City of Cleveland v. The Cleveland Electric Illuminating Company

570 F.2d 123, 24 Fed. R. Serv. 2d 1225, 1978 U.S. App. LEXIS 12581
CourtCourt of Appeals for the Sixth Circuit
DecidedFebruary 16, 1978
Docket77-3017 and 77-3310
StatusPublished
Cited by28 cases

This text of 570 F.2d 123 (City of Cleveland v. The Cleveland Electric Illuminating Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Cleveland v. The Cleveland Electric Illuminating Company, 570 F.2d 123, 24 Fed. R. Serv. 2d 1225, 1978 U.S. App. LEXIS 12581 (6th Cir. 1978).

Opinion

WEICK, Circuit Judge.

The City of Cleveland (City) has appealed from a summary judgment entered against it by the District Court on Counts 2 and 3 of the Second Counterclaim filed against the City by The Cleveland Electric Illuminating Company (CEI), which judgment was made final under Fed.R.Civ.P. 54(b).

I

The City had filed an antitrust action in the Federal District Court against defendants, CEI, Duquesne Light Company, Ohio Edison Company, Pennsylvania Power Company and Toledo Edison Company. 1 In its complaint the City alleged acts of conspiracy to monopolize and to restrain trade in the electric power generating market, in violation of the Sherman Act, 15 U.S.C. §§ 1 & 2, and prayed for damages and injunctive relief.

CEI filed an answer and two counterclaims, only the second of which is at issue here. Count 2 of the Second Counterclaim alleged that the City had failed to pay CEI the purchase price of electric power supplied by CEI to the City’s municipal electric light plant, and the cost of construction and installation for the City of a permanent 138 KV interconnection over which the current was supplied, pursuant to certain Federal Power Commission (FPC) orders and a contract entered into between the parties.

Two additional counterclaims, styled Counts 3 and 4 of the Second Counterclaim, were subsequently filed, each alleging nonpayment of charges for electric power supplied to the City during later periods. The City filed answers to Counts 2 and 4, but filed no answer to Count 3.

On motion of defendant CEI, summary judgment was entered in favor of CEI against the City on Counts 2 and 3 in a memorandum and order of the District Court dated August 4, 1976, and judgment was entered on September 21. The Court granted summary judgment on Count 4 on February 24, 1977 and judgment was entered on April 7, following a joint stipulation of the parties with respect to the amount owed.

From these judgments plaintiff City now appeals. The appeal in case No. 77-3017 is from the judgments on Counts 2 and 3 of CEI’s Second Counterclaim; the appeal in case No. 77-3310 is from the judgment entered on Count 4. Because the issues concerned in the two appeals are identical they will be considered together.

II

The sole issue in the City’s appeals is the claim that CEI’s counterclaims were not compulsory counterclaims within the meaning of Fed.R.Civ.P. 13(a), and that therefore the District Court lacked subject-matter jurisdiction over them. The City did not question that it owed CEI the amounts for which judgments were entered.

We disagree with the City’s contentions, and accordingly we affirm the judgments of the District Court. We hold first, that CEI’s counterclaims were compulsory counterclaims and were within the ancillary jurisdiction of the District Court; and second, in any event and independently, we hold *125 that the District Court had its jurisdiction conferred by the Federal Power Act, 16 U.S.C. § 825p to entertain an action based on an order of the Federal Power Commission requiring the City to pay these charges.

On May 13, 1971 the City filed a complaint against CEI before the FPC, alleging anticompetitive acts by CEI and praying, inter alia, that CEI be required to construct at the expense of the City, an emergency permanent electrical interconnection between CEI’s Electric Light Plant and the City’s Municipal Electric Light Plant (MELP). The subsequent decision and order of the Administrative Law Judge (ALJ) found the City’s charges of antitrust violations against CEI were unsupported by the evidence. He found:

[T]he City’s past inability to furnish reliable, dependable service on the MÉLP System ha[d] been due primarily to incompetent management and inefficient operation.

The ALJ did find, however, that the public interest required the construction, at the sole expense of the City, of an emergency 138 kilovolt permanent synchronous interconnection between the City’s Lake Road Plant and CEI’s Lake Shore Plant. Further, it was ordered that existing emergency service provided the City by CEI over an existing 69 KV temporary nonsynchronous open-switch interconnection should be continued until the new facilities were operational.

These orders were affirmed by the FPC in its Opinion No. 644, issued January 11, 1973, with the provision that the orders would not take effect unless both parties accepted the conditions imposed by the FPC and entered an agreement to that effect between themselves to govern the new service. Opinion No. 644 fixed the rates to be charged for the power to be sold via both the 138 KV and the 69 KV interconnections.

Further, noting that the “City ha[d] for some time refused to pay, or ha[d] been quite late in paying, certain bills rendered by CEI,” for electric current supplied to the City, which current the City sold to its customers, the FPC ordered that an additional five percent could be added to invoices unpaid after forty-five days. It was also ordered that if an invoice went unpaid for sixty days an additional charge of one percent of the amount of the original bill could be added for each unpaid month thereafter.. This additional charge of one percent per month was intended, not as a penalty, but rather to compensate CEI for the cost of maintaining its working capital during a prolonged period of nonpayment.

In its Opinion No. 644-A, issued March 9, 1973, the FPC denied the City’s application for rehearing and stay of its previous orders. The orders of FPC were appealed by the City to the United States Court of Appeals for the District of Columbia Circuit, and were in all respects affirmed except as to the rate structure which was remanded for further consideration. City of Cleveland v. FPC, 174 U.S.App.D.C. 1, 525 F.2d 845 (1976), clarified and compliance ordered, 561 F.2d 344 (D.C.Cir.1977).

CEI filed motions with the FPC on July 13, 1973 and on January 30, 1974, alleging the continued and repeated neglect and failure of the City to pay for power provided via the existing 69 KV interconnection, and seeking enforcement of the payment provisions of the previous FPC orders. On April 8, 1974 the FPC issued an order directing compliance with its previous orders, and ordered the City to make payment to CEI of all undisputed charges for past and future services, including any accrued interest, and also ordered the City to deposit in escrow any disputed amounts. The City has neglected to comply with this order.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bruce v. Sana Health, Inc
E.D. Michigan, 2020
Dotson v. Ally Financial, Inc.
W.D. Tennessee, 2019
Columbia Gas Transmission, LLC v. Kanwal Singh
707 F.3d 583 (Sixth Circuit, 2013)
Walker v. THI of New Mexico at Hobbs Center
803 F. Supp. 2d 1287 (D. New Mexico, 2011)
Frisby v. Keith D. Weiner & Associates Co., LPA
669 F. Supp. 2d 863 (N.D. Ohio, 2009)
Engle v. West Penn Power Co.
530 A.2d 913 (Supreme Court of Pennsylvania, 1987)
Borgquist v. Carr
815 F.2d 701 (Sixth Circuit, 1987)
Angelo Lee Cross v. Jefferson County Fiscal Court
805 F.2d 1034 (Sixth Circuit, 1986)
United States v. James M. Labay
803 F.2d 722 (Sixth Circuit, 1986)
Mapson v. Seiter
802 F.2d 458 (Sixth Circuit, 1986)
Agliam v. Ohio Savings Ass'n
99 F.R.D. 145 (N.D. Ohio, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
570 F.2d 123, 24 Fed. R. Serv. 2d 1225, 1978 U.S. App. LEXIS 12581, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-cleveland-v-the-cleveland-electric-illuminating-company-ca6-1978.