City of Wahpeton v. Drake-Henne, Inc.

228 N.W.2d 324
CourtNorth Dakota Supreme Court
DecidedApril 2, 1975
DocketCiv. 9067
StatusPublished
Cited by50 cases

This text of 228 N.W.2d 324 (City of Wahpeton v. Drake-Henne, Inc.) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Wahpeton v. Drake-Henne, Inc., 228 N.W.2d 324 (N.D. 1975).

Opinions

VOGEL, Justice.

This is an appeal from an order of the district court of Richland County denying the motion of the defendants under Rule 60(b), North Dakota Rules of Civil Procedure, to vacate a judgment against the defendants and grant a new trial on the issue of damages.

The judgment in question was entered pursuant to the majority opinion in a previous appeal reported at 215 N.W.2d 897 (N.D.1974).

THE FACTS AND CONTENTIONS OF THE PARTIES

The action arose from a dispute over whether the defendant Drake-Henne, Inc., properly performed a contract to construct storm sewer, sanitary sewer, and waterworks improvements. A simultaneous contract between the City and a third party provided for pavement to be laid over the sewer and water mains. The trial court, sitting without a jury, found that the paving was defective due to failure of the sewer and water contractor to compact the soil beneath the paving to the degree required by the contract. Defendant Johnson, Drake & Piper, Incorporated, is the successor to Drake-Henne, and defendant American Casualty Company is surety on its performance bond.

Judgment was entered for $58,367.30. The defendants appealed, and the City, claiming the damages inadequate, cross-appealed. The appeals were filed in 1968 and argued in 1973. The delay was due largely to inaction by former counsel for the City. An opinion was written, a petition for rehearing was granted, and upon rehearing a majority affirmed the judgment of the trial court on the issue of liability but modified it as to damages and directed that judgment be entered in favor of the City in the amount of $517,791.60. It should be noted that the former appeal was taken under former Section 28-27-32, N.D.C.C., allowing trial de novo in the Supreme Court. Trials de novo have since been abolished. Ch. 311, 1971 S.L.

A petition for certiorari to the United States Supreme Court was made and was denied. 419 U.S. 986, 95 S.Ct. 245, 42 L.EJd.2d 194 (1974).

Judgment on remittitur was entered on May 2, 1974. The defendants thereafter [327]*327made a motion to the district court under Rule 60(b), N.D.R.Civ.P., to vacate the judgment and grant a new trial on the issue of damages.

The defendants’ motion under Rule 60(b)(2), (5), and (6), is based on claims: (1) of newly discovered evidence which by due diligence could not have been discovered in time to move for a new trial under Rule 59, N.D.R.Civ.P.; (2) that it no longer is equitable that the judgment should have prospective application; and (3) that other reasons justify the granting of relief from the judgment.

The motion to reopen is based upon affidavits of William H. DeButts, James L. Lamb, and John Drake, and upon a letter from Robert L. Eckert, city attorney of Wahpeton, to Mr. Lamb, dated June 18, 1974.

The letter of Mr. Eckert, written during settlement negotiations after the case was decided by this court, was a reply to an inquiry as to the amount of repairs to the pavement project since it was completed. Mr. Eckert stated that about $2,000 had been spent in 1970, about $6,400 in 1971, about $10,200 in 1972, and about $9,700 in 1973, and that $10,000 was projected for expenditures in 1974. He also stated that the city engineer estimated that less than 50 percent of the necessary repairs had been completed.

From these statements the defendants argue that total repairs necessary to the project would be slightly more than double the expenditures made through 1974, or about $80,000, and that therefore the judgment in favor of the City in the amount of $517,791.60 constitutes a windfall to the City, and the judgment should not be allowed to stand.

This argument ignores- a portion of Mr. Eckert’s letter stating that “ . . . the City Engineer’s office has been taking this on a year-by-year basis. Obviously the City is limited in regard to its funds available for repairs so it is prohibited from making all of the repairs at one particular time.” In further explanation of the letter and in opposition to the motion, the City submitted affidavits of Mr. Eckert and the City engineer to the effect that the repairs made were only patchwork, that the City had no way of raising the money necessary to do more, and that to restore the streets, sidewalks, and boulevards to the condition they would have been in if Drake-Henne had performed its contract according to its terms would cost in excess of $1,000,000.

The affidavit of Mr. DeButts, who was a witness at the original trial, shows that he spent approximately 4V2 hours on August 12, 1974, driving over and inspecting the project, and that in his opinion the curb and gutter, pavement, and boulevard over or directly adjacent to trenches excavated by the defendant Drake-Henne had stabilized and would not significantly or substantially change in the future other than as a result of normal deterioration; that no further trenches would need to be disturbed or re-compacted; that all present irregularities in the pavement can be repaired and maintained at nominal normal maintenance cost; and that only approximately 3,045 feet of curb and gutter had been replaced since the termination of the project on August 5, 1963.

In opposition to the DeButts affidavit the City presented affidavits of Arden Anderson, city auditor of Wahpeton, Ross Milne, a consulting engineer, and Adolph Tryba, city engineer for the City of Wahpeton. The Anderson affidavit indicates that there have been numerous breaks in city water mains which were directly caused by improper backfilling on the project; that there will be recurring problems due to curbs sinking and applying pressure to water and sewer lines; that some houses in one addition to the city were having trouble with private sewer line blockage resulting from improper backfilling; and that the City was being asked to compensate the private owners for losses.

The Milne affidavit was to the effect that the patching of the streets in the project [328]*328area did not take care of the underlying-defects, which could be corrected only by a general reconstruction of the streets to improve traffic and correct grade and drainage problems; that maintenance costs are higher because of the defective streets; that until drainage is restored the curbs and gutters will continue to shift, which will cause increased breaking up of the pavement; and that to put the project into condition called for by the contract would cost in excess of $1,000,000. The affidavit of Adolph Tryba was substantially similar.

The affidavit of Robert Eckert, previously referred to, also stated that Wahpeton was exposed to great legal liability by reason of sinking sidewalks, which constituted a threat to the safety of the public, for which the City was liable.

The defendants vigorously assert that the affidavits, fairly read, show that the soil in the project area has now stabilized; that the City does not plan to tear up and reconstruct the entire project; that the damages attributable to the cost of recompacting were excessive in the amount of at least $133,000; and that the case should be reopened and a new trial granted on the issue of damages.

We do not so read the affidavits. It may very well be true that with the passage of some 11 years since the completion of the project natural compaction and partial or complete stabilization of the soil has occurred.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Allery v. Whitebull
2022 ND 140 (North Dakota Supreme Court, 2022)
Hoffarth v. Hoffarth
2020 ND 218 (North Dakota Supreme Court, 2020)
Key Energy Services, LLC v. Ewing Construction Co., Inc.
2018 ND 121 (North Dakota Supreme Court, 2018)
Hildebrand v. Stolz
2016 ND 225 (North Dakota Supreme Court, 2016)
Monster Heavy Haulers, LLC v. Goliath Energy Services, LLC
2016 ND 176 (North Dakota Supreme Court, 2016)
Silbernagel v. Silbernagel
2011 ND 140 (North Dakota Supreme Court, 2011)
State v. Ennen
2011 ND 130 (North Dakota Supreme Court, 2011)
Shull v. Walcker
2009 ND 142 (North Dakota Supreme Court, 2009)
Kautzman v. Kautzman
2003 ND 140 (North Dakota Supreme Court, 2003)
Matrix Properties Corp. v. TAG INVESTMENTS
2002 ND 86 (North Dakota Supreme Court, 2002)
Lang v. State
2001 ND App 2 (North Dakota Court of Appeals, 2001)
Delzer v. United Bank of Bismarck
1997 ND 3 (North Dakota Supreme Court, 1997)
State v. Torres - Criminal No. 960244
North Dakota Supreme Court, 1997
North Shore, Inc. v. Wakefield
542 N.W.2d 725 (North Dakota Supreme Court, 1996)
Neubauer v. Neubauer
524 N.W.2d 593 (North Dakota Supreme Court, 1994)
Federal Land Bank of Saint Paul v. Ziebarth
520 N.W.2d 51 (North Dakota Supreme Court, 1994)
Gilbert v. City of Caldwell
732 P.2d 355 (Idaho Court of Appeals, 1987)
Federal Savings & Loan Insurance Corp. v. Albrecht
379 N.W.2d 266 (North Dakota Supreme Court, 1985)
Lang v. Bank of North Dakota
377 N.W.2d 575 (North Dakota Supreme Court, 1985)
Fleck v. Fleck
337 N.W.2d 786 (North Dakota Supreme Court, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
228 N.W.2d 324, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-wahpeton-v-drake-henne-inc-nd-1975.