AB & Palumbo Electrical Contractors, Inc. v. John T. Callahan & Sons, Inc.

15 Mass. L. Rptr. 182
CourtMassachusetts Superior Court
DecidedAugust 23, 2002
DocketNo. 012308
StatusPublished

This text of 15 Mass. L. Rptr. 182 (AB & Palumbo Electrical Contractors, Inc. v. John T. Callahan & Sons, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
AB & Palumbo Electrical Contractors, Inc. v. John T. Callahan & Sons, Inc., 15 Mass. L. Rptr. 182 (Mass. Ct. App. 2002).

Opinion

Donohue, J.

The plaintiff in this action, AB & Palumbo Electrical Contractors (“Palumbo”), an electrical subcontractor, alleges that the defendant City of Worcester (“the City”), acting as general contractor on the renovation and construction of a public school, breached the terms of the subcontract when it refused to pay for work completed, but allegedly not included, in the contract’s specifications. The plaintiff moved for summary judgment, requesting declaratory judgment pursuant to G.L.c. 231A on the issue of breach and for its claim of unfair and deceptive acts and practices against the City. The City opposed the motion and [183]*183cross-moved for summary judgment in its favor on all claims. Defendant Royal Steam Heater (“Royal Steam”) also opposed Palumbo's motion for summary judgment and cross-moved for summary judgment on any claims against it. For the following reasons, the plaintiffs motion for summary judgment is DENIED, the City’s motion for summary judgment is DENIED in part and ALLOWED in part, and Royal Steam’s motion for summary judgment is DENIED.

BACKGROUND

This dispute involves the construction and renovation of the Forest Grove Middle School in Worcester. Because Forest Grove is a public school, the project must be bid according to G.L.c. 149, §44. As the awarding authority on the project, prior to soliciting bids from any prospective general contractors or subcontractors pursuant to G.L.c. 149, §44B, Worcester prepared the project specifications. Palumbo submitted a sub-bid for the electrical work under Division 16100 and was subsequently awarded a subcontract to furnish $1,477,756.00 of electrical labor and material for the project. Royal Steam submitted a sub-bid for the heating, ventilation and air conditioning (“HVAC”) work under Division 15600 and was subsequently awarded a subcontract to furnish $2,345,000.00 of HVAC labor and materials for the project. Both subcontractors filed the bids directly with the City, which the City then opened and provided to the bidders for the project’s general contracting work. John T. Callahan & Sons (“Callahan”) was awarded the general contract for the project.

The original specifications for the Division 16100 section were issued in February 2000 and contained a section, 1.05(E)(2), which stated the following:

[M]otors and all electro-mechanical systems and equipment will be furnished, set in place, installed, wired, and tested under other Sections.

On or about March 3, 2000, Stephen O’Day, an estimator for Palumbo contacted Steve Smith at RES Engineering, Inc., the firm that drafted the specifica- and served as a resource to the architect on the project, seeking clarification of that language and sections of the specifications. Smith discussed questions with other members of the project at and drafted a response.

In May of 2001, Palumbo became aware that it was expected to complete certain wiring to the HVAC equipment that it believed was not included in its scope of work. The disputed wiring is the electrical power wiring from the main electrical panel board, where electrical current enters the building, to the disconnect switches mounted on or adjacent to the various HVAC equipment Royal installed throughout the building. Palumbo proceeded with the disputed wiring under protest and now claims that the City owes it compensation for what it considers to be extra work on the project under the contract documents.

DISCUSSION

I. Declaratory Judgment

Summary judgment is granted where there are no genuine issues of material fact and the moving party is entitled to judgment as a matter of law. Kourouvacilis v. General Motors Corp., 410 Mass. 706, 716 (1991); Cassesso v. Commissioner of Correction, 390 Mass. 419, 422 (1983); Mass.R.Civ.P. 56(c). The moving party bears the burden of affirmatively demonstrating that there is no triable issue of fact. Pederson v. Time, Inc., 404 Mass. 14, 17 (1989). At bar, each party contends that, because its suggested interpretation of the contract language is unarguably correct, there are no material facts in dispute. Accordingly, the parties say, the underlying contract claim may be resolved by this court as a matter of law. See USM Corp. v. Arthur D. Little Sys., Inc., 28 Mass.App.Ct. 108, 116 (1989) (where material facts are not in dispute, interpretation of contract is question of law for the court). The court is not persuaded, however, that the parties’ suggestions as to the interpretation of the Division 16100 project specifications can be determined without resolving issues of fact.

Where the wording of a contract is unambiguous, the agreement must be enforced according to its terms. See In re Biotech Corp., 186 F.3d 1356 (D.Mass. 1999). A party’s mere claim of ambiguity may not defeat a motion for summary judgment “if the documents do not reflect ambiguity on the point in question, and the party resisting summary judgment adduces no evidence of ambiguity.” US Trust v. Henley Warren Mgt., Inc., 40 Mass.App.Ct. 337, 343 (1996). Thus, where the language of a contract is clear and unambiguous, summary judgment is an appropriate vehicle for judicial interpretation because the court interpret the meaning of the contract as a matter law without resort to extrinsic evidence or determinations of fact. ER Holdings, Inc. v. Norton Co., 735 F.Sup. 1094, 1097 (D.Mass. 1990). On the other hand, the contract language is indeed ambiguous, a finder must resolve the ambiguity by considering factual evidence offered by the parties to support differing interpretations. Commercial Union Ins. v. Boston Edison Co., 412 Mass. 545, 557 (1992); also Trafton v. Custeau, 338 Mass. 305, 307-08 In such circumstances, summary judgment is inappropriate.

The test for resolving disputes as to which party the blame for a construction contract’s ambiguis the degree of obviousness of the omission, error, discrepancy in the specifications. John F. Miller Co., v. George Fichera Construction Corp., 7 Mass.App.Ct. 494, 498-99 (1979). Thus, if the discrepis subtle, so that a subcontractor who examines specifications reasonably conscientiously might a requirement which is out of sequence or ineptly expressed, the burden of the error falls on the issuer the specifications. Id. Conversely, a subcontractor [184]*184who is presented with an obvious omission, inconsistency or discrepancy is required to ask for clarification prior to bidding "if he intends to bridge the crevasse in his favor.” Id.

Relevant Sections of the Specifications

The original specifications for the Division 16100 electrical section were issued in February 2000. Paragraph 1.04, section D on page 16100-3 of the specifications pertains to the scope of the electrical subcontractors work and reads, in relevant part, as follows:

(D) Description of Work

A. Perform work and provide material and equipment as shown on Drawings and/or as specified and/or indicated in this Section of the Specifications. Completely coordinate work of this Section with work of other trades and provide a complete and fully functional installation.
D. Work shall include, but not be limited to the following:
(1) Main primary and secondary electrical services.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hardware Specialties, Inc. v. Mishara Construction Co.
311 N.E.2d 564 (Massachusetts Appeals Court, 1974)
Pederson v. Time, Inc.
532 N.E.2d 1211 (Massachusetts Supreme Judicial Court, 1989)
Manning v. Zuckerman
444 N.E.2d 1262 (Massachusetts Supreme Judicial Court, 1983)
Trafton v. Custeau
155 N.E.2d 159 (Massachusetts Supreme Judicial Court, 1959)
John F. Miller Co. v. George Fichera Construction Corp.
388 N.E.2d 1201 (Massachusetts Appeals Court, 1979)
Commercial Union Insurance v. Boston Edison Co.
591 N.E.2d 165 (Massachusetts Supreme Judicial Court, 1992)
Kourouvacilis v. General Motors Corp.
575 N.E.2d 734 (Massachusetts Supreme Judicial Court, 1991)
Cassesso v. Commissioner of Correction
456 N.E.2d 1123 (Massachusetts Supreme Judicial Court, 1983)
United States Leasing Corp. v. City of Chicopee
521 N.E.2d 741 (Massachusetts Supreme Judicial Court, 1988)
USM Corp. v. Arthur D. Little Systems, Inc.
546 N.E.2d 888 (Massachusetts Appeals Court, 1989)
Planned Parenthood Federation of America, Inc. v. Problem Pregnancy of Worcester, Inc.
398 Mass. 480 (Massachusetts Supreme Judicial Court, 1986)
USTrust v. Henley & Warren Management, Inc.
663 N.E.2d 1238 (Massachusetts Appeals Court, 1996)
Hyppolite ex rel. Hyppolite v. City of Boston
1 Mass. L. Rptr. 31 (Massachusetts Superior Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
15 Mass. L. Rptr. 182, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ab-palumbo-electrical-contractors-inc-v-john-t-callahan-sons-inc-masssuperct-2002.