City of Oglesby v. Federal Energy Regulatory Commission

610 F.2d 897, 197 U.S. App. D.C. 378, 1979 WL 405509
CourtCourt of Appeals for the D.C. Circuit
DecidedAugust 21, 1979
DocketNo. 76-1585
StatusPublished
Cited by6 cases

This text of 610 F.2d 897 (City of Oglesby v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Oglesby v. Federal Energy Regulatory Commission, 610 F.2d 897, 197 U.S. App. D.C. 378, 1979 WL 405509 (D.C. Cir. 1979).

Opinion

Opinion for the Court filed by SPOTTSWOOD W. ROBINSON, III, Circuit Judge.

SPOTTSWOOD W. ROBINSON, III, Circuit Judge:

Illinois Power Company, the intervenor, supplies electric energy to petitioners, the City of Oglesby, the Village of Ladd, and Cedar Point Light and Water Company, pursuant to separate contracts. The present controversy arose when Illinois Power lodged with the Federal Power Commission 1 a new rate schedule purporting to increase the charges for service. Petitioners, resisting its filing, contended that Illinois Power lacked any contractual prerogative to change rates unilaterally, and that the rates designated by the parties’ agreements were unalterable unless and until modified by order of the Commission itself.

The Commission construed Illinois Power’s compacts with Oglesby and Ladd as contemplating rate readjustments in the manner prescribed by Illinois law, and on that basis as unconditionally authorizing rate elevations by Illinois Power. By a more direct route, the Commission interpreted the agreement with Cedar Point as likewise tolerating rate revisions on Illinois Power’s initiative. Resultantly, the Commission refused to deny Illinois Power the benefit of the proposed rate hike pending investigation and affirmative endorsement by the Commission.2

We are unable to agree that the Oglesby and Ladd contracts incorporate Illinois law.3 We hold that the terms of those agreements bar effectuation of rate increases until they are finally approved by the Commission.4 We concur, however, in the Commission’s view that Illinois Power and Cedar Point fashioned a going-rate contract interposing no obstacle to supplier-inaugurated rate changes.5 Accordingly, we reverse the Commission’s order insofar as it pertains to Oglesby and Ladd, and affirm it in its application to Cedar Point.

I. THE ADMINISTRATIVE BACKGROUND

The City of Oglesby and the Village of Ladd maintain and operate their own electric-power distribution systems. Cedar Point Light and Water Company, a privately-owned utility, furnishes energy to about 150 retail customers. All three purchase their requirements exclusively from Illinois Power, a public electric utility subject to the Federal Power Act.6

On June 27, 1975, Illinois Power tendered for filing with the Commission a new schedule raising its service rates. In response, petitioners, on July 28, submitted a “motion to reject, protest and petition to intervene” alleging, inter alia, that their contracts7 with Illinois Power are of the fixed-rate variety governed by the Mobile-Sierra doc[381]*381trine,8 and hence are not subject to modification at Illinois Power’s behest but only by order of the Commission predicated upon a determination of public necessity therefor.

On October 29, 1975, the Commission accepted Illinois Power’s filing, suspended the new rates until January 1, 1976, authorized petitioners’ intervention and directed a hearing.9 On March 8,1976, after that rate had automatically gone into effect,10 the Commission denied petitioners’ motion to reject the controverted increases.11 It held that a reference to the Illinois Commerce Commission in the Oglesby and Ladd agreements 12 necessitated resort to Illinois law to glean the parties’ intentions.13 Pursuing that course, the Commission surmised that if the Illinois agency elects to suspend rates pending a hearing, under state law the suspension can endure until a final decision is reached.14 Thus, on the premise that Illinois Power had contracted with Oglesby and Ladd with calculated reference to these procedures, the Commission concluded that operation of the new rates before completion of its investigation would be inconsistent with the parties’ understanding.15 Illinois Power was thus ordered to refund all revenues collected from Oglesby and Ladd after January 1, 1976, in excess of the contract rates.16 Contrastingly, the Commission read the Cedar Point agreement as a going-rate contract17 entitling Illinois Power to change the rates unilaterally. Accordingly, a final decisional order by the Commission was not deemed a prerequisite to implementation of the increase affecting Cedar Point.18

Both Illinois Power and petitioners sought rehearing of the March 8 order. Illinois Power argued that, contrary to the Commission’s belief, Illinois law provides for the immediate operation of a rate increase if no agency decision has been reached at the expiration of the limited statutory suspension period. By this construction, Illinois Power’s attempt to secure the rate hike would have been sanctioned by Illinois regulatory procedures resembling those delineated in Section 205 of the Federal Power Act.19 In their petition, the customer group took issue with any utiliza[382]*382tion of a more lenient burden of proof than that announced in Sierra20 in determining whether the circumstances warranted a rate increase. Petitioners further objected to the Commission’s treatment of the Cedar Point agreement as a going-rate contract.

On May 7,1976, the Commission issued an order rejecting petitioners’ bid for rehearing but granting Illinois Power’s application therefor.21 Reversing its March 8 order, the Commission agreed with Illinois Power that the state regulatory agency could put a [383]*383rate increase into effect prior to final decision on the merits, and that upon lapse of the statutory suspension period without-rendition of such a decision that body would have no choice but to permit the increase to become operative.22 In consequence, the Commission ruled that it had properly permitted Illinois Power’s new rate to commence prior to final decisional order.23

Petitioners, on May 25, 1976, moved for reconsideration and rehearing of the May 7 order, insisting that the contracting parties never intended that Illinois law should dictate whether rates can be increased unconditionally by Illinois Power or, instead, only by a regulatory agency after resolution on the merits. They maintained that the language of their service agreements made clear that the parties contemplated no rate change unless and until finally ordered by the Commission; and that, even if Illinois law applied, in actual practice the Illinois agency had always promulgated a final rate order within the statutory suspension period. On June 25, 1976, the Commission rebuffed petitioners’ contentions, denied their request for rehearing and reaffirmed its ruling of May 7;24 Petitioners then resorted to this court.25

II. THE FOUNDATION PRINCIPLES

The ability of contracting parties to determine for themselves whether and under what conditions rates may be altered — subject, of course, to the overriding regulatory power of the Commission to adjust rates in the public interest26 — has been delineated in three decisions of the Supreme Court. In Mobile,27

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
610 F.2d 897, 197 U.S. App. D.C. 378, 1979 WL 405509, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-oglesby-v-federal-energy-regulatory-commission-cadc-1979.