Massachusetts Port Authority v. City of Boston

17 Mass. L. Rptr. 125
Massachusetts Superior Court·Decided November 18, 2003·No. No. 012731BLS2·Published·Cited by 2 cases

Opinion

Botsford, J.

At the heart of this case is a proposed new runway for Logan International Airport. In 1976, a permanent injunction was entered in an earlier case between many of these parties concerning another proposed runway at the airport, and the plaintiff Massachusetts Port Authority (Massport) brings this case to seek relief from that injunction. Massport claims that even if one assumes the 1976 injunction applies to the proposed new runway at all — an assumption Massport disputes — the underlying rationale and purpose for that injunction have now been satisfied and in any event, changed circumstances warrant relief from the injunction’s prohibitions. The defendant City of Boston (Boston) and the intervening parties — the cities of Chelsea (Chelsea) and Somerville (Somerville), the town ofWinthrop (Winthrop), and five individuals3 disagree with each of these propositions, and claim no basis for lifting the injunction has been shown.4 Boston and the intervening defendants have also filed counterclaims against Massport. Among other grounds, these counterclaims assert that Massport has not complied with the Massachusetts Environmental Policy Act (MEPA) G.L.c. 30, §§61-62H, in relation to its proposed new runway and the larger “Airside Improvements Planning Project” (Airside Project) of which the runway is a significant part.

The earlier procedural history of this case may be briefly stated. Following the entry of the various intervening defendants, Massport moved for judgment on the pleadings concerning two of the claims in its complaint, and also moved to dismiss most of the counterclaims that Boston and the intervening defendants had filed. The motion for judgment on the pleadings was denied,5 and the motion to dismiss the counterclaims was allowed in part and denied in part.6 Thereafter the parties conducted discovery, and the case was tried before me without a jury in late J anuary and early February 2003, with post-trial argument extending to June 2003.

The case has two distinct parts: Massport’s complaint, which focuses entirely on the 1976 injunction (referred to as “the injunction case”); and the counterclaims brought by Boston and the interveners, which primarily relate to Massport’s compliance with MEPA and related claims. This memorandum of decision concerns solely the injunction case; the counterclaims are dealt with in a separate memorandum of decision.

Set forth below are my findings of fact on the injunction claims, based on the evidence presented at trial, followed by a discussion of the legal issues raised. For the reasons stated there, I conclude the injunction should be modified.

Findings of Fact7

The 1974 Massport Runways Project, the Ensuing Litigation and the Injunctions8

In 1974, and today, Logan International Airport (Logan Airport, or Logan) has five operating Runways to accommodate the arrival and departure of all aircraft to and from the airport.9 On May 17, 1974, Massport entered into a contract with the Perini Corporation for the construction at Logan of a new, 3830-foot Runway called “GA/STOL Runway 14-32"10 with associated taxiways, lighting and marking, as well as extensions of Runways 9 and 4L (4 left) with associated taxiways, lighting and marking; certain other taxiway and service road improvements were also included. The entire construction project was known as the ’’Runways Project." Among the proposed restrictions for the new GA/STOL Runway portion of the Runways Project were that (a) no turbo jet or turbo fan jet powered aircraft would use the Runway; and (b) operations on it would be limited to take offs to, and landings from, the southeast. These restrictions were set out in a memorandum of understanding between Massport and the Massachusetts Executive Office of Transportation and Construction (EOTC). The agreement between Massport and its contractor Perini was that unless the approval of the Federal Aviation Administration (FAA) were obtained for the proposed Runway restrictions, Massport could terminate the contract without obligation.

Massport did not file an environmental impact report pursuant to G.L.c. 30, §62, of MEPA (§62),11 before contracting with Perini, or before construction commenced on the Runways Project. Massport took the position that it was exempt from the requirement to comply with that section of MEPA by virtue of its own enabling act, and further because it had dredged and filled the Bird Island Flats in Boston harbor and had made certain plans in regard to the Runways Project before July 1, 1973, the date that §62 became effective.

On May 18, 1974, at the request of the EOTC, Massport submitted to the EOTC an environmental assessment form, although continuing to contest the applicability of §62 to Massport or to the Runways Project. In the environmental form, Massport determined that the Runways Project would not cause significant environmental damage, and therefore that no further environmental reports would be filed (the “negative assessment”).

[167]*167On May 21, 1974, the FAA indicated its consent to the Runway restrictions set out in Massport’s memorandum of understanding with the EOTC. Massport then gave Perini permission to proceed, and work on the Runways Project commenced on May 23, 1974. The next day, May 24, Boston filed a petition for declaratory relief in the Superior Court, seeking to enjoin further work on the Runways Project.

The Secretary of Environmental Affairs (the Secretary) rejected Massport’s negative assessment on July I, 1974, having determined that the Runways Project might cause damage to the environment so as to require the preparation of a final environmental impact report (EIR). On July 7, 1974, the Secretary and the Secretary of Transportation and Construction filed a complaint against Massport, seeking to enjoin further construction. After trial of Boston’s suit against Massport, the Secretaries’ case was consolidated with it and submitted to the court on the same record. (The two actions — the one initiated by Boston, and the second initiated by the Secretaries — are referred to hereafter as “the 1974 actions.”)

On August 26, 1974, a judge of this court (Mason, J.), ruled in the 1974 actions that §62 of MEPA applied to Massport, that the Runways Project had commenced after the effective date of §62, and that the Runways Project might cause damage to the environment such that full compliance with MEPA was required. The court entered a judgment containing a permanent injunction that barred Massport “from any further construction of the Runways Project at Logan until [Massport] has published a final environmental impact report and otherwise complied with the provisions of G.L.c. 30, §§61 and 62.” Massport appealed. In February 1975, the Supreme Judicial Court affirmed the Superior Court judgment. See Secretary of Environmental Affairs v. Massachusetts Port Auth’y, 366 Mass. 755 (1975).

While Massport’s appeal of the Superior Court judgment was pending, the Secretary determined in October 1974 that Massport’s draft EIR, submitted two months earlier, did not adequately and properly comply with §62 of MEPA. On April 30, 1975, Massport submitted a final EIR for the Runways Project to the Secretary. The Secretary determined that the final EIR failed to comply with MEPA on June 6, 1975.

Free access — add to your briefcase to read the full text and ask questions with AI

Massachusetts Port Authority v. City of Boston, 17 Mass. L. Rptr. 125 (Mass. Ct. App. 2003).

17 Mass. L. Rptr. 125 (Massachusetts Port Authority v. City of Boston) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Massachusetts Port Authority v. City of Boston
17 Mass. L. Rptr. 158 (Massachusetts Superior Court, 2003)