Denny Express Vinyl Siding, Inc. v. Boatright Roofing and General Contracting, Inc.

808 S.E.2d 1, 343 Ga. App. 235
CourtCourt of Appeals of Georgia
DecidedOctober 19, 2017
DocketA17A1237; A17A1238
StatusPublished
Cited by12 cases

This text of 808 S.E.2d 1 (Denny Express Vinyl Siding, Inc. v. Boatright Roofing and General Contracting, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Denny Express Vinyl Siding, Inc. v. Boatright Roofing and General Contracting, Inc., 808 S.E.2d 1, 343 Ga. App. 235 (Ga. Ct. App. 2017).

Opinion

Self, Judge.

*235 These appeals arise from a suit alleging negligent construction, misrepresentation, and breach of contract involving the Shadow Brooke Village Condominiums in St. Simons Island, Georgia (the "Project") filed against the developer, general contractor, a roofing subcontractor, and a vinyl-siding contractor by the Shadow Brooke Village Condominium Owners' Association (the "Association"). The issues on appeal involve whether the Association's claims are barred by the statute of limitation, sanctions for spoliation, and the effect of a "full and final judgment" entered in favor of the roofing subcontractor. For the reasons explained below, we conclude that *236 (1) the Association's claims are barred by the statute of limitation, except with regard to building 15; (2) the trial court's order on spoliation should be reversed to the extent it allows the jury to make findings of fact as to whether spoliation occurred; and (3) this Court cannot issue an advisory opinion regarding the trial court's grant of summary judgment to the roofing subcontractor.

To prevail at summary judgment, the moving party must demonstrate that there is no genuine issue of material fact and that the undisputed facts, viewed in the nonmovant's favor, warrant judgment as a matter of law. A defendant who will not bear the burden of proof at trial need only show an absence of evidence to support an *3 essential element of the nonmoving party's case. If the moving party discharges this burden, the nonmoving party cannot rest on its pleadings, but rather must point to specific evidence giving rise to a triable issue.

(Citation, punctuation, and footnote omitted.) Danjor, Inc. v. Corporate Constr ., 272 Ga. App. 695 , 695-696, 613 S.E.2d 218 (2005). "A de novo standard of review applies to an appeal from a grant of summary judgment, and we view the evidence, and all reasonable conclusions and inferences drawn from it, in the light most favorable to the nonmovant." 1 (Citation and punctuation omitted.) Costrini v. Hansen Architects , 247 Ga. App. 136 , 543 S.E.2d 760 (2000).

The record shows that the Project consists of 15 residential buildings, each comprised of six separate condominium units, for a total of 90 units, and a clubhouse. Construction of the buildings began in 2001, and was completed between 2003 and 2009, with buildings one through fourteen receiving certificates of occupancy between January 2003 and September 2008. Demere Marsh Associates, LLC (the "developer") was the developer, Sea Oaks, Inc. (the "general contractor") was the general contractor, Denny Express Vinyl Siding, *237 Inc. (the "vinyl-siding subcontractor," collectively "appellants") was a subcontractor of the developer hired to install vinyl siding on buildings 2, 8, 9, 14, and 15, and Boatright Roofing and General Contracting, Inc. (the "roofing subcontractor") was the subcontractor that installed the roofs on some of the buildings for the Project.

On October 18, 2012, the Association sued the developer, general contractor, and both subcontractors, among others, alleging that negligent construction caused substantial damage to the buildings, particularly water damage. The crux of the complaint is that "[d]uring construction of the condominium complex, [the developer and general contractor] modified the design of the buildings and used materials that were not specified by the architect ... and as a result, there was water intrusion and decay which has left the buildings unstable and at risk of collapse." The developer and general contractor filed a cross-claim against the roofing subcontractor for indemnity and/or contribution and a notice of apportionment.

The roofing subcontractor moved for summary judgment on the ground that all of the Association's claims against it were barred by the statute of limitation. The appellants moved for partial summary judgment on the ground that the applicable four-year statute of limitation and eight-year statute of repose barred the Association's claims with regard to 14 of the 15 buildings. 2 Appellants also moved for sanctions for spoliation of evidence, on the ground that the Association "engaged in extensive destructive testing including the removal and discarding of material elements of evidence from the exterior facades" of the buildings after it filed suit against the appellants.

The Association consented to the entry of summary judgment in favor of the roofing subcontractor, and the trial court granted the motion, entering final judgment in favor of the roofing subcontractor and against the Association. The trial court granted in part and denied in part the remaining motions for summary judgment. As to buildings 3, 4, 5, 6, and 7, all of which were completed between July 2003 and August 11, 2004, the trial court determined that the statute of repose barred *4 all of the Association's claims including for attorney *238 fees under OCGA § 13-6-11. As to the developer's and general contractor's liability in connection with the remaining nine buildings, the trial court found that there was a genuine issue of material fact as to whether the Association knew or should have known of the construction problems by October 2008, and that " OCGA § 9-3-30 (b) (1) applies to protect the Association's claims from the four-year statute of limitation." As to the vinyl-siding subcontractor, the trial court concluded that the Association's claims regarding buildings 2, 9, and units 100, 101, and 300 of building 8 were barred by the statute of repose; it found genuine issues of material fact regarding buildings 14 and 15, as well as units 200, 201, and 301 of building 8 on the same ground set forth against the developer and general contractor. With regard to the spoliation motions, the trial court's order stated that they were granted in part and denied in part, but it "decline [d] to impose the sanction of dismissal of plaintiff's case."

In Case No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

TATYANA ELLIS v. DAVID EDWARD OLES
Court of Appeals of Georgia, 2022
SEIBERT v. ALEXANDER, Jr. Et Al.
829 S.E.2d 473 (Court of Appeals of Georgia, 2019)
Rubie Hillman v. Aldi, Inc.
Court of Appeals of Georgia, 2019
Henry Cook v. Don Smith
Court of Appeals of Georgia, 2019
HUDDLE Et Al. v. HEINDEL.
821 S.E.2d 61 (Court of Appeals of Georgia, 2018)
Hans G. Reid v. Waste Industries USA, Inc
Court of Appeals of Georgia, 2018
Reid v. Waste Indus. USA, Inc.
812 S.E.2d 582 (Court of Appeals of Georgia, 2018)
HOUSTON HOSPITALS, INC. v. PAMELA FELDER
Court of Appeals of Georgia, 2018

Cite This Page — Counsel Stack

Bluebook (online)
808 S.E.2d 1, 343 Ga. App. 235, Counsel Stack Legal Research, https://law.counselstack.com/opinion/denny-express-vinyl-siding-inc-v-boatright-roofing-and-general-gactapp-2017.