Pitcherville Sand & Gravel, Inc. v. Holden Sand & Gravel Co.

24 Mass. L. Rptr. 243
CourtMassachusetts Superior Court
DecidedJune 20, 2008
DocketNo. 200700531D
StatusPublished

This text of 24 Mass. L. Rptr. 243 (Pitcherville Sand & Gravel, Inc. v. Holden Sand & Gravel Co.) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pitcherville Sand & Gravel, Inc. v. Holden Sand & Gravel Co., 24 Mass. L. Rptr. 243 (Mass. Ct. App. 2008).

Opinion

Lemire, James R., J.

The plaintiff, Pitcherville Sand & Gravel, Inc. (“Pitcherville”), was hired by the defendant, Holden Sand & Gravel, Company, Inc. (“Holden”), to deliver fill on a construction project for the defendant, Town of Ashburnham (“Ashburnham”). Holden obtained a bond securing the construction project from the defendant, Travelers Casualty & Surety Company, Inc. (“Travelers”), which it furnished to Ashburnham. After Holden failed to pay Pitcherville for the fill, Pitcherville sued the defendants alleging breach of contract (Count I), unjust enrichment (Count II), breach of contract as a third-party beneficiary (Count III), negligence (Count IV), negligent misrepresentation (Count V), and violations of G.L.c. 93A, §11 (Count VI) against Holden, breach of contract as a third-party beneficiaiy (Count VII), negligence (Count VIII), negligent misrepresentation (Count IX), and violations of G.L.c. 93A, §11 (Count X) against Ashburnham, and breach of contract as a third-party beneficiaiy (Count XI), two counts of negligent misrepresentation (Counts XII and XIII), violation of G.L.c. 176D (X3V], and violations of G.L.c. 93A, §11 (Count XV) against Travelers. This matter is before the court on Ashburnham’s motion for summary judgment as to Counts VII, VIII, IX, and X and Travelers’ motion for summaiy judgment as to Counts X3, XII, XIII, XTV, and XV pursuant to Mass.R.Civ.P. 56. For the following reasons, the defendants’ motions for summaiy judgment are allowed in part and denied in part.

BACKGROUND

The undisputed facts and the disputed facts viewed in the light most favorable to the non-moving party, as revealed by the summaiy judgment record, are as follows.

On August 22, 2005, Ashburnham published a request for bids to provide fill and perform site work (“the Work”) on a project to construct a new public safety facility (“the Project”). Pursuant to the bidding process, Ashburnham made available site specifications for potential bidders to review. The specifications described the Work as follows:

1) [C]ut & fill approved materials & construction operations to stabilize the entire site per the grading plan, including (but not limited to) wetland replication. 2) (E)rosion control to stabilize the site[.) 3) Modification of existing guardrail along Central Street where indicated on the plans. 4) (Rjemoval of existing concrete headwall adjacent to Central Street on the northeastern side of the site, installation of new manhole & new HDPE storm drain [244]*244extension with rip-rap spillway. 5) [CJonstruction of a new stormwater detention basin, outlet structure & HDPE piping, & spillway rip rap. 6) [EJxcavation as required to bring the site to proposed finished floor elevation where structures will be located. 7) [Ejxcavation as required to bring the site to sub-grade (below pavement gravel) in all exterior vehicle circulation areas).] 8) [E]xcavation and site stabilization as required to bring the site to finished grade in vegetated areas.

In addition, the site specifications dictated that “ [performance and payment bonds in the penal sum of 100% of the total contract price will be required for any contract awarded as a result of this bid. The Contractor shall furnish performance and payment bonds within five (5) days of such notification by the Purchasing Agent.” The site specifications also stated that “)t]his bid is subject to the requirements of Chapter 30B of the Massachusetts General Laws.” Holden submitted a bid to perform the Work. On September 26, 2005, Ashburnham accepted Holden’s bid.

Pursuant to the Project specifications, Holden retained Insurance Marketing Agencies, Inc. (“IMA”) to obtain a bond. For Holden, IMA submitted a “Performance & Payment” bond application to Travelers, which described the Work as:

Insured is delivering 40,00 yards of fill to Central Street (Route 101), Ashburnham. MA and then grading it.
Insured has 150,000 yards of fill on hand which our insured owns and as such does not need to purchase any fill for this job.
Total contract price is $589,500, of which 85% is for the cost of fill which our client already owns. Job should take 45 days and is due to begin on 09/26/05.

Within the application, an IMA agent wrote “$589,500" in a space titled ’’Performance Bond Amt." IMA left blank the space for “Payment Bond Amt.”

Subsequently, Travelers issued a “Contract Bond” (“the Bond”) to Holden for $589,500.00. The terms of the Bond stated that “the Principal has entered, or is about to enter, into a written Agreement with the Obligee for the supply of Jill and site work at New Public Safety Building Route 101, Main Street, Ashburnham, MA as is more specifically set forth in said Agreement, to which reference is hereby made.”

Sometime thereafter, Holden and Pitcherville entered an agreement whereby Pitcherville would supply fill to the Project. Pitcherville complied with this agreement, however Holden failed to pay Pitcherville.1 On December 15, 2006, Pitcherville notified Ashburnham that Holden owed Pitcherville for materials it supplied to the Project. On December 20, 2006, Pitcherville sent a letter to Holden requesting payment of $66,657.80.2 On January 5, 2007 and on January 8, 2007, Pitcher-ville sent letters to Ashburnham requesting information as to any bonds that were applicable to the Project. On January 9, 2007, Ashburnham responded to Pitcherville stating that the Bond covering the project was a “performance” bond. However Ashburnham would not disclose the terms of the Bond.

Nevertheless, on January 25, 2007, Pitcherville made a claim on the Bond to Travelers. On March 19, 2007, Travelers denied Pitcherville’s claim, stating that the Bond was a “supply bond." On March 19, 2007, Pitcherville sued the defendants to recover payment for the materia] it provided on the Project. On April 22, 2008, Ashburnham and Travelers filed motions for summary judgment pursuant to Mass.R.Civ.P. 56.

DISCUSSION

Summary judgment is appropriate if there exists no genuine issue of material fact and the moving party is entitled to judgment as a matter of law. Mass.R.Civ.P 56(c); Cassesso v. Comm’r of Corr., 390 Mass. 419, 422 (1983); Cmty. Nat’l Bank v. Dawes, 369 Mass. 550, 553 (1976). It is the moving party’s burden to demonstrate affirmatively the absence of a triable issue, and that the summary judgment record entitles him to judgment as a matter of law. Pederson v. Time, Inc., 404 Mass. 14, 16-17 (1989). The moving party may satisfy this burden either by submitting affirmative evidence that negates an essential element of the opposing party’s case or by demonstrating that the opposing party has no reasonable expectation of proving an essential element of his case at trial. Flesner v. Technical Commc’ns Corp., 410 Mass. 805, 809 (1991); Kourouvacilis v. Gen. Motors Corp., 410 Mass. 706, 716 (1991).

A. Breach of Contract as a Third-Party Beneficiary against Ashburnham (Count VII)

Pitcherville argues that it is a third-party beneficiary of the contract between Holden and As-hburnham, which Pitcherville contends required Ashburnham to ensure that Holden obtained a payment bond.3 Conversely, Ashburnham maintains that only a performance bond was required by its agreement with Holden, meaning Pitcherville was not a third-party beneficiary.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Whitinsville Plaza, Inc. v. Kotseas
390 N.E.2d 243 (Massachusetts Supreme Judicial Court, 1979)
Wightman v. Town of Methuen
526 N.E.2d 1079 (Massachusetts Appeals Court, 1988)
Pederson v. Time, Inc.
532 N.E.2d 1211 (Massachusetts Supreme Judicial Court, 1989)
Tambolleo v. Town of West Boylston
613 N.E.2d 127 (Massachusetts Appeals Court, 1993)
Dodd v. Commercial Union Insurance
365 N.E.2d 802 (Massachusetts Supreme Judicial Court, 1977)
Gilmore v. Commonwealth
632 N.E.2d 838 (Massachusetts Supreme Judicial Court, 1994)
Community National Bank v. Dawes
340 N.E.2d 877 (Massachusetts Supreme Judicial Court, 1976)
Jet Line Services, Inc. v. American Employers Insurance
537 N.E.2d 107 (Massachusetts Supreme Judicial Court, 1989)
Van Dyke v. St. Paul Fire & Marine Ins. Co.
448 N.E.2d 704 (Massachusetts Supreme Judicial Court, 1983)
Commercial Union Insurance v. Boston Edison Co.
591 N.E.2d 165 (Massachusetts Supreme Judicial Court, 1992)
Kourouvacilis v. General Motors Corp.
575 N.E.2d 734 (Massachusetts Supreme Judicial Court, 1991)
Flesner v. Technical Communications Corp.
575 N.E.2d 1107 (Massachusetts Supreme Judicial Court, 1991)
Weaver v. Commonwealth
438 N.E.2d 831 (Massachusetts Supreme Judicial Court, 1982)
Madsen v. Erwin
481 N.E.2d 1160 (Massachusetts Supreme Judicial Court, 1985)
Cassesso v. Commissioner of Correction
456 N.E.2d 1123 (Massachusetts Supreme Judicial Court, 1983)
Polaroid Corp. v. the Travelers Indemnity Co.
610 N.E.2d 912 (Massachusetts Supreme Judicial Court, 1993)
United States Leasing Corp. v. City of Chicopee
521 N.E.2d 741 (Massachusetts Supreme Judicial Court, 1988)
Lodge v. District Attorney for the Suffolk District
486 N.E.2d 764 (Massachusetts Appeals Court, 1985)
Massachusetts Employers Insurance Exchange v. Propac-Mass, Inc.
420 Mass. 39 (Massachusetts Supreme Judicial Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
24 Mass. L. Rptr. 243, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pitcherville-sand-gravel-inc-v-holden-sand-gravel-co-masssuperct-2008.