Rogers v. Osborn

250 S.W.2d 296, 1 Oil & Gas Rep. 1417, 1952 Tex. App. LEXIS 1592
CourtCourt of Appeals of Texas
DecidedMay 28, 1952
Docket12362
StatusPublished
Cited by8 cases

This text of 250 S.W.2d 296 (Rogers v. Osborn) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rogers v. Osborn, 250 S.W.2d 296, 1 Oil & Gas Rep. 1417, 1952 Tex. App. LEXIS 1592 (Tex. Ct. App. 1952).

Opinion

NORVELL, Justice.

Certain operations described as “periodic flowing” were undertaken by ap-pellees to bring in an oil or gas well, and the question presented by this lawsuit is whether or not such actions may be properly considered as “drilling or re-working operations” under the provisions of the oil and gas lease involved.

Appellants are the named lessors in a written instrument dated September 21, 1942, and the successors in interest of said lessors. The appellees are the lessee and those claiming under him.

The pertinent clauses of the lease are contained in paragraphs 2 and 5 thereof and are as follows:

“2. Subject to the other provisions herein contained, this lease shall be for a term of five (5) years from this date (called ‘primary term’) and as long thereafter as oil, gas or other mineral is produced from said land hereunder.”
“5. * * * If at the expiration of the primary term oil, gas or other mineral is not being produced on said land but lessee is then engaged in drilling or re-working operations thereon, this lease shall remain in force so1 long as operations are prosecuted with no cessation of more than thirty (30) consecutive days, and if they result in the production of oil, gas or other mineral so long thereafter as oil, gas or other mineral is produced from said land.”

The jury findings were for appellees and appellants’ position here is that they were entitled to judgment declaring the lease terminated as a matter of law, and consequently their motion for an instructed verdict or for judgment non obstante vere-dicto should have been granted.

The following facts are undisputed:

The primary term of the lease expired on September 21, 1947, and prior thereto on May IS, 1947, the actual drilling of a well, designated as Clopton No. 1, was commenced. Casing was set at 6,256 feet on June 21st. This was perforated at the 3,900, 4,400, 5,600 and 5,690-5,700 foot levels. The Christmas tree (a piece of equipment with numerous valves for flowing and operating the well) was set on July 20, 1947. Tubing was run in the casing and an American packer set. The derrick was torn down and the drilling tools taken away on July 30th. From then until November 12th (and perhaps longer), the well was subjected to the process of “periodic flowing,” hereinafter described.

A re-working rig was moved over the hole on November 12th, but the operator was unable to complete the well as a producer. He moved off on November 29th, and since that time no work of any kind or character has been done upon Clopton No. 1. (Theré seems to be some dispute as to this, as appellees assert that attempts to bring in the well continued until the present suit was filed.)

On October 25th, appellants notified ap-pellees in writing of their claim that the lease had terminated. However, on October 31st appellees commenced the actual drilling of Clopton No. 2, which was completed as a gas producer. The well was shut in for lack of market and appellees have tendered to appellants the sum of $500 per year for said shut in gas well, in accordance with the terms of the lease. It is the gas production of Clopton No. 2 which is relied upon as perpetuating the lease under the clause which provides that the same shall remain in force as long “as oil, gas or other mineral is produced from said land.”

There is one preliminary matter to be disposed of. Appellants contend that as work on Clopton No. 2 was not in progress at the time of the expiration of the primary term (September 21, 1947), production from said well can not be relied upon to perpetuate the lease. This result is arrived at by construing the clause as if the words, “which were in progress at the time o.f the expiration of the primary term,” immediately followed the word, “operations,” the second time the same was used in the clause, viz-:

*298 “If at the expiration of the primary term, oil, gas, or other mineral is not being produced on said land hut lessee is then engaged in drilling or re-working operations thereon, this lease shall remain in force so long as operations •which were in progress at the time of the expiration of the primary term are prosecuted, with no cessation of more than thirty (30) consecutive days, etc.”

Neither party has cited a case directly in point upon the conflicting constructions of this particular clause and we have found none. However, it seems that appellants’ position is untenable under the primary rule that, “a written instrument must ordinarily be interpreted to mean what on its face it purports to mean, unless some good reason can be assigned to show that the words used should be understood in a different sense.” 12 Am.Jur. 751, Contracts, § 229. No limitation is placed upon the word “operations” the second time it is used in the clause, but it possesses the same broad connotation or meaning that it has when used the first time in the clause. There is -no verbal basis for restricting “operations” to those actually being prosecuted at the end of the primary term. The clause means that, “If at the expiration of the primary term oil, gas or other mineral is not being produced on said land but lessee is then engaged in drilling or reworking operations on said lamd, this lease shall remain in force so long as drilling or reworking operations on said land are prosecuted with no cessation of more than (30) consecutive days,” etc.

Under this clause, the lessee may keep the lease in force after the primary term by conducting continuous drilling or reworking operations on the land with no cessation of more than thirty consecutive days, providing, of course, drilling or reworking operations were being prosecuted at the termination of the primary term. The drilling of Clopton No. 2 was a drilling operation upon th,e land. The question then is whether or not continuous drilling or re-working operations (with no more than 30 days cessation) were prosecuted upon the land covered by the lease from the termination of the primary term to the commencement of drilling operations upon Clopton No. 2.

The jury found that drilling operation and re-working operations upon Clopton No. 1 were maintained during that period of time. Appellants take the position that the evidence conclusively shows the contrary as a matter of law.

This brings us to a consideration of the “periodic flowing” process above referred to, which was used in an attempt to bring in Clopton No. 1, as a producer.

Appellees’ testimony shows that during the drilling of Clopton No. 1 heavy gas pressures were encountered. I. K.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Harrington
407 S.W.2d 467 (Texas Supreme Court, 1966)
Stanolind Oil & Gas Co. v. Newman Brothers Drill. Co.
305 S.W.2d 169 (Texas Supreme Court, 1957)
Clopton Rogers v. Osborn
261 S.W.2d 311 (Texas Supreme Court, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
250 S.W.2d 296, 1 Oil & Gas Rep. 1417, 1952 Tex. App. LEXIS 1592, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rogers-v-osborn-texapp-1952.