Columbus Pipe & Equipment Co. v. Sefansky

90 N.W.2d 492, 352 Mich. 539, 1958 Mich. LEXIS 473
CourtMichigan Supreme Court
DecidedJune 11, 1958
DocketDocket 92, Calendar 47,422
StatusPublished
Cited by19 cases

This text of 90 N.W.2d 492 (Columbus Pipe & Equipment Co. v. Sefansky) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Columbus Pipe & Equipment Co. v. Sefansky, 90 N.W.2d 492, 352 Mich. 539, 1958 Mich. LEXIS 473 (Mich. 1958).

Opinion

Kavanagh, J.

Plaintiff instituted this tort action, founded in fraud, against defendant. In a trial in the circuit court without a jury the court rendered a judgment in fraud for the plaintiff against the defendant in the sum of $3,879.68 plus interest in the sum of $301.

Defendant appeals to this Court, claiming the circuit court erred in holding that all the elements of actionable fraud had been proven by the plaintiff by a preponderance of the evidence.

Defendant, David Sefansky, in July, 1955, was engaged in the development of land for building purposes in the Detroit area. He was confronted with the lack of water and sewer pipe available in Detroit, and began looking for other sources of supply. A contact furnished plaintiff’s name as a company that would be able to supply such pipe. Defendant, after *541 oral negotiations with plaintiff, ordered the desired pipe in writing. In this letter ordering the pipe was enclosed a check in the amount of $24,344.40, being 1/2 of the total contract price. The letter was on the letterhead of David Sefansky, defendant herein, and read as follows:

“July 29, 1955

“Columbus Pipe & Equipment Company “Columbus, Ohio “Gentlemen:

“Please accept this as a purchase order for the following quantities of water pipe:

“7,419 lineal feet of 8 inch Class 150 cast iron mechanical joint (your WWP 421)

(a) $2.79 per ft. $20,699.01 “14,578 lineal feet of 6 inch Class 150 cast iron mechanical joint (your WWP 421)

(a) $1.92 per ft. 27,989.76

Total price........$48,688.77

“Delivery to be as follows — 8-inch to be shipped at once; 6-ineh pipe to follow within 2 weeks. Order to be completed within 30 days of above date.

“The pipe is to be delivered to ‘Winshall Villa’ subdivision which is located 1/4 mile west of Gratiot avenue on 15 Mile road, Clinton township, Michigan, to the attention of Tullio Marroeco Construction Company.

“Enclosed herewith is check in the amount of $24,344.40. Balance is to be billed to Tullio Marroc-co Construction Company, 16073 Bell avenue, East Detroit, Michigan.

“Thank you for your courtesy and co-operation.

“Sincerely,

/s/ David Sefansky David Sefansky”

*542 Plaintiff made several shipments of pipe, with sight drafts attached, directed to Tullio Marroeco Construction Company (contractor installing pipe), which drafts were paid-as presented by the defendant, David Sefansky. The last carload was shipped without sight drafts, in error, and could not be delivered. Plaintiff, after a telephone conversation with defendant, released said car to the defendant. The telephone conversation was immediately confirmed by letter from the plaintiff, stating, in substance, as follows:

“Dave, I am personally responsible for releasing this car to you, although I was told not to' release this car until payment was received. Personally I felt that our relations had been very satisfactory in the past, and I felt certain that you would treat me in the same way.”

The balance due on this last carload was never paid. Defendant claimed that before payment he should be given credit for certain.shipping charges. This plaintiff, denied. Hence, plaintiff eventually brought this suit in fraud, claiming: that defendant made a material representation to plaintiff; that it was false.; that when defendant made it he knew that it was false; that he made it with the intention that it should be acted upon by plaintiff; that plaintiff acted in reliance upon it, and that he thereby suffered injury. Plaintiff alleges that defendant’s representation that he was an agent for a disclosed principal, and that they should bill him for the balance, was a material representation, and that it was false by reason of the fact that there was no principal except Sefansky. Plaintiff further alleges that Tullio Marroeco Construction Company never authorized Sefansky to act for them; that he never had authority to act for them; that he had no authority to write such a letter; that Sefansky admits that when he *543 made this representation he knew that it was. false; that he admits that he was misleading the plaintiff; that hé-admits that he had no authority to act for anybody, let alone the Tullio Marrocco Construction Company, It is plaintiff’s claim that it acted in reliance upon such representation by obtaining a Dunn and Bradstreet report on Tullio Marrocco Construction Company, and thereafter set up a ledger account in the name of Tullio Marrocco Construction Company, finally sending statements to that company; that as a result of the failure of the last carload to be paid they have been damaged.

This Court has stated many times the proposition that it will not disturb the findings of the lower court who had the opportunity to hear the witnesses testify, observe their demeanor on the stand, and who certainly, normally, would be in a better position to judge the truth of their testimony than this Court, excepting in the instances where the testimony clearly preponderates against the finding of the lower-court. Jones v. Eastern Michigan Motorbuses, 287 Mich. 619; Eagan v. Edwards, 294 Mich 260; Mahoney v. Lincoln Brick Co., 304 Mich 694; Green v. Woods, 325 Mich 649; Moller v. Sirhal, 342 Mich 391; Zarecki v. Hatch, 347 Mich 138 (62 ALR2d 284).

The doctrine is well established that fraud will not be presumed, but must be proved. Robert v. Morrin Estate, 27 Mich 306; Brown v. Dean, 52 Mich 267; Raymond v. McKenna, 147 Mich 35; Krolik v. Lang, 187 Mich 286; Steele v. Shaffer, 241 Mich 632; Richard v. Detroit Trust Co., 269 Mich 411; Achenbach v. Mears, 272 Mich 74; Rossman v. Hutchinson, 289 Mich 577; John Heidsik Co. v. Rechter, 291 Mich 708.

The .burden of proof rests upon plaintiff to show actionable fraud, the elements of which have been stated in a number of cases, particularly in Candler v. Heigho, 208 Mich 115, 121, which case, with the citations therein, was cited with approval in the case *544 of Waldbauer v. Hoosier Casualty Co., 285 Mich 405. Also, see Marshall v. Ullmann, 335 Mich 66, 73.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mina v. General Star Indemnity Co.
555 N.W.2d 1 (Michigan Court of Appeals, 1996)
Triplett v. St Amour
507 N.W.2d 194 (Michigan Supreme Court, 1993)
Disner v. Westinghouse Electric Corporation
726 F.2d 1106 (Sixth Circuit, 1984)
Disner v. Westinghouse Electric Corp.
726 F.2d 1106 (Sixth Circuit, 1984)
Precopio v. City of Detroit
330 N.W.2d 802 (Michigan Supreme Court, 1982)
Hammond v. Matthes
311 N.W.2d 357 (Michigan Court of Appeals, 1981)
U. S. Fibres, Inc. v. Proctor & Schwartz, Inc.
358 F. Supp. 449 (E.D. Michigan, 1972)
Smithson v. Leonard Refineries, Inc.
188 N.W.2d 168 (Michigan Court of Appeals, 1971)
Windham v. Morris
121 N.W.2d 479 (Michigan Supreme Court, 1963)
Reinink v. Van Loozenoord
121 N.W.2d 689 (Michigan Supreme Court, 1963)
Irwin v. Carlton
119 N.W.2d 617 (Michigan Supreme Court, 1963)
People's Furniture & Appliance Co. v. Healy
113 N.W.2d 802 (Michigan Supreme Court, 1962)
Cyril Hubert v. George S. May
292 F.2d 239 (Seventh Circuit, 1961)
Hubert v. May
292 F.2d 239 (Seventh Circuit, 1961)
Smith v. Taber
107 N.W.2d 761 (Michigan Supreme Court, 1961)
A & M Land Development Co. v. Miller
94 N.W.2d 197 (Michigan Supreme Court, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
90 N.W.2d 492, 352 Mich. 539, 1958 Mich. LEXIS 473, Counsel Stack Legal Research, https://law.counselstack.com/opinion/columbus-pipe-equipment-co-v-sefansky-mich-1958.