Consumers Energy Co. v. United States

84 Fed. Cl. 670, 2008 U.S. Claims LEXIS 348, 2008 WL 5135913
United States Court of Federal Claims·Decided November 26, 2008·No. No. 02-1894 C·Published·Cited by 6 cases

Opinion

OPINION

DAMICH, Chief Judge.

I. INTRODUCTION

On January 7, 1983, Congress enacted the Nuclear Waste Policy Act (“NWPA”), 42 U.S.C. §§ 10101-10270 (1982), which authorized the United States Department of Energy (“DOE”) “to enter into contracts with any person who generates or holds title to high-level radioactive waste [HLW], or spent nuclear fuel [SNF], of domestic origin for the acceptance of title, subsequent transportation, and disposal of such waste or spent fuel.” Id. § 10222(a)(1). Pursuant to the NWPA, DOE drafted the Standard Con[672] tract1 providing for the Government’s acceptance, transportation, storage, and disposal of SNF and HLW, the costs of which would be borne by the “generators and owners” thereof. Id. § 10131(b)(4). Plaintiff, Consumers Energy Company (“Consumers Energy”), entered into the Standard Contract with DOE on June 3,1983. DOE was required by the Standard Contract to commence acceptance of SNF and/or HLW not later than January 31,1998. As of today, DOE has not yet accepted any SNF or HLW.

Currently before the Court is the Government’s motion for summary judgment on Consumers Energy’s claims for interest and attorney and expert fees. This Court holds that Consumers Energy is impermissibly seeking interest on a claim against the United States in contravention of 28 U.S.C. § 2516(a). Additionally, this Court holds that Consumers Energy’s claim for attorney and expert fees is not permitted under binding case law. For the reasons set forth below, the Government’s motion for partial summary judgment is GRANTED.

II. BACKGROUND

Consumers Energy is a utility company organized and incorporated in Michigan. Compl. 113. At the time the complaint was filed Consumers Energy owned the shutdown Big Rock Point Nuclear Plant (“Big Rock”) in Charlevoix, Michigan and the operating Palisades Nuclear Plant (“Palisades”) located near Covert, Michigan. Id. Big Rock’s SNF is held in on-site dry cask storage and Palisades stores its SNF in its spent fuel pool and in on-site dry cask storage. Id.

On April 29, 2005, this Court found DOE liable for partial breach of the Standard Contract; therefore, the only remaining issue before the Court is a determination of damages. Consumers Energy Co. v. United States, 65 Fed.Cl. 364, 375 (2005). According to the instant motion for partial summary judgment, Consumers Energy’s claim for an additional $17.6 million for “time price differential dollars” is prejudgment interest which is prohibited by statute. Def.’s Mot. at 3-4. Consumers Energy counters that it is claiming the financing costs incurred to construct and operate the Independent Spent Fuel Storage Installations (ISFSI) and to fabricate and load dry storage casks. Pl.’s Resp. at 3. The parties also dispute whether or not Consumers Energy is entitled to claim attorney and expert fees as damages. Def.’s Mot. at 4; Pl.’s Resp. at 4.

The damages at issue are found in Consumers Energy’s expert report by James M. Speyer of CRA International, Inc. Def.’s Mot.App. A (Speyer Rep.). According to Mr. Speyer, because DOE did not commence acceptance of SNF on or before January 31, 1998, Consumers Energy has incurred increased costs at both Big Rock and Palisades. Id. at A5; Defendant’s Proposed Findings of Uncontroverted Fact (“DPFUF”) 111.

As a result of DOE’s partial breach, Mr. Speyer concluded that Consumers Energy incurred increased costs through April 11, 2007, of $145.7 million in as-spent dollars and $163.3 million in time price differential dollars. Speyer Rep. at A5, A6; DPFUF Iff 1, 2. It is the methodology used to calculate time price differential dollars, as well as the underlying reason for the calculation, that are essential to this Court in deciding the instant motion.

As-spent dollars were calculated by determining the difference between Consumers Energy’s cash flows in the “no-breach” world and “breach” world. Speyer Rep. at A7; DPFUF H 5. The as-spent dollars were then converted to time price differential dollars by “restating] ... as-spent dollars by adjusting for inflation using the GDP implicit price deflator indices published by the U.S. Government.” Speyer Rep. at A7 (emphasis added). Mr. Speyer converted as-spent dollars into time price differential dollars to “place [Consumers Energy] in the same financial position that it would have been in had the breach of contract not taken place.” Id. at A6. Mr. Speyer’s further explains that time price differential dollars “account for [673] the fact that the plaintiff would not receive compensation until after the time it has incurred the damages.” Id. at A7; DPFUF H 6. Notably, there is no information regarding any borrowing in Mr. Speyer’s report. Consumers Energy’s calculation of time price differential dollars is simply as-spent dollars adjusted for inflation by Mr. Speyer to account for the fact that Consumers Energy would not receive a judgment, if any, until after it incurred its expenses. Speyer Rep. at A7. Included in Consumers Energy’s damages are attorney and expert fees. Id. at A12, A26. Like his increased cost calculations, Mr. Speyer also calculates attorney and expert fees in both as-spent and time price differential dollars. Id. at A25, A26. Mr. Speyer also “reserve[s] the right to adjust the price-differential dollars to the date of trial” because time price differential dollars could only be calculated up to the first quarter of 2008—the last quarter the Government published GDP price deflator data prior to the filing of the expert report. Id. at A7, A8.

III. DISCUSSION

A. Standard of Review

Free access — add to your briefcase to read the full text and ask questions with AI

Consumers Energy Co. v. United States, 84 Fed. Cl. 670, 2008 U.S. Claims LEXIS 348, 2008 WL 5135913 (uscfc 2008).

84 Fed. Cl. 670 (Consumers Energy Co. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Entergy Nuclear Vermont Yankee, LLC v. United States
95 Fed. Cl. 160 (Federal Claims, 2010)
Yankee Atomic Power Co. v. United States
94 Fed. Cl. 678 (Federal Claims, 2010)
Southern California Edison Co. v. United States
93 Fed. Cl. 337 (Federal Claims, 2010)
Energy Northwest v. United States
91 Fed. Cl. 531 (Federal Claims, 2010)
Wisconsin Electric Power Co. v. United States
90 Fed. Cl. 714 (Federal Claims, 2009)
North Star Alaska Housing Corp. v. United States
85 Fed. Cl. 241 (Federal Claims, 2009)