Clopton Rogers v. Osborn

261 S.W.2d 311, 152 Tex. 540, 2 Oil & Gas Rep. 304, 1953 Tex. LEXIS 509
Texas Supreme Court·Decided April 29, 1953·No. A-3824·Published·Cited by 67 cases

Opinions

Mr. Justice Wilson

delivered the opinion of the Court.

This is a suit to terminate an oil and gas lease. The principal questions are: Whether work done upon a first well in an unsuccessful effort to make it produce at and after the expiration [542] of the primary term kept alive the lease; and if so, whether the drilling of and production from a second well commenced after the expiration of the primary term will support the lease. Our answer to the first is “Yes” and to the second “No”.

For a detailed statement of the facts see the opinion of the Court of Civil Appeals at 250 S.W. 2d 296.

Before the primary term expired on September 21, 1947, Well No. 1 had been commenced on May 15. The derrick was torn down and drilling tools removed on July 30th. From then until November 12th the well was subjected to “periodic flowing”. This was an effort to clean baroid and drilling mud out of the well by allowing it to build up a head of gas and then opening the flow valve into the pits. The head of gas was followed by a flow of oily mud. After the flow ceased it would be shut in to accumulate more pressure. At first this procedure was followed almost every day but it soon slowed down to once a week.

The uncontroverted evidence established that all cutting of new hole on Well No. 1 had been completed, all pipe cemented, and all flowing arrangements completed when the primary term expired on September 21st.

At that time there was no production from the lease. The word “production” means marketable oil or gas. Garcia v. King, 139 Texas 578, 164 S.W. 2d 509. There is positive testimony from lessees’ witnesses that there was never any production from Well No. 1. The well was allowed to blow itself out a number of times in an effort to clean it, but neither party claims this as production. There was no “shut-in” royalty tendered for Well No. l. (1) We hold as a matter of law that there was no production from Well No. 1. Freeman v. Magnolia Petroleum Co., 141 Texas 274, 171 S.W. 2d 339.

The lease terminated on September 21, 1947 unless some provision other than the primary term kept it alive. To accomplish [543] this, lessees rely (first) upon reworking operations upon Well No. 1 and (second) upon the drilling of and production from Well No. 2.

Paragraph No. 5 of the lease is as follows:

“If prior to discovery of oil or gas on said land Lessee should drill a dry hole or holes thereon, or if after discovery of oil or gas the production thereof should cease from any cause, this lease shall not terminate if lessee commences additional drilling or re-working operations within sixty (60) days thereafter or (if it be within the primary term) commences or resumes the payment or tender of rentals on or before the rental paying date next ensuing after the expiration of three months from date of completion of dry hole, or cessation of production. If at the expiration of the primary term oil, gas or other mineral is not being produced on said land but lessee is then engaged in drilling or re-working operations thereon, this lease shall remain in force so long as operations are prosecuted with no cessation of more than thirty (30) consecutive days, and if they result in the production of oil, gas or other mineral so long thereafter as oil, gas or other mineral is produced from said land * *

We will first consider the first sentence of paragraph 5. If, prior to discovery of gas, lessees drilled a dry hole, they had sixty days in which to commence additional drilling or reworking operations. Lessees plead that oil and gas were discovered in the first well. They offered opinion evidence upon which the jury found that gas in paying quantities was discovered “prior to September 21, 1947.” Since lessees sought and obtained a finding that Well No. 1 was not dry, the dry hole clause had no application. We do not reach the question in St. Louis Royalty Co. v. Continental Oil Co., U.S. C.C.A., 5th Cir., 193 F. 2d 778.

This presents a situation where gas was discovered in paying quantities in Well No. 1 but never produced. The second alternative in this first sentence of paragraph 5 is: “or if after the discovery of oil and gas the production should cease from any cause” the lessee had 60 days to commence additional drilling or reworking operations. If production never began, it could not “cease” and by ceasing give the lessee 60 days in which to commence additional drilling. Clearly the first sentence of paragraph 5 did not provide for discovering but not producing gas. Our construction is supported by the fact that the royalty provision quoted in Footnote 1, supra, did provide for just this situation and required the payment of a specific shut-in royalty. [544] And we have held that where the “year” of this shut-in gas royalty clause straddles the date for the expiration of the primary term, the “shut-in” payment must be made during the primary term, or the lease expires. Freeman v. Magnolia Petroleum Co., supra. Therefore the first sentence of paragraph 5 cannot be used to prolong the life of the lease. Morrison v. Swaim, Texas Civ. App. 1949, 220 S.W. 2d 493, wr. er. ref., n.r.e.; Producers Oil & Gas Co., Inc., v. Continental Securities Corp., 188 La. 564, 177 So. 668.

We pass now to the second sentence.

The two conditions of the opening prepositional phrase are: (1) if "at the expiration of the primary term” gas was not being “produced on said lease,” and (2) the lessee was “then engaged in drilling or reworking operations thereon”. It is uncontroverted that no gas was being produced and the lessees were not “then engaged” in drilling hole. The second word “operations” (“so long as operations are prosecuted with no cessation of more than thirty (30) consecutive days”), undoubtedly means both “drilling” and “reworking operations”. It is not necessary to determine whether this lessee’s efforts to clean out the well be defined as “drilling” or “reworking” because without objection the trial court used almost the same definition for both drilling and reworking. It would include almost any type of work. Since it was not objected to it is part of the jury’s finding. It was:

“You are instructed that the term ‘re-working operations,’ as used herein, means actual work or operations which have theretofore been done, being done over, and being done in good faith endeavor to cause a well to produce oil and gas or oil or gas in paying quantities as an ordinarily competent operator would do in the same or similar circumstances.”

The jury found in response to Special Issue’s Nos. 1 and 2 that on the expiration date (September 21st) lessees were then engaged in both drilling and reworking operations. For convenience we will discuss lessees’ efforts as “reworking”. Is there evidence to support this?

Free access — add to your briefcase to read the full text and ask questions with AI

Clopton Rogers v. Osborn, 261 S.W.2d 311, 152 Tex. 540, 2 Oil & Gas Rep. 304, 1953 Tex. LEXIS 509 (Tex. 1953).

261 S.W.2d 311 (Clopton Rogers v. Osborn) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Zavanna v. Gadeco
2023 ND 142 (North Dakota Supreme Court, 2023)
Cimarex Energy Co. v. Anadarko Petroleum Corporation
574 S.W.3d 73 (Court of Appeals of Texas, 2019)
O'NEAL v. JLH Enterprises, Inc.
862 So. 2d 1021 (Louisiana Court of Appeal, 2003)
Utley v. Marathon Oil Co.
31 S.W.3d 274 (Court of Appeals of Texas, 2000)
Neel v. HECI Exploration Co.
942 S.W.2d 212 (Court of Appeals of Texas, 1997)
Transamerican Natural Gas Corp. v. Finkelstein
933 S.W.2d 591 (Court of Appeals of Texas, 1996)
Roemer Oil Co. v. Aztec Gas & Oil Corp.
886 P.2d 259 (Wyoming Supreme Court, 1994)
Pro-Chem, Inc. v. Lassetter Petroleum, Inc.
837 P.2d 823 (Court of Appeals of Kansas, 1990)
Cali-Ken Petroleum Co. v. Slaven
754 S.W.2d 64 (Court of Appeals of Tennessee, 1988)
Serhienko v. Kiker
392 N.W.2d 808 (North Dakota Supreme Court, 1986)
Griffin v. Crutcher-Tufts Corp.
500 So. 2d 1008 (Supreme Court of Alabama, 1986)
Jardell v. Hillin Oil Co.
485 So. 2d 919 (Supreme Court of Louisiana, 1986)
Wiggins Bros. v. Department of Energy
667 F.2d 77 (Temporary Emergency Court of Appeals, 1981)