Clark v. City of Seward

659 P.2d 1227, 1983 Alas. LEXIS 388
CourtAlaska Supreme Court
DecidedFebruary 25, 1983
Docket5457
StatusPublished
Cited by7 cases

This text of 659 P.2d 1227 (Clark v. City of Seward) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clark v. City of Seward, 659 P.2d 1227, 1983 Alas. LEXIS 388 (Ala. 1983).

Opinions

OPINION

MATTHEWS, Justice.

In February of 1971 appellant, Engineering Science of Alaska (ESAL) contracted [1228]*1228with appellee, the City of Seward, to perform engineering services as required for the design and construction of a sewage treatment plant and for the extension of the City’s water and sewer systems to a new subdivision. The contract called for ESAL to prepare a preliminary engineering report for review by an agency of the federal government and by the City. After, such review, the City could then direct ESAL to prepare a detailed design of the project, but the City was under no obligation to do so until it was satisfied “that funds are then or will be available within one year, in an amount sufficient to pay the entire project costs.”

The preliminary engineering report was completed before July 30,1971. A modified report was authorized by the City on April 6, 1972, to deal with industrial water flows. This was submitted to the City in November of 1972.

On July 25, 1973, the City directed ESAL “to proceed with the preliminary and final design of the project.” In August of 1973 the City was advised that the Environmental Protection Agency (EPA) had recently promulgated a requirement that a study be made of any existing sewer system as a condition to the allocation of grant funds for sewage treatment plants. The study had two parts. First, an infiltration and inflow analysis was to be conducted to determine if too much clear water was entering the system. Secondly, if it was determined that there was a problem in this respect, a report evaluating the cost and effectiveness of various means of dealing with the problem was required.

A first phase draft report was completed in October of 1973 and forwarded to the City, EPA, and the Economic Development Administration (EDA). It' concluded that a serious excess inflow problem existed during the winter. This was caused by water users leaving faucets on to prevent freezing, a practice necessitated by the fact that a large number of the water lines in the City were too shallow. The excessive flow of clean water in the system would require, according to the report, a treatment plant larger than would otherwise be needed, and resulted in high water system pumping costs. Further, the report questioned whether the dilute waste could be effectively treated with a conventional biological system and suggested that a more complex and expensive method of treatment might be required.

The draft report outlined a corrective action program including excavating and lowering shallow water lines or, where feasible, insulating or installing heat tapes on them, installing water meters to discourage water wastage, and passing City codes to insure proper installation of new lines. The report also recommended that the corrective action program be declared eligible for a grant to the extent of 87 ½% of its cost and concluded that the second phase of the required study proceed to establish detailed corrective recommendations and costs, and treatment plant design.

On October 27, 1973 a representative of the EDA wrote the City asking whether it had any objection to using meters in order to conserve water. The City Manager’s response, given on November 12, 1973, was that while the City did not object to water meters per se, “such an installation for individual residential services would create problems in installation, servicing and would also result in reduced flows with increased incidents of freezing. This would be detrimental to the system and would cost thousands of dollars to maintain and repair.” The City Manager suggested as a counter proposal metering commercial accounts only as “one which may fare better before the City Council.”

On November 27, 1973, the City Manager reported by letter to ESAL that the City Council had reviewed the infiltration and inflow analysis, and “have no adverse comments to make regarding it other than to point out a few of the many problems which apparently will be encountered in trying to install meters for residential and commercial use in Seward.” The problems included the high cost of metering, the need to dig out most of the service lines and mains in the City in order to either lower [1229]*1229them, or insulate them and install antifreez-ing devices, and the extensive disruption and repaving that this would entail. The City’s letter concluded:

If you will incorporate these problems as an addition to the report we have no objection to its being transmitted to the EPA or the State of Alaska for their review.

ESAL responded on December 6, 1973 that the draft phase I infiltration/inflow analysis had already been transmitted to EPA and the State and that copies of the city’s letter would be forwarded to them. ESAL noted that “the specific problems identified ... are those which would be evaluated by the phase II survey work as proposed.... ”

On December 10, 1973, the EDA notified the City that the installation of water meters, apparently throughout the City, would be required as a condition of a grant for the water system expansion. In March of 1974 the EDA formally offered a grant with this condition.

The EDA letter of December 10 requiring water meters caused the City Council to hold a public hearing on the matter on January 28, 1974. The hearing was well attended, and most citizens who testified were strongly against the installation of residential water meters.

ESAL wrote the City on February 19, 1974, advising it that the second phase of the EPA-required study had not yet taken place and that if the study showed that rehabilitation of the water system was not cost effective, EPA would fund a sewage treatment plant adequate to process the unrehabilitated system, while if cost effectiveness was shown EPA would fund the rehabilitation costs as well as the treatment system. ESAL, however, was never given the authority to proceed with the second phase of the study and on April 24,1974 the City terminated its services. The cause for termination was, as expressed by the City Manager at trial, “the fact that they did not resolve the [water meter] question.”

The City then hired another engineer who represented them in their dealings with the various governmental agencies involved. After a delay of more than a year the City was able to obtain grants for the water and sewer system expansions and for a sewage treatment plant which required commercial, but not residential water meters, and did not require that existing water lines be lowered or otherwise protected from freezing. The projects were bid in 1976, and subsequently constructed. The residents of Seward still leave their faucets on to keep their pipes from freezing, and freezing problems persist due to shallow water lines.

ESAL filed suit against the City to recover fees for services performed of $47,620.00 and lost profits of $20,392.00. The City answered denying liability, and counterclaimed for additional costs caused by ESAL in an amount in excess of $200,-. 000.00.

At the trial the City claimed that the projects had been delayed for two years, from 1974 to 1976, due to ESAL’s negligence. This, it claimed, caused an increase in costs of some $207,000.00. In addition, it claimed damages of $79,000.00 for substitute engineering services in excess of those it would have incurred had ESAL performed its contract.

The jury returned a verdict allowing ESAL $31,365.00 on its claim and awarding the City $234,966.21 on its counterclaim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Veys v. Applequist
2007 WY 60 (Wyoming Supreme Court, 2007)
STATE, DEPT. OF NAT. RES. v. Transamerica
856 P.2d 766 (Alaska Supreme Court, 1993)
Matthews v. Kincaid
746 P.2d 470 (Alaska Supreme Court, 1987)
Lamer v. McKee Industries, Inc.
721 P.2d 611 (Alaska Supreme Court, 1986)
Clark v. City of Seward
659 P.2d 1227 (Alaska Supreme Court, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
659 P.2d 1227, 1983 Alas. LEXIS 388, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clark-v-city-of-seward-alaska-1983.