U. S. Fibres, Inc. v. Proctor & Schwartz, Inc.

358 F. Supp. 449, 13 U.C.C. Rep. Serv. (West) 254, 1972 U.S. Dist. LEXIS 10881
CourtDistrict Court, E.D. Michigan
DecidedDecember 1, 1972
DocketCiv. 32942
StatusPublished
Cited by41 cases

This text of 358 F. Supp. 449 (U. S. Fibres, Inc. v. Proctor & Schwartz, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
U. S. Fibres, Inc. v. Proctor & Schwartz, Inc., 358 F. Supp. 449, 13 U.C.C. Rep. Serv. (West) 254, 1972 U.S. Dist. LEXIS 10881 (E.D. Mich. 1972).

Opinion

OPINION AND ORDER GRANTING IN PART AND DENYING IN PART DEFENDANT’S MOTION FOR INVOLUNTARY DISMISSAL

KAESS, Chief Judge.

This is a civil action for damages, claiming fraud, breach of express warranties, breach of implied warranty of merchantability, breach of implied warranty of fitness for a particular purpose, and negligence. Jurisdiction is based on diversity of citizenship under 28 U.S.C. § 1332.

After plaintiff had completed the presentation of its evidence, the defendant moved for a dismissal on the grounds that, upon the facts and the law, the plaintiff has shown no right to relief. Rule 41(b), Federal Rules of Civil Procedure.

Between 1960 and 1963, Mr. Dan Steuernagel, then employed at the Lock-port Mills in Buffalo, New York, was working on a process to produce a resinated cotton pad. This process consisted of introducing a dry resin into a fluffy cotton pad, curing the resinated pads under heat, and then reducing the thickness of the pad by pressure.

In 1962, Mr. William Clapp, then employed by C. H. Masland & Sons, became aware of this process of producing resinated pads. Clapp and Steuernagel then contacted various car makers who expressed interest in the cotton pads. Mr. George Simon, of Detroit, was then persuaded to supply the capital to form a company to supply padding. There was an agreement to become a licensee of Loekport Mills; however, with the ensuing financial demise of Loekport Mills, this venture was- abandoned. Mr. Steuernagel then went with Allen Industries and continued to work on padding.

Two years later, in the spring of 1965, Steuernagel advised Clapp that he believed that Proctor & Schwartz (P&S), of Philadelphia, could supply the machinery necessary to produce the resinated padding. Simon indicated that he was interested, but suggested that tests be conducted at the P&S laboratory to determine whether the P&S machinery could produce padding to the specifications required by the Ford Motor Company. The Ford specifications described various sound absorption pads of from inch to 1 inch thick and of various densities and weights. The maximum density of the pads in these specifications was 4 lbs./cu. ft.

Near the end of April, 1965, Steuernagel inquired of P&S as to the cost of a *453 duo-form and related components by letter dated May 5, 1965. P&S replied that the cost would be $50,945.00. This inquiry precipitated further communications with P&S, and late in 1964, Steuernagel contacted Mr. Christiansen of P&S and told him he wanted to introduce dry resin into the duo-form. Steuernagel asked for a test of the duo-form to determine if it could be used with dry resin. The test was set up by Mr. Christiansen in Philadelphia. In May, 1964, Steuernagel went to the P&S laboratories in Philadelphia to participate in the tests. Steuernagel determined how the resin would be introduced at these tests. Mr. Clapp provided the fibers used in the tests. The Ford specifications were discussed at the tests. Two days of tests were conducted. Using a P&S duo-form and injecting the resin into a cotton pad with a fertilizer spreader, a pad Was produced at a rate of 1200 pounds per hour, as set by Steuernagel. Curing was done in an ordinary, stationary oven where the pressure was applied by weights which were held in place by clamps. All of the weights and sizes in the Ford specifications were run successfully.

Following these tests, Christiansen came to Detroit and met with Steuernagel and Simon from May 26 through May 30, 1965. Christiansen brought with him a proposal to supply a duo-form and a drying oven. According to the proposal, the oven was to be capable of producing a cured pad at the rate of 1200 pounds per hour, would be 52 feet long and 8 feet high with conveyors 84 inches wide, and capable of exerting 50 pounds per square inch. Since plaintiff wanted a 96 inch oven, this first proposal was rejected, and a second proposal was submitted on July 10, 1965. This proposal added a second duo-form, changed the width of the oven from 84 inches to 96 inches and the length of the oven from 52 feet to 66 feet. This contract described the oven as being capable of exerting a compressive force of 30 pounds per square foot while maintaining a tolerance of plus or minus %2 of an inch over width of the batt. The oven involved in this proposal was being used to cure cotton float in other applications, but had never been used in the application contemplated by the plaintiffs. Likewise, the duo-forms involved in the above quotes had never been used for the application contemplated by the plaintiffs. This July 10th proposal was signed by Simon on July 22, and was countersigned by P&S on July 26, 1965.

The duo-forms were already in existence and the drying oven was fabricated by P&S, based on specifications of other ovens recently constructed by it.

The duo-forms were installed by P&S and were successfully put in operation. There was a delay in the completion of the drying oven. When the drying oven arrived in October, it was a left-handed drying oven while the contract called for a right-handed oven. This necessitated rearranging the utilities which serviced the oven. Numerous difficulties were encountered during installation of the drying oven due to wrong parts being supplied.

Erection of the first production line, consisting of a duo-form and drying oven, was completed and the line started up on January 3, 1966.

Difficulty was immediately encountered with the drying oven. When the oven was started, the conveyor plates bound up as they went around the end of the conveyor. This was caused by the failure of P&S to punch the holes in the right places on the conveyor hinges. The conveyors were taken out of the oven, disassembled, and the hinges were repunched.

On January 20, 1966 the line was started up again and the padding which was produced was acceptable. Upon the completion of the repairs, Proctor paid U. S. Fibres $16,639.00 in “back charges”.

Several weeks after Line I began to run, Steuernagel complained to Proctor that the pads which were being produced were wedge-shaped, i. e., thicker on one edge than on the other. In response to this complaint, two service en *454 gineers were sent to the U. S. Fibres plant. After adjustments to both the duo-form and the dryer, the line again produced an acceptable product on February 22, 1966. On March 3, 1966, a test showed the dryer was producing pads within the ± Mand thickness tolerance.

Between January 20 and June 1, 1966, no complaints were received from U. S. Fibres.

On June 13, 1966, it was discovered that one of the tail sprockets was badly worn. This sprocket was replaced. The following week the conveyor in the dryer jammed because the main head shafts were out of square with the center line of the dryer. To remedy this situation, an alignment was carried out and the squareness of the head shafts and the levelness of the dryer were adjusted. Additional guiding rollers were placed in the compression conveyor and the frame was stiffened. When the conveyor was installed, it immediately became apparent that the conveyors were not running at the same speed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Patel v. OMH Medical Center, Inc.
1999 OK 33 (Supreme Court of Oklahoma, 1999)
Coursey v. Caterpillar, Inc.
64 F.3d 662 (Sixth Circuit, 1995)
St. Paul Fire & Marine Insurance v. CEI Florida, Inc.
864 F. Supp. 656 (E.D. Michigan, 1994)
Kearney & Trecker Corp. v. Master Engraving Co.
527 A.2d 429 (Supreme Court of New Jersey, 1987)
Island Creek Coal Co. v. Lake Shore, Inc.
636 F. Supp. 285 (W.D. Virginia, 1986)
Wisconsin Knife Works v. National Metal Crafters
781 F.2d 1280 (Seventh Circuit, 1986)
Gilbert Waters v. Massey-Ferguson, Inc.
775 F.2d 587 (Fourth Circuit, 1985)
Pasternak v. Sagittarius Recording Co.
617 F. Supp. 1514 (E.D. Michigan, 1985)
Eaton Corp. v. Magnavox Co.
581 F. Supp. 1514 (E.D. Michigan, 1984)
Disner v. Westinghouse Electric Corporation
726 F.2d 1106 (Sixth Circuit, 1984)
Disner v. Westinghouse Electric Corp.
726 F.2d 1106 (Sixth Circuit, 1984)
Knoxville Rod & Bearing, Inc. v. Bettis Corp. of Knoxville
672 S.W.2d 203 (Court of Appeals of Tennessee, 1983)
West Central Packing Inc. v. a F Murch Co.
311 N.W.2d 404 (Michigan Court of Appeals, 1981)
Barb v. Wallace
412 A.2d 1314 (Court of Special Appeals of Maryland, 1980)
Monroc, Inc. v. Jack B. Parson Construction Co.
604 P.2d 901 (Utah Supreme Court, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
358 F. Supp. 449, 13 U.C.C. Rep. Serv. (West) 254, 1972 U.S. Dist. LEXIS 10881, Counsel Stack Legal Research, https://law.counselstack.com/opinion/u-s-fibres-inc-v-proctor-schwartz-inc-mied-1972.