City of Oxnard v. The United States

851 F.2d 344, 34 Cont. Cas. Fed. 75,513, 1988 U.S. App. LEXIS 9109, 1988 WL 69050
CourtCourt of Appeals for the Federal Circuit
DecidedJuly 6, 1988
DocketAppeal 87-1638
StatusPublished
Cited by16 cases

This text of 851 F.2d 344 (City of Oxnard v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Oxnard v. The United States, 851 F.2d 344, 34 Cont. Cas. Fed. 75,513, 1988 U.S. App. LEXIS 9109, 1988 WL 69050 (Fed. Cir. 1988).

Opinion

PAULINE NEWMAN, Circuit Judge.

We affirm the decision of the Armed Services Board of Contract Appeals 1 denying the claims of the City of Oxnard for payment, on behalf of the Department of the Navy, of a share of the cost overruns incurred by Oxnard in performance of Contract Nos. N62474-76-C-6511 and N62474-76-C-6512.

Discussion

In accordance with the contracts, Navy installations at Port Hueneme, California and Point Mugu, California would be connected to Oxnard’s sewer service lines and waste water treatment facilities, requiring inter alia the construction of adequate connections and the upgrading of Oxnard’s regional waste water treatment plant. The two contracts provided that the Navy would pay a designated “Connection Charge”, which was a share of the total construction costs. The Connection Charge *346 was described in the contracts as “not to exceed” a stated amount. 2

Oxnard asserts that the mutual intent and understanding was that the Navy would pay a proportionate share of the total actual costs, and that Navy representatives orally so assured Oxnard as it became apparent, during the course of construction, that the costs would exceed the estimates on which the Navy’s share was calculated. The Navy’s position is that it never gave such assurances, that such assurances if given were unauthorized and therefore of no effect, that the written contract must prevail, and that Navy representatives told and wrote Oxnard that the “not to exceed” price was the government’s maximum liability. Oxnard replies that persons representing the Navy told them that “not to exceed” clauses were always included in Navy contracts, but that the Navy would pay its fair share and when the project was finished the Navy would request any necessary additional funds. The Navy ultimately refused to pay a share of the increased costs.

Witnesses on both sides testified in support of their respective positions. The Board found credible the denial of the Navy’s representative that she had given the assurances attributed to her, and placed weight on various letters from Navy contracting officials, written in connection with change orders and progress payments and expressly stating that the “not to exceed” price was the maximum commitment. Such correspondence spans several years, and is illustrated as follows:

Letter dated May 10, 1978 from Sukeo Oji, Head, Commercial Utilities Branch, Western Division, Naval Facilities Engineering Command: to the Director of Public Works of the City of Oxnard:
Your attention is called to the requirement that total construction costs, in-eluding all change orders previously effected and the instant change order in the sum . of $421,101, shall not exceed $1,649,796.

Letter dated March 13, 1979 from C.C. Hoffner, Jr., Director, Utilities Division (Navy) to the Oxnard Director of Public Works:

Your attention is called to the requirement that total costs, including all change orders (amendments) shall not exceed $1,649,796 under Contract N62474-76-C-6512 and $538,319 under Contract N62474-76-C-6511.

Letter dated July 25, 1980 from Commander J.D. Kunz, Head, Facilities Management Department, to the Oxnard Director of Public Works:

In any event, the Government’s total liability for all construction costs under Contracts N62474-76-C-6511 and N62474-76-C-6512, including contract contingencies, shall not exceed $538,-319 and $1,649,796, respectively.

The record also shows that on January 29, 1981 the Finance Director of Oxnard wrote to Sukeo Oji, expressing the same position now pressed, that the Navy had agreed to share the higher construction costs:

The second issue relates to costs of construction above those originally budgeted for in the contract. We have been told that at such time as construction is complete, the Navy will approach Congress to request appropriation for the Navy’s proportionate shares of the construction overruns.

In answer to this letter Mr. Oji again referred to the “Connection Charge” clause in the contract, and wrote:

the Government is required to pay a proportionate share of the actual cost but not to exceed the amount committed by the Navy in the contract, [emphasis in original].

*347 There is no written representation as to additional funds. Although Oxnard’s officials testified as to their belief that Oxnard would be proportionately reimbursed for overruns, the Board concluded that the evidence presented by Oxnard was outweighed by the unambiguous written contracts and the consistent written communications from the contracting officials of the Navy. The Board was not persuaded that the conversations to which Oxnard referred could and did vary the express contract terms. The Board held that the Navy had no obligation to pay more than the “not to exceed” prices stated in the contracts.

Oxnard argues that the Navy is es-topped from taking the position that it did not agree to pay a proportionate share of the actual cost of construction. Estoppel may be applied against the government in appropriate circumstances, see American Electronic Laboratories v. United States, 774 F.2d 1110, 1113 (Fed.Cir.1985) (Army estopped from invoking a limitation of funds clause when contractor’s continued performance was in reasonable reliance on the repeated statements of Army representatives that additional funds would be forthcoming); Thanet Corp. v. United States, 591 F.2d 629, 635 (Ct.C1.1979); cf. Law Mathematics and Technology, Inc. v. United States, 779 F.2d 675, 678 (Fed.Cir. 1985) (Navy not estopped from invoking a limitation of funds clause when Navy had not promised funds beyond the amount specified in the contract and the contractor had not relied reasonably on such promise to its detriment).

In pressing the theory of estoppel Oxnard relies particularly on the audit report of the Defense Contract Audit Agency. This report was made shortly after the contracts were entered into, and states that the Navy’s share was “computed as a ratio of the reserved capacity to the total capacity”. This report is in accord with other evidence as to how the not-to-exceed prices were calculated, but it does not add weight to Oxnard’s position that the government intended not to be bound by the not-to-exceed prices set in the contracts, or that the government led Oxnard to believe that these prices were not binding. (This report corrected a calculation error and resulted in a contract amendment decreasing the not-to-exceed total. No subsequent amendments to this total were made.)-

We affirm the Board’s holding that es-toppel has not been shown.

The Board also considered the question of whether the written contracts stated the intent of the parties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Richardson v. United States
Federal Claims, 2021
Shell Oil Company v. United States
751 F.3d 1282 (Federal Circuit, 2014)
Chevron U.S.A., Inc. v. United States
110 Fed. Cl. 747 (Federal Claims, 2013)
Glenn Defense Marine (Asia) PTE, Ltd. v. United States
97 Fed. Cl. 311 (Federal Claims, 2011)
Urban Development Solutions, LLC v. District of Columbia
992 A.2d 1255 (District of Columbia Court of Appeals, 2010)
Sterling, Winchester & Long, L.L.C. v. United States
83 Fed. Cl. 179 (Federal Claims, 2008)
Vassar v. United States
63 Fed. Cl. 166 (Federal Claims, 2004)
Westinghouse Electric Corp. v. United States
42 Cont. Cas. Fed. 77,332 (Federal Claims, 1998)
City of Tacoma v. United States
38 Fed. Cl. 582 (Federal Claims, 1997)
Applied Companies v. United States
41 Cont. Cas. Fed. 77,122 (Federal Claims, 1997)
KMS Fusion, Inc. v. United States
41 Cont. Cas. Fed. 77,000 (Federal Claims, 1996)
Huna Totem Corp. v. United States
40 Cont. Cas. Fed. 76,937 (Federal Claims, 1996)
Conoco Inc. v. United States
35 Fed. Cl. 309 (Federal Claims, 1996)
Atlas Corp. v. United States
35 Cont. Cas. Fed. 75,578 (Court of Claims, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
851 F.2d 344, 34 Cont. Cas. Fed. 75,513, 1988 U.S. App. LEXIS 9109, 1988 WL 69050, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-oxnard-v-the-united-states-cafc-1988.