Serhienko v. Kiker

392 N.W.2d 808, 91 Oil & Gas Rep. 278, 1986 N.D. LEXIS 397
CourtNorth Dakota Supreme Court
DecidedAugust 20, 1986
Docket11039
StatusPublished
Cited by14 cases

This text of 392 N.W.2d 808 (Serhienko v. Kiker) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Serhienko v. Kiker, 392 N.W.2d 808, 91 Oil & Gas Rep. 278, 1986 N.D. LEXIS 397 (N.D. 1986).

Opinion

GIERKE, Justice.

The plaintiffs appeal from a judgment and amended judgment of the district court which dismissed their action seeking cancellation of two oil and gas leases and damages for slander of title. Defendants Russell L. Kiker, Jr., and Martin Oil Company (Martin) have cross-appealed from a portion of the amended judgment dismissing their counterclaims against the plaintiffs. We affirm in part, reverse in part, and remand for further proceedings.

The plaintiffs collectively own 240 of the mineral acres in Billings County described as follows:

“Township 143 North, Range 98 West of the 5th P.M.
“Section 3: SVííNEVí, SEVí
“Section 10: SV2NWy4, NASWV-i”

The oil and gas interests owned by the plaintiffs were leased to Kiker through two leases executed on October 6 and 7, 1977, for primary terms of five years and ten years, respectively. The controversy in this case centers upon a cessation of production clause contained in each lease. That clause states in pertinent part:

“If prior to discovery of oil or gas on said land, or on acreage pooled therewith, lessee should drill a dry hole or holes thereon, or if after discovery of oil or gas production thereafter should cease for any cause, this lease shall not terminate if lessee commences additional drilling or reworking operations within sixty (60) days thereafter, or (if it be within the primary term) commences or resumes the payment or tender of rental on or before the rental-paying date next ensuing after the expiration of three (3) months from the date of completion of a dry hole or cessation of production.”

During August 1978 a producing well, known as the Symionow Well, was completed by Gulf Oil Corporation (Gulf) in Section 10 on property pooled by agreement of the plaintiffs. The Symionow Well was a marginal producer. On June 27, 1980, still within the primary term of both leases, production from the Symionow Well ceased. During a two-week period in July 1980, Gulf conducted tests on the Symio-now Well. This operation included pulling the tubing and running a pipe inspection log. Gulf determined that serious casing leaks existed which prevented the well from producing oil and gas. This problem was similar to that encountered by Gulf with other wells it operated in the Little Knife Field. On July 29, 1980, Gulf removed the workover rig from the Symio-now Well site and, except for routine maintenance visits by the pumper, all physical activity on the site ceased for approximately seven and one-half months. No delay rental payments were tendered on or before October 6 or 7, 1980, the anniversary dates of the leases.

After evaluating the test data, Gulf decided in October 1980 to develop a special casing liner as a possible remedy, a technique that previously had not been used in the Little Knife Field. Gulf decided to install the liner in a well known as the Kostelnak Well, which had problems similar to those encountered with the Symio-now Well, to test whether the liner concept was feasible from an engineering standpoint. The Kostelnak Well, in which the plaintiffs had no interest, was chosen by Gulf for installation of the liner because of its greater producing capacity and because Gulf was the only working interest holder, thereby obviating the need for obtaining consent from other parties.

*811 In late December 1980 and early January 1981, Kiker tendered delay rental payments to the plaintiffs, which they refused to accept and returned to him. By mid-January 1981, the special liner had arrived and Gulf installed it in the Kostelnak Well, but because of other problems at the well site, production was not restored. Gulf, however, determined that the concept of the liner was feasible and could be used in the other wells located in the Little Knife Field.

During March 1981, Gulf returned to the Symionow Well and attempted to perforate another zone to determine whether sufficient additional quantities of oil and gas could be recovered to justify the cost of installing the special liner to correct the casing leaks. Pumping operations were continued until May 3, 1981, when Gulf determined that no oil or gas could be obtained from the additional zone. No liner was installed and the Symionow Well was abandoned. In the meantime, Martin, pursuant to a farm-out agreement with Kiker, had staked a well on March 12,1981, in Section 3 on lands pooled by agreement of the plaintiffs. The well was completed on August 1, 1981, and it produced oil in commercial quantities.

The plaintiffs, in February 1981, served written demands upon Kiker and Martin pursuant to § 47-16-36, N.D.C.C., that the two oil and gas leases be released of record. Kiker and Martin replied pursuant to the statute and asserted that the leases were in full force and effect. The plaintiffs instituted the present action against Kiker and Martin in September 1981 seeking cancellation of the leases and damages for slander of title. The plaintiffs claimed that the leases expired by their own terms because of the failure to timely pay delay rentals. Kiker and Martin asserted that the leases remained in effect because reworking operations were commenced within 60 days after the Symionow Well ceased production, and counterclaimed for damages for malicious prosecution. Kiker and Martin also brought a third-party action against Gulf seeking contribution or indemnity and asserting negligence in its operation of the Symionow Well.

Following a bench trial on the- issue of liability alone, 1 the trial court dismissed the plaintiffs’ action. The court determined that, “as a matter of law, ‘reworking operations’ as contemplated in the leases commenced” on the Symionow Well within 60 days from the date that production ceased; that the actions of Gulf “were those of a prudent operator” and that Gulf “exhibited good faith and a bona fide intent to restore production” of the well; that reworking operations included “the testing and evaluation of the casing problems” on the Symio-now Well and “the efforts of Gulf to determine the engineering feasibility of a liner in the Little Knife Field that could be used” on the well; that the “subsequent determination of engineering feasibility and recompletion of the well constituted additional reworking operations in an attempt to restore production;” and that Gulf’s reworking operations “held the ... leases through the time that operations were commenced by Martin ... which culminated in a producing oil well in Section 3, ...” In a subsequent separate order incorporated into the amended final judgment, the court granted the plaintiffs’ motion for partial summary judgment dismissing Kiker and Martin’s counterclaims for malicious prosecution. The court also dismissed as moot Kiker and Martin’s third-party action against Gulf. These appeals followed.

The oil and gas leases involved in this case are “unless” leases. 2 An “unless” clause does not obligate the lessee to do an act but provides that the lease shall terminate unless the lessee does some act. The “unless” clause does not state a condi *812

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Zavanna v. Gadeco
2023 ND 142 (North Dakota Supreme Court, 2023)
Great Plains Royalty Corp. v. Earl Schwartz Co.
2021 ND 62 (North Dakota Supreme Court, 2021)
Abell v. GADECO, LLC
2017 ND 163 (North Dakota Supreme Court, 2017)
Horob v. Zavanna, LLC
2016 ND 168 (North Dakota Supreme Court, 2016)
Beaudoin v. JB Mineral Services, LLC
2011 ND 229 (North Dakota Supreme Court, 2011)
Van Berkom v. Cordonnier
2011 ND 239 (North Dakota Supreme Court, 2011)
Anderson v. Hess Corp.
649 F.3d 891 (Eighth Circuit, 2011)
Anderson v. Hess Corp.
733 F. Supp. 2d 1100 (D. North Dakota, 2010)
Disciplinary Board of the Supreme Court v. Korsmo
2006 ND 148 (North Dakota Supreme Court, 2006)
In Re Disciplinary Action Against Korsmo
2006 ND 148 (North Dakota Supreme Court, 2006)
Maragos v. Union Oil Co. of California
1998 ND 180 (North Dakota Supreme Court, 1998)
Roemer Oil Co. v. Aztec Gas & Oil Corp.
886 P.2d 259 (Wyoming Supreme Court, 1994)
Disciplinary Action Against Kaiser
484 N.W.2d 102 (North Dakota Supreme Court, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
392 N.W.2d 808, 91 Oil & Gas Rep. 278, 1986 N.D. LEXIS 397, Counsel Stack Legal Research, https://law.counselstack.com/opinion/serhienko-v-kiker-nd-1986.