Monroc, Inc. v. Jack B. Parson Construction Co.

604 P.2d 901, 28 U.C.C. Rep. Serv. (West) 18, 1979 Utah LEXIS 961
CourtUtah Supreme Court
DecidedDecember 5, 1979
Docket15847
StatusPublished
Cited by1 cases

This text of 604 P.2d 901 (Monroc, Inc. v. Jack B. Parson Construction Co.) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Monroc, Inc. v. Jack B. Parson Construction Co., 604 P.2d 901, 28 U.C.C. Rep. Serv. (West) 18, 1979 Utah LEXIS 961 (Utah 1979).

Opinion

MAUGHAN, Justice:

Plaintiff, Monroe, Inc., initiated this action to recover the difference between the original contract price and the modified contract price for certain goods delivered and accepted by defendant, Jack B. Parson Construction Company. The specific goods involved were inch and ¾ inch bituminous surface course mixes and a seal coat mix.

Defendant incorporated these materials into 1-215 Interstate Highway project in Salt Lake County. Upon trial before the court, judgment was rendered to plaintiff pursuant to the price terms under the modified agreement. Defendant, Parson, appeals therefrom, contending the prices set forth in the original contract were not modified. The judgment of the trial court is affirmed. All statutory references are to Utah Code Annotated, 1953, as amended.

In the spring of 1973, plaintiff supplied defendant with certain price quotations for materials for a highway project upon which defendant desired to bid. Thereafter, defendant was the successful bidder, and on December 12, 1973, a purchase order was submitted to plaintiff setting forth the prices and materials to be furnished by plaintiff. Plaintiff modified the terms for the price of oil to be supplied and executed the purchase order and returned it to defendant. Defendant accepted this modification without protest and without executing any writing acknowledging these amended terms of price, a fact of interpretive significance which will be discussed infra.

At the time the original purchase order was executed both parties anticipated that the asphalt-laying portion of the contract would begin in 1974. The work was delayed by the failure of the State to have the utilities relocated until September 30, 1974; by that date the temperature was too cold to proceed with the asphalt operations. The following July 18, 1975, defendant’s agent contacted plaintiff’s agent to arrange for the delivery of the materials. Defendant’s agent inquired whether plaintiff would adhere to the prices set forth in the purchase order. Plaintiff’s agent said no, stating the prices were for 1974 only, and the work was not done at that time. Plaintiff’s agent testified there was a standard in the asphalt-selling industry of holding quoted prices for one year.

*903 Plaintiff specifically refused to deliver the materials at the December 1973 prices as set forth in the purchase order because of the time elapsed and the increase in cost of these materials. In a telephone conversation on July 18, 1975, plaintiff’s agent informed defendant’s agent of the increased price of $1.25 per ton for the two bituminous asphalt courses, and the seal coat. The parties also agreed to other modifications of the purchase order. Plaintiff sent a letter to defendant dated August 21,1975. The letter memorialized the oral agreement, made by the telephone conversation of July 18.1975. The current prices for the surface courses, seal coat, and oil were set forth. The letter further noted the original order called for AC 15 and AC 20 oils, and that the State had agreed to change the specification to AC 10 oil with an anti-strip agent additive. The price for this substitute was $82.80 per ton. The letter further stated:

. In addition our agreement is that Parson will pay Monroe an additional $100 per day overtime charge when we go over an eight hour shift and will pay an additional $400.00 per day for Saturday work. .

On August 20, 1975, defendant, Parson, sent a letter to the State Project Engineer, wherein, it was stated:

I have recently been informed by our suppliers of bituminous surface courses that due to continued increases in labor, material and equipment costs, they are unable to provide the various products at previously quoted prices.
Because of this cost increase, we now submit revised unit prices for the below listed items:

The letter set forth revised prices for the two bituminous surface courses and the seal coat.

Plaintiff claims the parties agreed to the modification. Plaintiff’s agent denied in his testimony that defendant’s agent had stated in the telephone conversation of July 18.1975, that Parson intended to hold Mon-roc to the prices set forth in the purchase order, but that Parson would attempt to collect the difference Monroe wanted from the State. Defendant, Parson, did not respond to the letter of August 21,1975 from Monroe, as provided in Section 70A-2- 201(2) by a “written notice of objection to its contents . . . within ten days after it is received.” Defendant’s agent testified he saw no reason to reply because of his reliance on the initial prices quoted in the purchase order; under his concept, no matter how long the delay was, the prices in the purchase order were binding.

Defendant’s agent testified he was aware of the substantial inflationary pressures during 1974 and its tremendous impact on the construction industry. He further testified plaintiff’s price increases were not unreasonable and constituted normal price increase during that period of time. Defendant’s agent testified Parson was pursuing a claim against the State for these price increases.

In its complaint, plaintiff alleged, on July 18, 1975, the parties had agreed verbally to modify the agreement of December 12, 1973, that plaintiff had delivered the materials under the modified contract, and defendant had accepted and incorporated the materials into the project. Defendant in its answer denied the agreement of December 12, 1973, had been modified. Defendant further pleaded as an affirmative defense paragraph 8 of the purchase order, which provided: “Claims for extras positively will not be allowed unless ordered in writing.” Defendant pleaded the failure to comply with this provision of the contract precluded plaintiff’s recovery for the increased price.

The trial court ruled Section 70A-2-201(2) governed the situation between the parties and required defendant Parson to respond in writing within ten days after receiving the letter of August 21, 1975, from plaintiff, Monroe, if Parson objected to the proposed modification. Parsons did not respond. As a consequence, the oral agreement of July 1975 as confirmed in the letter of August 21,1975, modified the original purchase order of December 12, 1973, as to the particulars specified in the letter. The trial court further found defendant *904 paid, without protest, the overtime charges as provided in the modified agreement. Defendant further accepted the new type of oil as provided in the modified agreement, and paid for it at the modified price. The trial court awarded judgment to plaintiff for the additional sum of $1.25 per ton (the modified price specified) for the bituminous surface course mixes and the seal coat mix delivered during the term of the contract.

The parties are in agreement the provisions of the Uniform Commercial Code, Title 70A, are applicable to this case, and they qualify as merchants under the act, viz., a contractor and a supplier of materials for a government project are merchants under the act. 1

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lake Philgas Service v. Valley Bank & Trust Co.
845 P.2d 951 (Court of Appeals of Utah, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
604 P.2d 901, 28 U.C.C. Rep. Serv. (West) 18, 1979 Utah LEXIS 961, Counsel Stack Legal Research, https://law.counselstack.com/opinion/monroc-inc-v-jack-b-parson-construction-co-utah-1979.