C.J. HUGHES CONSTRUCTION COMPANY INC. v. EQM GATHERING OPCO, LLC

CourtDistrict Court, W.D. Pennsylvania
DecidedJune 24, 2020
Docket2:18-cv-00168
StatusUnknown

This text of C.J. HUGHES CONSTRUCTION COMPANY INC. v. EQM GATHERING OPCO, LLC (C.J. HUGHES CONSTRUCTION COMPANY INC. v. EQM GATHERING OPCO, LLC) is published on Counsel Stack Legal Research, covering District Court, W.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C.J. HUGHES CONSTRUCTION COMPANY INC. v. EQM GATHERING OPCO, LLC, (W.D. Pa. 2020).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF PENNSYLVANNIA

C. J. HUGHES CONSTRUCTION COMPANY, INC. Plaintiff, Civil Action No. 2:18-cv-168 Vv. Hon. William S. Stickman IV

EQM GATHERING OPCO, LLC Defendant.

MEMORANDUM OPINION AND ORDER OF COURT WILLIAM S. STICKMAN IV, District Judge Generally stated, this lawsuit arises out of contractual relationships between Plaintiff C.J. Hughes Construction Company, Inc. (“C.J. Hughes”) and Defendant EQM Gathering OPCO, LLC (“EQM”) pursuant to which C.J. Hughes undertook to construct certain natural gas pipelines. C.J. Hughes claims that it performed work in the construction of the pipelines and that it has not been paid for that work in accordance with the parties’ contract.! Pending before the Court is the Motion for Partial Summary Judgment of C. J. Hughes against EQM on Counts I, Il and VI. (ECF No. 69). C.J. Hughes seeks affirmative summary judgment in its favor on its breach of contract claims and its claims under the Pennsylvania Contractor and Subcontractor Payment Act (“CASPA”). EQM also filed a Motion for Summary Judgment seeking dismissal of all counts of C.J. Hughes’ Amended Complaint. (ECF No. 74). Briefing and oral argument is complete. For the following

! As explained below, the terms of the parties’ contractual regimen are expressed in multiple documents, including a Master Construction Services Agreement and work orders.

reasons, the Court DENIES C.J. Hughes’ Motion in its entirety and GRANTS IN PART and DENIES IN PART EQM’s Motion. FACTUAL BACKGROUND C.J. Hughes is an underground pipeline, utility, and facility construction contractor. In August of 2007, it entered into a Master Construction Services Agreement (“MCSA”) with Equitable Gas Company through which it agreed to perform work on one or more pipeline construction projects for Equitable Gas Company or its affiliates. (ECF No. 69, Exhibit (“Ex.”) O); (ECF No. 77, Ex. 24). EQM is an affiliate of Equitable Gas Company. (ECF No. 71, 9 1-2); (ECF No. 76, § 4). In 2015, EQM began soliciting bids from contractors for the construction of its Mako Pipeline Project (the “Project”). C.J. Hughes, in August of 2015, received an invitation to attend a bid meeting for the Project and a Request for Proposal (“RFP”) that provided descriptions of the scope of the work. The RFP included four segments of pipe installation work — Segments A through D. Of relevance to this lawsuit, the RFP indicated that Segment A work consisted of installing an estimated 8 miles of 24-inch pipe and Segment D included installing 9.7 miles of 30- inch pipe. The RFP instructed that EQM would provide the “pipe, valves, fittings, pre-fabricated assemblies, and CP material to construct the project.” Contractors were invited to submit bids for all or any of the Segments. (ECF No. 71, {] 3-6, 24-26); (ECF No. 76, {| 5-7). Following a pre-bid meeting on August 18, 2015, EQM sent interested contractors a preliminary KMZ file that showed views of the pipeline route. Contractors were also provided with a link to a File Transfer Protocol (“FTP”) site that contained various bid documents contractors were to use for the project. Included within these documents was an “Estimated Fitting Sheet” created by EQM. According to EQM, the factory fittings estimate (41 fittings on Segment

A and 50 fittings on Segment D) was approximately 50% of the factory fittings EQM estimated would be used on the Project. EQM supplied contractors with a bid pricing template and instructed contractors use it to submit their bids for each individual component of the project. Section 10 of the EQM-prepared bid pricing form governed “Non-Contemplated Welding,” and set forth specific rates for any non-contemplated welding, backwelding, and cutting work. (ECF No. 71, 10, 13- 14, 17, 20-21); (ECF No. 76 J 16-18, 21-22). C.J. Hughes’ bid was a “unit priced bid submission” that did not provide a line/pay item for fittings and allegedly relied upon the pricing template provided by EQM. The bid pricing form did not provide a line item for fittings. The bid included line items to compensate for uncontemplated labor, including specific rates for welding, backwelding, and cutting work. C.J. Hughes’ final bids were accepted by EQM for Segments A and D on October 1, 2015. (ECF No. 71, 44 15, 22-23); (ECF No. 76, f§ 23-24); (ECF No. 70, p. 6); (ECF No. 77, Ex. 39). On January 27, 2016, EQM issued a purchase order for the clearing of the Segment D right of way of the pipeline. On or about March 1, 2016, EQM issued a purchase order for the construction of Segment A of the pipeline — an estimated 41,000 feet of 24-inch diameter steel pipe. A June 28, 2016 change order expanded C.J. Hughes’ scope of work as to Segment D to include the installation of an estimated 51,000 feet of 30-inch diameter steel pipe. Neither party disputes that the purchase orders and their incorporated documents (i.e., the 2007 MSCA, the unit price bid submission, the bid appendices listed in the RFP, and the documents included on the ExaVault RFx site) created two contracts between them. EQM agreed to compensate C.J. Hughes according to its “unit priced bid submission.” The individual purchase orders for both Segments A and D state that “line items will be paid according to the submitted bid pricing form and will be

billed on the actuals.” (ECF No. 71, {§ 23-30); (ECF No. 76, 25-27); (ECF No. 69, Ex.BB at p. 2 & Ex. CC at p. 3); (ECF No. 77, Exs. 26-28). Daily Foreman reports captured the day-to-day work performed by C.J. Hughes on Segments A and D. Wade Carver “engineered” C.J.’s pipeline construction and recorded the information concerning pipe joint lengths, cut locations, fitting angles and ends in his logbooks. During construction, C.J. Hughes invoiced EQM weekly. The parties dispute whether C.J. Hughes invoiced EQM for work on Segments A and D specifically identified as a fitting. Some invoices included payment sought for non-contemplated welding and cutting. (ECF No. 76, {| 28-30, 33- 37, 40-41, 49-51, 63-65); (ECF No. 82, 40-41, 49-51, 63-65). Following the installation of the pipeline on Segment A and Segment D, C.J. Hughes determined the exact footage of pipeline installed and the number of fittings used in both segments by using reports generated by Enduro Pipeline Services, Inc. (“Enduro”). Enduro sent a “smart pig” (the “Enduro run”), through Segment A on July 16, 2016. Segment A was 43,108 feet of pipeline and it required 121 fittings and 1,176 welds. The report for Segment A was prepared on July 29, 2016, and a true-up meeting occurred for Segment A on July 30, 2016. On August 2, 2016, C.J. Hughes submitted a true-up invoice to EQM”; it included no new charges for non- contemplated welding, cutting or back welding. (ECF No. 71, ff] 36-38, 56); CECF No. 76, {4 53- 54); (ECF No. 82, 9 53-54); (ECF No. 69, Ex. HH); (ECF No. 77, Ex. 47). The Enduro run for Segment D occurred on December 28, 2016. Segment D was 52,288 feet of pipeline and required 111 fittings. C.J. Hughes submitted what EQM believed to be the

2 C.J. Hughes has countered that not all line item quantities were trued up on this date as the final grading was still being performed and was only 70% complete. Furthermore, it argues that it was not contractually obligated to bill all line item quantities. (ECF No. 82, § 54).

true-up of line item quantities on January 3, 2017.2 (ECF No. 71, {§ 36-38, 56); (ECF No. 76, 4 66); (ECF No. 82, 9 56); (ECF No. 69, Ex. GG); (ECF No. 77, Ex. 48). On January 11, 2017, C.J. Hughes sent EQM a Request for Information (“RFT”) #5 seeking additional compensation for the excess fittings it installed on Segment D. (ECF No. 76, §{ 55- 57); (ECF. No. 82, §§ 55-57); (ECF No. 77, Ex. 49).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
American Eagle Outfitters v. Lyle & Scott Ltd.
584 F.3d 575 (Third Circuit, 2009)
Gonzalez v. United States Steel Corp.
398 A.2d 1378 (Supreme Court of Pennsylvania, 1979)
Wingert v. T. W. Phillips Gas & Oil Co.
157 A.2d 92 (Supreme Court of Pennsylvania, 1959)
Schott v. Westinghouse Electric Corp.
259 A.2d 443 (Supreme Court of Pennsylvania, 1969)
Wilson Area School District v. Skepton
895 A.2d 1250 (Supreme Court of Pennsylvania, 2006)
Gurenlian v. Gurenlian
595 A.2d 145 (Superior Court of Pennsylvania, 1991)
John B. Conomos, Inc. v. Sun Co., Inc.
831 A.2d 696 (Superior Court of Pennsylvania, 2003)
Bruno, D., Aplts. v. Erie Insurance
106 A.3d 48 (Supreme Court of Pennsylvania, 2014)
Dommel Properties LLC v. Jonestown Bank and Trust Compa
626 F. App'x 361 (Third Circuit, 2015)
Bell, Secy. of Banking v. Brady
31 A.2d 547 (Supreme Court of Pennsylvania, 1943)
Third National Bank & Trust Co. v. Lehigh Valley Coal Co.
44 A.2d 571 (Supreme Court of Pennsylvania, 1945)
Cole v. Lawrence
701 A.2d 987 (Superior Court of Pennsylvania, 1997)
Shafer Electric & Construction v. Mantia
67 A.3d 8 (Superior Court of Pennsylvania, 2013)
Durham Terrace, Inc. v. Hellertown Borough Authority
148 A.2d 899 (Supreme Court of Pennsylvania, 1959)
Tax Matrix Technologies, LLC v. Wegmans Food Markets, Inc.
154 F. Supp. 3d 157 (E.D. Pennsylvania, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
C.J. HUGHES CONSTRUCTION COMPANY INC. v. EQM GATHERING OPCO, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cj-hughes-construction-company-inc-v-eqm-gathering-opco-llc-pawd-2020.