ways that [44]*44might otherwise be considered unreasonable to avoid gravel damage to their cars.5

Although there was testimony that not all of the required signs were actually in place that day, McCorvey’s traffic engineering expert testified that even if all the signs had been placed correctly, UDOT’s traffic control plan was inadequate and did not comply with federal safety guidelines. The plan failed to provide drivers with sufficient warning of the hazards presented by the loose gravel. Also, it failed to physically close off the outside right lane until it had been swept, and it did not impose a speed slower than the 55-mile-per-hour speed posted for the unswept lane. On the other hand, defendants’ experts testified that the plan was adequate and that the accident was caused by driver error on McCorvey’s part.

The jury returned a verdict in favor of McCorvey and attributed fault for the accident as follows: LeGrand, 50 percent; UDOT, 28 percent; McCorvey, 10 percent; and Wright, 12 percent. UDOT’s proportionate share of liability of $1,517,800 was reduced to $250,000 pursuant to Utah Code Ann. § 63-30-84, which limits the amount of damages recoverable against the state.6 UDOT moved for a new trial, claiming that the evidence was insufficient to support the verdict against it. The trial court denied the motion.

McCorvey appeals that portion of the final judgment reducing his recovery against UDOT to $250,000.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

University of Utah Hospital v. Tullis
2025 UT 17 (Utah Supreme Court, 2025)
Richmond v. Bateman
2024 UT App 103 (Court of Appeals of Utah, 2024)
State v. Murray
2023 UT App 52 (Court of Appeals of Utah, 2023)
State v. Randall
2019 UT App 120 (Court of Appeals of Utah, 2019)
Gardner v. Gardner
2019 UT 28 (Utah Supreme Court, 2019)
State v. Oliver
2018 UT App 101 (Court of Appeals of Utah, 2018)
Larsen v. Davis County School District
2017 UT App 221 (Court of Appeals of Utah, 2017)
State v. Strieff
2015 UT 2 (Utah Supreme Court, 2015)
Jenkins v. Jordan Valley Water Conservancy District
2012 UT App 204 (Court of Appeals of Utah, 2012)
Gardner v. SPX Corporation
2012 UT App 45 (Court of Appeals of Utah, 2012)
North v. Ford Motor Co.
505 F. Supp. 2d 1113 (D. Utah, 2007)
Tindley v. Salt Lake City School District
2005 UT 30 (Utah Supreme Court, 2005)
Hatch v. Davis
2004 UT App 378 (Court of Appeals of Utah, 2004)
Johnson v. Department of Transportation
2004 UT App 284 (Court of Appeals of Utah, 2004)
Laney v. Fairview City
2002 UT 79 (Utah Supreme Court, 2002)
Parks v. Utah Transit Authority
2002 UT 55 (Utah Supreme Court, 2002)
Lyon v. Burton
2000 UT 19 (Utah Supreme Court, 2000)
Child v. Gonda
972 P.2d 425 (Utah Supreme Court, 1998)
Hart v. Salt Lake County Commission
945 P.2d 125 (Court of Appeals of Utah, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
868 P.2d 41, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mccorvey-v-utah-state-department-of-transportation-utah-1993.