C.J. HUGHES CONSTRUCTION COMPANY INC. v. EQM GATHERING OPCO, LLC

CourtDistrict Court, W.D. Pennsylvania
DecidedJune 28, 2022
Docket2:18-cv-00168
StatusUnknown

This text of C.J. HUGHES CONSTRUCTION COMPANY INC. v. EQM GATHERING OPCO, LLC (C.J. HUGHES CONSTRUCTION COMPANY INC. v. EQM GATHERING OPCO, LLC) is published on Counsel Stack Legal Research, covering District Court, W.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C.J. HUGHES CONSTRUCTION COMPANY INC. v. EQM GATHERING OPCO, LLC, (W.D. Pa. 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF PENNSYLVANIA

C.J. HUGHES CONSTRUCTION COMPANY INC., Plaintiff, Civil Action No. 2:18-cv-168 V. Hon. William S. Stickman IV EQM GATHERING OPCO, LLC, □ Defendant.

MEMORANDUM OPINION Plaintiff C.J. Hughes Construction Company (“C.J. Hughes”) brought this action against Defendant EQM Gathering OPCO, LLC (“EQM”), raising several claims that EQM breached contracts relating to C.J. Hughes’s construction of a natural gas pipeline. After a twelve-day trial, the jury returned a verdict for C.J. Hughes on some claims and EQM on others. The jury awarded an aggregate sum of $5,883,786.68 in damages to C.J. Hughes. EQM has filed a Motion for Judgment as a Matter of Law and for a New Trial pursuant to Federal Rules of Civil Procedure 50 and 59. (ECF No. 187). For the reasons set forth below, the Court will deny the motion. The jury’s verdict will stand. I. FACTUAL AND PROCEDURAL HISTORY C.J. Hughes is a West Virginia corporation that offers various construction services, including the construction of natural gas pipelines. EQM is in the business of constructing natural gas pipelines. In 2015, EQM sought bids from contractors for the construction of a natural gas pipeline in southwestern Pennsylvania called the MAKO pipeline. The overall pipeline project was divided into four segments—Segments A, B, C, and D. EQM provided

prospective bidders with information regarding the project and held a meeting to answer any questions that contractors might have had. Among the information that contractors were provided was an electronic resource called a KMZ file. This file was a map of each segment of the project showing the topography, necessary bends, road crossings, stream crossings and other geographical information relating to the project. The KMZ file was intended to educate contractors about the requirements of installation for each segment in order to allow them to make reasonable projections of work and costs to serve as foundations for their bids. But at trial, the jury heard evidence that the route depicted on the KMZ file was considerably different than the route that EQM ultimately selected for the project. Prospective bidders were also provided information about the number of fittings projected for each segment of the pipeline. A fitting is a curved elbow that allows a pipe to make a turn to a degree greater than bending will permit. Compared to laying straight-a-way pipe and curving by bending, fittings are time-, labor- and cost-intensive. They require multiple cuts, multiple welds and coating to create an elbow that will facilitate the appropriate turn. Testimony and exhibits demonstrated that EQM provided a projected number of fittings for contractors to include as part of their base-lay bids. For Segment A, EQM represented that there would be 41 fittings. For Segment D, it represented that there would be 50. C.J. Hughes included those amounts in its bid.! EQM also provided prospective contractors with the average pipe length for pipe segments that EQM would source and provide. For Segment A, it stated that the average pipe length would be 44 feet. In actuality, the average length was shorter due to EQM obtaining

' As to Segment D, C.J. Hughes mistakenly included only 22 fittings in its bid. It made no claim for fittings 23-50.

savings on shipping shorter pipes. EQM knew of this change during the bidding process and recognized that it was at odds with what the contractors had been told. Nevertheless, there was no evidence presented showing that the contractors were ever informed of the change. Testimony explained that pipe length matters because shorter pipes cannot be bent as much as longer pipes, which can result in the need for more fittings. Further, shorter pipes need more welds across the length of a pipeline. C.J. Hughes was the successful bidder on Segments A and D of the project. The contract documents for each of the two segments included a Master Construction Services Agreement (“MCSA”), the Purchase Orders, Appendices to the Purchase Orders, and various other documents referenced in the Purchase Orders. C.J. Hughes performed the work required to complete Segments A and D. It was paid the base-lay price under the contracts. Nevertheless, when C.J. Hughes submitted demands for additional compensation for work beyond the initial EQM projections, that was needed to complete the project, EQM refused payment. After informal negotiations broke down, C.J. Hughes initiated this action. C.J. Hughes ultimately proceeded to trial on three overarching breach of contract theories. First, C.J. Hughes claimed that it was required to install significantly more fittings on Segments A and D than it had included in its bid as part of the base-lay price. C.J. Hughes based its base-lay bid on the representations that EQM provided to contractors during the bidding process. C.J. Hughes sought to be paid for each of the additional fittings needed to complete the project at the unit prices for “Non-Contemplated Welding” in the Purchase Orders. C.J. Hughes argued, and presented evidence, that the parties had intended that C.J. Hughes would be paid on actuals, rather than be limited to the number of fittings represented by EQM that made the basis of its base-lay bid. C.J. Hughes claimed that EQM’s failure to pay for the installation of fittings

beyond the number it represented in the bidding process was a breach of the contracts. EQM admitted that C.J. Hughes installed substantially more fittings than was projected by EQM during the pre-bid process. Nevertheless, it denied it was obligated to pay on multiple grounds. As a threshold matter, EQM argued that C.J. Hughes’s claims for payment were untimely because they were asserted outside of the one-year contractual limitations period set forth in the MCSA. Next, as a substantive defense, EQM contended that the number of fittings that it projected to the contractors was just an estimate and that C.J. Hughes was not entitled to be compensated for supernumerary fittings actually installed beyond the base-lay contract price. Finally, in the alternative, EQM argued that if C.J. Hughes was entitled to payment for the additional fittings, it was required to go through the contractual conditions for compensation for “extra work.” As its second breach of contract theory, C.J. Hughes claimed it had to perform more welding than originally anticipated for two reasons. The first was that the average lengths of the pipe joints that were furnished and delivered by EQM to C.J. Hughes for installation on Segment A of the project were shorter than what was agreed upon in the contract. Pipe joints are the individual pieces of pipe that are all welded together to make a pipeline. C.J. Hughes claimed that, because the pipe joints that were delivered were shorter on average than EQM stated they would be, C.J. Hughes had to do more welding to install the pipeline than was originally anticipated. C.J. Hughes’s second claim relating to welds was that the pipe joints provided at Segment D were thicker than represented, requiring more weld passes to join segments together. C.J. Hughes sought to be paid at the “non-contemplated welding” unit prices in the contracts to perform these welds and contended that EQM’s failure to pay for those costs was a breach of the Segment A and Segment D purchase orders.

EQM admitted that the pipe joints on Segment A were shorter than represented to C.J. Hughes and other contractors. But it contended that the impact on C.J. Hughes was less than claimed. It also argued that C.J. Hughes made its initial claim for compensation outside the limitations period.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Douglas v. Owens
50 F.3d 1226 (Third Circuit, 1995)
Reeves v. Sanderson Plumbing Products, Inc.
530 U.S. 133 (Supreme Court, 2000)
Donlin v. Philips Lighting North America Corp.
581 F.3d 73 (Third Circuit, 2009)
Marra v. Philadelphia Housing Authority
497 F.3d 286 (Third Circuit, 2007)
Darien Capital Management, Inc. v. Commonwealth
700 A.2d 395 (Supreme Court of Pennsylvania, 1997)
Bhaya v. Westinghouse Electric Corp.
709 F. Supp. 600 (E.D. Pennsylvania, 1989)
Gurenlian v. Gurenlian
595 A.2d 145 (Superior Court of Pennsylvania, 1991)
Montgomery County v. MicroVote Corp.
152 F. Supp. 2d 784 (E.D. Pennsylvania, 2001)
Bell, Secy. of Banking v. Brady
31 A.2d 547 (Supreme Court of Pennsylvania, 1943)
Andrew Leonard v. Stemtech International Inc
834 F.3d 376 (Third Circuit, 2016)
Dunn v. HOVIC
1 F.3d 1371 (Third Circuit, 1993)
Lightning Lube, Inc. v. Witco Corp.
4 F.3d 1153 (Third Circuit, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
C.J. HUGHES CONSTRUCTION COMPANY INC. v. EQM GATHERING OPCO, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cj-hughes-construction-company-inc-v-eqm-gathering-opco-llc-pawd-2022.