Commercial Union Insurance v. Boston Edison Co.

591 N.E.2d 165, 412 Mass. 545
CourtMassachusetts Supreme Judicial Court
DecidedApril 27, 1992
StatusPublished
Cited by41 cases

This text of 591 N.E.2d 165 (Commercial Union Insurance v. Boston Edison Co.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commercial Union Insurance v. Boston Edison Co., 591 N.E.2d 165, 412 Mass. 545 (Mass. 1992).

Opinion

Abrams, J.

The plaintiffs, former coowners of the building at One Beacon Street in Boston (building), brought an action for breach of contract and restitution for money paid by mutual mistake against the Boston Edison Company (Edison), claiming that Edison had overcharged them for steam usage at the building between January, 1974, and January 10, 1979. Edison, alleging that the overcharge was the result of the plaintiffs’ improper installation of the steam metering system in the building, and that the plaintiffs had refused to accept Edison’s reasonable settlement offer for the overcharge, asserted a counterclaim for violation of G. L. c. 93A (1990 ed.). The judge dismissed Edison’s counterclaim before trial for failure to state a claim on which 'relief could be granted, and denied Edison’s motion for leave to file an amended counterclaim. At trial, the judge directed a verdict for the plaintiffs on liability on their restitution claim, and the jury awarded damages of $650,000 on that claim. The jury found for Edison on the plaintiffs’ contract claim. The judge entered final judgment on the plaintiffs’ jury verdict in the amount of $1,590,371. We allowed Edison’s application for direct review. On appeal, Edison claims errors based on the admission in evidence of a computer simulation and expert opinions based on the simulation. Edison also challenges *547 the amount of damages and the rate of interest applied to the judgment. The plaintiffs, in their cross-appeal, argue that the judge erred in not directing a verdict or granting judgment notwithstanding the verdict for them on their contract claim. We affirm.

Facts. Under the terms of an agreement between Edison and the plaintiffs, Edison supplied and the plaintiffs purchased steam for the air conditioning, cooking, and space and water heating systems in the building.

Due to a problem with the metering system of which the parties were unaware, the meter overregistered the amount of steam being used. The problem came to light when the • building manager, having taken several unsuccessful steps to reduce the steam bills by conserving steam usage in the building, finally shut down the steam system entirely, only to discover that the low-range steam meter nevertheless continued to register steam flow at eighteen percent. The problem was traced to the meter having been defectively installed when the building was built. During the time that the faulty metering system was in place, Edison had charged the plaintiffs $3,756,531.30 for steam used.

Edison does not dispute that it overcharged the plaintiffs during the relevant time period; rather, it disputes the amount of the overcharge. Prior to the litigation, Edison reviewed numerous steam usage charts for the relevant period and, applying a “correction formula” recommended by the meter manufacturer, concluded that the meter was off by four percent, rather than the eighteen percent recorded by the building manager and asserted by the plaintiffs. Edison nevertheless decided to split the difference between its and the plaintiffs’ estimated percentage of error. Basing its overcharge calculations on a system error of eleven percent, Edison offered $93,764.86 to the plaintiffs. Edison took the position that this figure constituted an estimate in lieu of an accurate reading, which the plaintiffs were bound to accept *548 under the terms of the agreement. 2 The plaintiffs rejected Edison’s calculations as premised on the erroneous assumption that the percentage of error had remained constant throughout the five-year period.

The plaintiffs relied on a computer simulation to make their own calculations of actual steam usage. The computer program, called TRACE (Trane Air Conditioning Economics), consists of scientific formulae and algorithms 3 concerning heat transfer, building materials, operating characteristics of various heating and air handling equipment, and weather history, among other things. To generate a simulation, the computer program uses data specifying a particular building’s construction materials, operating patterns, architectural details, latitude, longitude, outside air flow, and heating, ventilating and air conditioning equipment, among other things.

Evidentiary issues regarding TRACE. Edison moved in limine to exclude the TRACE evidence on the grounds that the data and equations used in the simulation were neither accurate nor complete, and that the program had not achieved general acceptance by the community of scientists involved. The judge, defining the relevant scientific community as heating, ventilating and air conditioning (HVAC) and building design professionals, determined that this group had accepted TRACE as scientifically reliable. At trial, following a voir dire of the plaintiffs’ expert, the judge further found that the program data and equations were accurate and complete, and ruled admissible the TRACE evidence and related expert testimony.

*549 Edison claims error in the admission of the TRACE evidence. First, Edison argues that the results "of the TRACE simulation are inadmissible hearsay, and the judge therefore erred in admitting them in evidence. We disagree.

The function of computer programs like TRACE “is to perform rapidly and accurately an extensive series of computations not readily accomplished without use of a computer.” Schaeffer v. General Motors Corp., 372 Mass. 171, 177 (1977). We permit experts to base their testimony on calculations performed by hand, cf., e.g., Anthony’s Pier Four, Inc. v. HBC Assocs., 411 Mass. 451, 478 (1992); Kroeger v. Stop & Shop Cos., 13 Mass. App. Ct. 310, 323 (1982). There is no reason to prevent them from performing the same calculations, with far greater rapidity and accuracy, on a computer. Therefore, as we indicated in Schaeffer, supra at 177-178, we treat computer-generated models or simulations like other scientific tests, and condition admissibility on a sufficient showing that: (1) the computer is functioning properly; (2) the input and underlying equations are sufficiently complete and accurate (and disclosed to the opposing party, so that they may challenge them); and (3) the program is generally accepted by the appropriate community of scientists. See Commonwealth v. Fatalo, 346 Mass. 266, 269 (1963).

Edison urge.s us to reject the computer simulation evidence. We decline to do so. We note that we are not the first jurisdiction to recognize that computer models or simulations may be used to assist the fact finder. Generally courts have permitted computer models in cases not easily susceptible of other forms of proof. See, e.g., Seattle Master Builders Ass’n v. Pacific Northwest Elec. Power & Conservation Planning Council, 786 F.2d 1359, 1370 (9th Cir. 1986), cert, denied, 479 U.S. 1059 (1987) (allowing use of computer simulations of value of energy conservation methods based on principles derived from American Society of Heating, Refrigerating and Air Conditioning Engineers “Handbook of Fundamentals” to determine energy conservation value); Perma Research & Dev. Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Commonwealth v. Cole
41 N.E.3d 1073 (Massachusetts Supreme Judicial Court, 2015)
America's Growth Capital, LLC v. PFIP, LLC
73 F. Supp. 3d 127 (D. Massachusetts, 2014)
Commonwealth v. Caruso
4 N.E.3d 1283 (Massachusetts Appeals Court, 2014)
Partylite Gifts, Inc. v. MacMillan
895 F. Supp. 2d 1213 (M.D. Florida, 2012)
Rev-Lyn Contracting Co. v. Patriot Marine, LLC
760 F. Supp. 2d 162 (D. Massachusetts, 2011)
Commonwealth v. Whitlock
906 N.E.2d 995 (Massachusetts Appeals Court, 2009)
F.W. Webb Co. v. Daco Mechanical & Contracting Co.
24 Mass. L. Rptr. 642 (Massachusetts Superior Court, 2008)
Pitcherville Sand & Gravel, Inc. v. Holden Sand & Gravel Co.
24 Mass. L. Rptr. 243 (Massachusetts Superior Court, 2008)
Quinn v. Mar-Lees Seafood, LLC
871 N.E.2d 511 (Massachusetts Appeals Court, 2007)
Lorraine v. Markel American Insurance
241 F.R.D. 534 (D. Maryland, 2007)
State v. Sipin
130 Wash. App. 403 (Court of Appeals of Washington, 2005)
State v. Swinton
847 A.2d 921 (Supreme Court of Connecticut, 2004)
Massachusetts Port Authority v. City of Boston
17 Mass. L. Rptr. 125 (Massachusetts Superior Court, 2003)
AB & Palumbo Electrical Contractors, Inc. v. John T. Callahan & Sons, Inc.
15 Mass. L. Rptr. 182 (Massachusetts Superior Court, 2002)
Portland Natural Gas Transmission System v. Maritimes & Northeast Pipeline, L.L.C.
15 Mass. L. Rptr. 134 (Massachusetts Superior Court, 2002)
Northeast Battery & Alternator Co. v. Seaco Insurance
14 Mass. L. Rptr. 579 (Massachusetts Superior Court, 2002)
Sax v. Sax
762 N.E.2d 888 (Massachusetts Appeals Court, 2002)
Commonwealth v. Serge
58 Pa. D. & C.4th 52 (Lackawanna County Court of Common Pleas, 2001)
People v. Cauley
32 P.3d 602 (Colorado Court of Appeals, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
591 N.E.2d 165, 412 Mass. 545, Counsel Stack Legal Research, https://law.counselstack.com/opinion/commercial-union-insurance-v-boston-edison-co-mass-1992.