Wellons, Inc. v. LANGBOARD, INC.

726 S.E.2d 673, 315 Ga. App. 183, 12 Fulton County D. Rep. 1233, 2012 Ga. App. LEXIS 340, 12 FCDR 1233
CourtCourt of Appeals of Georgia
DecidedMarch 27, 2012
DocketA11A1519
StatusPublished
Cited by15 cases

This text of 726 S.E.2d 673 (Wellons, Inc. v. LANGBOARD, INC.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wellons, Inc. v. LANGBOARD, INC., 726 S.E.2d 673, 315 Ga. App. 183, 12 Fulton County D. Rep. 1233, 2012 Ga. App. LEXIS 340, 12 FCDR 1233 (Ga. Ct. App. 2012).

Opinion

Blackwell, Judge.

Wellons, Inc. and Langboard, Inc. entered into two contracts in which Wellons agreed to design and install a custom energy system for a Langboard facility in Quitman. A Brooks County jury found that Wellons breached both contracts, and it awarded more than $8.4 million to Langboard as damages. Wellons appeals from the judgment entered upon the verdict of the jury, claiming that the trial court erred in three respects. First, Wellons contends that Langboard failed to bring its claim for breach of the design contract soon enough and that the trial court should have awarded summary judgment to Wellons on that claim. Second, Wellons argues that the evidence cannot sustain the award of damages for breach of the installation contract and that the trial court should have entered judgment for Wellons on the installation contract claim or, at the least, should have granted Wellons a new trial on that claim. Finally, Wellons contends that the trial court erred when it admitted certain evidence that is, Wellons says, speculative and irrelevant. We find no merit in these claims of error, and we affirm the judgment below.

1. We first consider the contention that Wellons was entitled to summary judgment on the claim for breach of the design contract because Langboard failed to assert that claim soon enough. The design contract requires that any claim for its breach be brought “within one year after the cause of action occurs . . . .” Before trial, Wellons moved for summary judgment on the design contract, arguing that Langboard waited more than a year after its claim accrued to file its complaint. Wellons explained in the trial court that the claim for breach of the design contract accrued at least by March 2006, when Langboard inquired of Wellons about replacing a super-heater in the system, an inquiry that demonstrates, Wellons said, an awareness of the problems with the system. The trial court denied the motion for summary judgment, and the case proceeded to trial.

We have some doubt about whether we properly can undertake to review the denial of the motion for summary judgment. As a general rule, “[a]fter verdict and judgment, it is too late to review a judgment denying a summary judgment, for that judgment becomes moot when the court reviews the evidence upon the trial of the case.” Kicklighter v. Woodward, 267 Ga. 157, 162 (4) (476 SE2d 248) (1996) (citation and punctuation omitted). Our Court has recognized a limited exception to this rule in cases in which “the legal issues raised and resolved in denying the motion for summary judgment were not considered at trial,” Smith v. Saulsbury, 286 Ga. App. 322, 323 (1) (a) (649 SE2d 344) (2007) (punctuation omitted), and Wellons argues *184 that this is such a case. But we note that Wellons repeatedly sought at trial to elicit testimony about the time that elapsed after Lang-board discovered problems with the custom energy system, Wellons argued to the jury that Langboard failed to promptly address these problems, and the court charged the jury that “the limitation period... begins to run at the time of the defendant’s last successful repair attempt,” an instruction to which Wellons did not object. Nevertheless, Langboard seems to concede that the limitation issue was not raised at trial, and for that reason, we will assume that we properly can consider the question of summary judgment, notwithstanding our doubts.

The standard for summary judgment is familiar and settled. “Summary judgment is warranted when any material fact is undisputed, as shown by the pleadings and record evidence, and this fact entitles the moving party to judgment as a matter of law.” Strength v. Lovett, 311 Ga. App. 35, 39 (2) (714 SE2d 723) (2011). “So, to prevail on a motion for summary judgment, the moving party must show that there is no genuine dispute as to a specific material fact and that this specific fact is enough, regardless of any other facts in the case, to entitle the moving party to judgment as a matter of law.” Id. We review the denial of a motion for summary judgment de novo, Higginbotham v. Knight, 312 Ga. App. 525, 526 (719 SE2d 1) (2011), and we view the evidence in the same way as the trial court, that is, in the light most favorable to the nonmoving party. Saiia Constr. v. Terracon Consultants, 310 Ga. App. 713, 713 (714 SE2d 3) (2011).

So viewed, the record shows that Wellons and Langboard entered into the design contract in October 2002. Pursuant to this contract, Langboard was to pay $13.7 million to Wellons, and Wellons was to design a custom energy system for the Langboard oriented strand board plant in Quitman. The parties agreed that the system would be designed to fulfill three essential purposes. First, the system would generate heat energy sufficient to power the production of oriented strand board. Second, the system would return any exhaust generated in the production process to the furnaces, where any pollutants would be incinerated, so that Langboard would not have to pay for additional pollution control equipment. Finally, the system would produce excess heat sufficient to power a boiler and turbine, which, in turn, would generate electricity that Langboard could use or sell. Wellons undertook to design the custom energy system, and in October 2003, Wellons and Langboard entered into a second contract, which provided for the installation of the system at the Quitman plant.

By June 2005, the system installation was far enough along that Langboard was able to operate the parts of the system designed to *185 power the production of oriented strand board and to incinerate pollutants. But Langboard presented evidence that, from the time it first began to operate the system, the system was unable to meet applicable emissions requirements. And when the portion of the system designed to produce electricity was finally activated in October 2005, Langboard found that it did not produce enough steam to generate electricity as the design contract required.

For several months thereafter, Wellons attempted to repair the system to bring it into compliance with the emissions requirements and to increase its production of steam. By November 2006, the emissions were “under control,” but the system remained unable to produce the required steam. In December 2006, a Wellons engineer spent five days at the Quitman plant to test the capacity of the system following additional repairs. The engineer concluded that he needed additional data to determine what modifications might enable the system to produce the necessary steam. At least through January 2007, Wellons employees remained at the facility, testing the system and attempting to determine why it was not producing steam sufficient to run the turbine and generate electricity. And as late as May 2007, Wellons continued to suggest modifications of the system, including the replacement of a superheater. Wellons apparently thought that, although a new superheater would not increase the amount of steam produced by the boiler, it would increase the thermal energy of the steam that was being produced and thereby improve the performance of the system. In May 2007, Langboard informed Wellons that it was not interested in a replacement superheater because it would not, Langboard had concluded in the meantime, solve the problem of inadequate steam production. 1 Langboard filed its complaint against Wellons in October 2007.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CHANTE AMOS v. CREATIVE CONSULTING SERVICES, INC.
Court of Appeals of Georgia, 2024
ROBERT HOWELL v. CORY COCHRAN
Court of Appeals of Georgia, 2022
DOCTORS HOSPITAL OF AUGUSTA, LLC Et Al. v. ALICEA
774 S.E.2d 114 (Court of Appeals of Georgia, 2015)
Vivek Pampattiwar v. Jan v. Hinson
Court of Appeals of Georgia, 2014
Pampattiwar v. Hinson
756 S.E.2d 246 (Court of Appeals of Georgia, 2014)
Pentagon Properties, Inc. v. Charles Wheat
Court of Appeals of Georgia, 2013
Pentagon Properties, Inc. v. Wheat
740 S.E.2d 374 (Court of Appeals of Georgia, 2013)
Garrett v. Southern Health Corp. of Ellijay, Inc.
739 S.E.2d 661 (Court of Appeals of Georgia, 2013)
Jeffery Mordica v. State of Georgia
Court of Appeals of Georgia, 2012
Pinnacle Properties V, LLC v. Mainline Supply Of
Court of Appeals of Georgia, 2012
Mordica v. State
736 S.E.2d 153 (Court of Appeals of Georgia, 2012)
Pinnacle Properties V, LLC v. Mainline Supply of Atlanta, LLC
735 S.E.2d 166 (Court of Appeals of Georgia, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
726 S.E.2d 673, 315 Ga. App. 183, 12 Fulton County D. Rep. 1233, 2012 Ga. App. LEXIS 340, 12 FCDR 1233, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wellons-inc-v-langboard-inc-gactapp-2012.