Smith v. HILLTOP POOLS AND SPAS, INC.

703 S.E.2d 424, 306 Ga. App. 881, 2010 Fulton County D. Rep. 3852, 2010 Ga. App. LEXIS 1080
CourtCourt of Appeals of Georgia
DecidedNovember 19, 2010
DocketA10A1002
StatusPublished
Cited by1 cases

This text of 703 S.E.2d 424 (Smith v. HILLTOP POOLS AND SPAS, INC.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smith v. HILLTOP POOLS AND SPAS, INC., 703 S.E.2d 424, 306 Ga. App. 881, 2010 Fulton County D. Rep. 3852, 2010 Ga. App. LEXIS 1080 (Ga. Ct. App. 2010).

Opinion

Doyle, Judge.

Matthew L. Smith appeals from the trial court’s grant of summary judgment to Hilltop Pools and Spas, Inc. (“Hilltop”), arguing that the trial court erred by finding that Smith’s negligence and contract claims were barred by the statute of limitation and that Smith failed to produce any evidence of fraud or deceit (and thereby rescission on the basis of fraud). For the reasons that follow, we affirm.

Summary judgment is proper when there is no genuine issue of material fact and the movant is entitled to judgment as a matter of law. OCGA § 9-11-56 (c). A de novo standard of review applies to an appeal from a grant of summary judgment, and we view the evidence, and all reasonable *882 conclusions and inferences drawn from it, in the light most favorable to the nonmovant. 1

So viewed, the record before us reveals that Smith entered into a contract with Hilltop in early February 2001, for construction of an in-ground swimming pool. Hilltop contracted with Wayne Younger to excavate the area, and during excavation, Younger discovered garbage fill in the area, which would cost extra to remove. Smith agreed to the extra expense, and Smith surveyed the area with Younger, at which time Younger told Smith all the garbage had been removed. Smith recalled that Younger had re-buried the trash approximately 30 to 40 feet away from the pool site, and Smith did not recall seeing any trash in the original trash pit after Younger completed the excavation. A Hilltop representative swore that he did not knowingly represent any fraudulent information concerning removal of the garbage and did not make any representation to Smith that was false or intended to deceive Smith about garbage remaining in the pool site.

Smith deposed that in August 2001, Hilltop had installed the liner for the pool, but the pool was unlevel, which was visually apparent from the tile pattern on the pool liner. Smith also deposed that the pool was usable at that time, but Hilltop agreed to return to the residence in February 2002, reassess the leveling situation, and change the liner at that time. Additionally, the parties agreed that Smith could withhold the final payment on the contract of approximately $1,300 and that Hilltop would begin changing the liner by February 28, 2002, would complete the work within 28 days, and would compensate Smith $150 per day for which the liner replacement was incomplete. It is undisputed that the liner replacement was never completed, although Smith met with a representative from Hilltop in May 2002, and Smith never remitted the final payment of the contract to Hilltop. Despite the unlevel appearance of the water in the pool, Smith deposed that he utilized the pool for swimming during warm months of the year, beginning in August 2001, until one wall of the pool collapsed in September 2004.

Smith deposed that the pool was unusable after September 2004, but he did not file suit against Hilltop until October 8, 2007. Hilltop filed a motion for summary judgment, contending that the claims against Hilltop should be dismissed because the applicable statutes of limitation had expired and because Smith had failed to produce evidence of fraud by Hilltop. The trial court agreed with Hilltop and granted the motion. Smith now appeals.

*883 1. Smith argues that the trial court erred by finding that his breach of contract and negligence claims were barred by the six-year statute of limitation. Specifically, Smith contends that the trial court erroneously relied on the date the contracted-for work was “substantially completed” as the date from which the statute of limitation began to run, and Smith argues instead that the date on which the final payment becomes due and payable is the appropriate date from which the statute began to run. Smith also contends that the parties mutually agreed to extend the contract until February 28, 2002, and the complaint was timely filed in October 2007, prior to expiration of the statute of limitation in February 2008. We disagree.

“Generally, whether a cause of action is barred by the statute of limitation is a mixed question of law and fact. Where the facts are in dispute, the question is one of fact to be determined by the trier of fact, but where the facts are not disputed, the question is one of law for the court.” 2

All actions upon simple contracts in writing shall be brought within six years after the same become due and payable. Based on this statute of limitation, this Court has held that an action for breach of a written construction contract must be filed within six years after the work has been substantially completed. Substantial completion means the date when construction was sufficiently completed, in accordance with the contract as modified by any change order agreed to by the parties, so that the owner could occupy the project for the use for which it was intended. 3

Substantial completion triggers the time to file an action because the “damage to the property arising out of faulty construction . . . normally is ascertainable ... at that time.” 4

The trial court determined that Hilltop substantially completed the project by August 2001, when Smith deposed that the pool was usable, and his only concern with the construction was that the pool was not level, and the tile pattern of the pool liner made this visually apparent and aesthetically displeasing. Although the parties exchanged correspondence in which Hilltop promised to change the liner in February 2002, the trial court determined that this agree *884 ment did not serve to change the trigger date for the statute of limitation because the pool served the purpose for which it was constructed beginning in August 2001. We agree and affirm.

Smith argues that while a construction contract’s “substantial completion” date normally is the date from which an action becomes “due and payable,” in this case, the extension until February 2002 of the agreement to replace the liner delayed the trigger date for the contract to be due and payable, as evidenced by the parties’ mutual agreement for Smith to withhold the final payment under the contract until that time. For support, Smith relies on Wallace v. Bock, 5 in which the Supreme Court of Georgia explained that “the true test to determine when the cause of action accrued is to ascertain the time when the plaintiff could first have maintained his action to a successful result.” 6 Here, the alleged breach occurred when Younger failed to adequately excavate the trash in the area around the pool, and Hilltop completed installation of the pool overtop, not when Hilltop failed to replace the liner in February 2002.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wellons, Inc. v. LANGBOARD, INC.
726 S.E.2d 673 (Court of Appeals of Georgia, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
703 S.E.2d 424, 306 Ga. App. 881, 2010 Fulton County D. Rep. 3852, 2010 Ga. App. LEXIS 1080, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smith-v-hilltop-pools-and-spas-inc-gactapp-2010.