Colormatch Exteriors, Inc. v. Hickey

569 S.E.2d 495, 275 Ga. 249, 2002 Fulton County D. Rep. 1795, 2002 Ga. LEXIS 479
CourtSupreme Court of Georgia
DecidedJune 10, 2002
DocketS01G1036, S01G1063
StatusPublished
Cited by23 cases

This text of 569 S.E.2d 495 (Colormatch Exteriors, Inc. v. Hickey) is published on Counsel Stack Legal Research, covering Supreme Court of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Colormatch Exteriors, Inc. v. Hickey, 569 S.E.2d 495, 275 Ga. 249, 2002 Fulton County D. Rep. 1795, 2002 Ga. LEXIS 479 (Ga. 2002).

Opinion

Carley, Justice.

In early April of 1995, David V. Bowden, Kevin Mathews, Mathews Home Builders, Inc., and Mathews Custom Homes, Inc. (Builders) finished construction of a house for which they did not yet have a buyer. On April 26, 1995, the Chatham County Building Inspections Department completed its inspection process and, in July, 1995, issued a certificate of occupancy. Builders then conveyed the property to David and Kimberly Hickey (Plaintiffs). After Plaintiffs discovered moisture damage under the house’s synthetic stucco cladding, they brought suit on April 26, 1999 against Builders and the manufacturer of the synthetic stucco, Colormatch Exteriors, Inc. (Appellants). Plaintiffs asserted products liability claims as to Colormatch and, with respect to Builders, alleged negligent construe *250 tion, breach of warranty, and negligent misrepresentation. The trial court granted summary judgment in favor of Appellants on the ground that the applicable statutes of limitation had expired. The Court of Appeals reversed, concluding that the trial court should have applied the six-year limitation period for contract actions to the claim for breach of implied warranty, and that the four-year statute of limitations for damage to realty did not preclude the remaining tort, fraud, and products liability claims. Hickey v. Bowden, 248 Ga. App. 647 (548 SE2d 347) (2001). The rationale for the latter conclusion was that the earliest date on which the house could be deemed substantially completed, so as to start the four-year period, was the date on which the certificate of occupancy was issued, at which time the house could be occupied legally. Hickey v. Bowden, supra at 650 (2). In order to consider this holding, we granted certiorari in Case Number S01G1036 as to Colormatch and in Case Number S01G1063 as to Builders. We conclude that in those circumstances where, as here, a contractor makes improvements to his own real property for the express purpose of sale and the property actually is sold, the applicable period of limitations for claims of damage to realty does not begin to run until the initial sale of the improved property, regardless of the date of “substantial completion.” However, the limitations period begins to run against the manufacturer of materials necessary for the improvement on the date of substantial completion, which we hold is not dependent on the issuance of a certificate of occupancy. Accordingly, we reverse the judgment of the Court of Appeals in Case Number S01G1036, but affirm in Case Number S01G1063 under the “right for any reason” principle. See Dental One Assoc. v. JKR Realty Assoc., 269 Ga. 616, 617 (501 SE2d 497) (1998).

1. The statute of limitations which is applicable to Plaintiffs’ tort claims, including their products liability claims, is found in OCGA § 9-3-30 (a). Corporation of Mercer Univ. v. Nat. Gypsum Co., 258 Ga. 365, 366 (1) (368 SE2d 732) (1988); Mitchell v. Contractors Specialty Supply, 247 Ga. App. 628, 629 (544 SE2d 533) (2001); Mitchell v. Jones, 247 Ga. App. 113, 115 (2) (541 SE2d 103) (2000); Hanna v. McWilliams, 213 Ga. App. 648, 649 (2) (a) (446 SE2d 741) (1994). Compare OCGA § 9-3-30 (b) (providing a special rule for synthetic stucco causes of action which do not expire before March 28, 2000); Daniel v. American Optical Corp., 251 Ga. 166, 167 (1) (304 SE2d 383) (1983). OCGA § 9-3-30 (a) provides that “[a]ll actions for trespass upon or damage to realty shall be brought within four years after the right of action accrues.” See Daniel v. American Optical Corp., supra at 168 (1) (the similar language of OCGA § 9-3-33 demonstrates that the scope of its application “is determined by the nature of the injury sustained rather than the legal theory underlying the claim for relief”).

*251 By its terms, the four-year time period established in OCGA § 9-3-30 (a) only began running when Plaintiffs’ rights of action in tort accrued. For statute of limitations purposes, the general rule for determining the time a cause of action accrues is well-settled in Georgia. “The true test to determine when a cause of action accrues is to ascertain the time when the plaintiff could first have maintained [his or] her action to a successful result. [Git.]” Travis Pruitt & Assoc. v. Bowling, 238 Ga. App. 225, 226 (1) (518 SE2d 453) (1999). Thus, Plaintiffs could have no cause of action for damage to the property under the theories of negligence and strict liability before they incurred some damage. OCGA §§ 51-1-8, 51-1-11 (b) (1); Travis Pruitt & Assoc. v. Bowling, supra at 226 (1). Damage to property arising out of construction is generally considered to occur at the time of the defendant-contractor’s “substantial completion” of the project, because damages usually become immediately ascertainable to the plaintiff-owner at that time. Corporation of Mercer Univ. v. Nat. Gypsum Co., supra at 366 (1); Travis Pruitt & Assoc. v. Bowling, supra at 226 (1); Hanna v. McWilliams, supra at 649 (2) (a). The issue presented for resolution is whether this general rule of “substantial completion” is applicable under the circumstances presented in this case.

Case Number S01G1063

2. Whatever the date of substantial completion, it occurred before title to the property was conveyed to the Plaintiffs. In the suit against Builders, the issue is whether Plaintiffs’ rights of action nevertheless accrued upon substantial completion of the house even though Builders were still the owners of the property at that time. Travis Pruitt appropriately distinguishes cases involving “alleged negligent design and construction of the plaintiff’s own property. [Cits.]” Travis Pruitt & Assoc. v. Bowling, supra at 226 (1). If the owner contracts with a builder and intends to retain the improved property after completion of the project, he can maintain an action against the contractor immediately upon substantial completion of the allegedly negligent construction and, thus, there is no question that the statute of limitations begins to run at that time. In such a case, the plaintiff is the owner of the property at the time of substantial completion. Where, however, the contractor is a developer who still owns the property at the time of substantial completion, he obviously cannot maintain an action for negligent construction or misrepresentation against himself. If the new house was constructed by an owner-builder for the purpose of sale and the property actually is sold, then the only persons who are injured by any negligence of the builder and who can successfully maintain an action therefor are the *252

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DOUGLAS COE v. PROSKAUER ROSE LLP
314 Ga. 519 (Supreme Court of Georgia, 2022)
Mbigi v. Wells Fargo Home Mortgage
785 S.E.2d 8 (Court of Appeals of Georgia, 2016)
Rosenberg v. Falling Water, Inc.
709 S.E.2d 227 (Supreme Court of Georgia, 2011)
Smith v. HILLTOP POOLS AND SPAS, INC.
703 S.E.2d 424 (Court of Appeals of Georgia, 2010)
Lesser v. Doughtie
686 S.E.2d 416 (Court of Appeals of Georgia, 2009)
Trax-Fax, Inc. v. Hobba
627 S.E.2d 90 (Court of Appeals of Georgia, 2006)
Wallace v. Bock
620 S.E.2d 820 (Supreme Court of Georgia, 2005)
Scully v. 1st Magnolia Homes, Inc.
614 S.E.2d 43 (Supreme Court of Georgia, 2005)
Danjor, Inc. v. Corporate Construction, Inc.
613 S.E.2d 218 (Court of Appeals of Georgia, 2005)
Stamschror v. Allstate Insurance
600 S.E.2d 751 (Court of Appeals of Georgia, 2004)
Western Pacific Mutual Insurance v. Davies
601 S.E.2d 363 (Court of Appeals of Georgia, 2004)
Bauer v. Weeks
600 S.E.2d 700 (Court of Appeals of Georgia, 2004)
Barnes v. Turner
593 S.E.2d 9 (Court of Appeals of Georgia, 2004)
Boaz v. Latson
580 S.E.2d 572 (Court of Appeals of Georgia, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
569 S.E.2d 495, 275 Ga. 249, 2002 Fulton County D. Rep. 1795, 2002 Ga. LEXIS 479, Counsel Stack Legal Research, https://law.counselstack.com/opinion/colormatch-exteriors-inc-v-hickey-ga-2002.