City of Cleveland, Ohio v. Federal Power Commission, Cleveland Electric Illuminating Co., Intervenor

561 F.2d 344, 182 U.S. App. D.C. 346, 1977 U.S. App. LEXIS 12611
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 1, 1977
Docket73-1282
StatusPublished
Cited by126 cases

This text of 561 F.2d 344 (City of Cleveland, Ohio v. Federal Power Commission, Cleveland Electric Illuminating Co., Intervenor) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Cleveland, Ohio v. Federal Power Commission, Cleveland Electric Illuminating Co., Intervenor, 561 F.2d 344, 182 U.S. App. D.C. 346, 1977 U.S. App. LEXIS 12611 (D.C. Cir. 1977).

Opinion

SPOTTSWOOD W. ROBINSON, III, Circuit Judge:

This litigation confronts us a second time. On its first appearance in this court, we held that the Federal Power Commission erred in adopting a schedule of rates filed by Cleveland Electric Illuminating Company (CEI), a public electric utility, without resolving the persisting claim of its municipal customer, the City of Cleveland, Ohio, that the rates exceeded those to which the parties had previously agreed for service to be supplied to the City. 1 Our mandate directed further proceedings by the Commission, 2 and a controversy now rages over the scope of the investigation that the Commission is thus obliged to make. When we recall the pertinent events 3 and consult well settled legal principles, 4 we are led to another adjudication in favor of the City.

I

Over a period of time, representatives of the City and CEI worked out the details of a load transfer service, including rates therefor. 5 Responsively to the City’s charter, its City Council enacted an ordinance authorizing execution of a contract with CEI at rates specified therein. 6 A letter agreement was signed, and with modifications was submitted to and accepted by the Commission for filing as a rate schedule. 7 A dispute subsequently arising, however, bared a “ratchet clause” 8 appearing in the letter agreement — and by its filing eventuating into the rate schedule — which was not mentioned in the ordinance or, according to the City, discussed during the antecedent negotiations. 9

In litigation before the Commission and later before this court, the City contended that the filed rates did not coincide with the rates contracted for, and thus that the rate schedule was subject to appropriate revi *346 sion. 10 The Commission disagreed 11 but, for reasons articulated in our opinion, we found the City’s argument persuasive enough to require investigation and adjudication of its claim. 12 We accordingly reversed the Commission on this score 13 and remanded the case for further proceedings consistent with the opinion. 14

On remand, the parties deadlocked on the breadth of the inquiry which the Commission was summoned by our mandate to make. After a settlement conference failed to achieve visible progress, the Commission’s staff moved for an order establishing a schedule for briefs addressing the matters to be considered. 15 By CEI’s interpretation of the mandate, the sole question was the role of the ratchet clause, 16 while the City insisted that the issue properly extended beyond to other energy charges for which it was billed, and which allegedly were also inconsistent with the parties pre-filing bargain. 17 The Commission concurred in the position advanced by CEI, 18 and we are asked to direct compliance with the mandate as the City reads it.

II

The decision of a federal appellate court establishes the law binding further action in the litigation by another body subject to its authority. 19 The latter “is without power to do anything which is contrary to either the letter or spirit of the mandate construed in the light of the opinion of [the] court deciding the case,” 20 and the higher tribunal is amply armed to rectify any deviation through the process of mandamus. 21 “That approach,” we have said, “may appropriately be utilized to correct a misconception of the scope and effect of the appellate decision.” 22 These principles, so familiar in operation within the hierarchy of judicial benches, 23 indulge no exception for reviews of administrative agencies. 24 Our mission thus becomes defi *347 nition of the exploratory obligation which our mandate laid upon the Commission, and for guidance we refer to our previous opinion. 25

When this case was here before, we faced “centrally the question whether the Federal Power Commission erred in adopting a rate structure specified in a schedule filed by a public electric utility without resolving its municipal customer’s contention that the schedule contravenes a preexisting agreement between the parties.” 26 The City’s major “contention[ ] [was] that the Commission erred ... in adhering to the rates filed by CEI despite the claim[] that they did not accurately reflect those previously agreed to”; 27 the City’s “primary argument [was] that CEI’s filings with the Commission, which eventuated as the schedule governing the rates payable until the Commission fixed rates of its own, departed from the preexisting agreement of the parties.” 28 To be sure, the only specific instance of inconsistency identified by the City’s briefs was the ratchet clause, 29 which accounts for the emphasis that we gave it in our opinion, 30 but the basic issue presented and decided loomed much larger. At stake was the pervasive view, espoused by the City, “that where the parties have agreed to rates, only the rates agreed upon can be filed, and that in such instances it is error, which the Commission can later correct, to accept for filing a rate schedule which does not accurately reflect the parties’ agreement.” 31

So, the ratchet clause becomes something of a focal point because assertedly it was a manifestation of divergence of the rates agreed to and the rates filed. 32 And indubitably, our decision encompassed, not the ratchet clause alone, but the vice of any such divergence. 33 The key elements of our holding were that “the proposition that a filed rate variant from an agreed rate is nonetheless the legal rate wages war with basic premises of the Federal Power

Free access — add to your briefcase to read the full text and ask questions with AI

Related

B.D. v. District of Columbia
District of Columbia, 2023
Lee Memorial Hospital v. Xavier Becerra
10 F.4th 859 (D.C. Circuit, 2021)
De Csepel v. Republic of Hungary
District of Columbia, 2020
Bayala v. United States Department of Homeland Security
246 F. Supp. 3d 16 (District of Columbia, 2017)
Board of Public Works v. K. Hovnanian's Four Seasons at Kent Island, LLC
115 A.3d 634 (Court of Appeals of Maryland, 2015)
Zinna v. Congrove Ex Rel. Estate of Congrove
755 F.3d 1177 (Tenth Circuit, 2014)
Larsen v. United States Navy
887 F. Supp. 2d 247 (District of Columbia, 2012)
Tigers Eye Trading, LLC v. Comm'r
138 T.C. No. 6 (U.S. Tax Court, 2012)
United States v. White
751 F. Supp. 2d 173 (District of Columbia, 2010)
United States v. Deft. 1
District of Columbia, 2010
Triton Marine Fuels, Ltd. v. M/V Pacific Chukotka
671 F. Supp. 2d 753 (D. Maryland, 2009)
Rubin v. the Islamic Republic of Iran
563 F. Supp. 2d 38 (District of Columbia, 2008)
United States v. Ronald Thrasher
483 F.3d 977 (Ninth Circuit, 2007)
Westside Mothers v. Olszewski
368 F. Supp. 2d 740 (E.D. Michigan, 2005)
State Ex Rel. Frazier & Oxley, L.C. v. Cummings
591 S.E.2d 728 (West Virginia Supreme Court, 2004)
In Re Midamerican Energy Company
286 F.3d 483 (Eighth Circuit, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
561 F.2d 344, 182 U.S. App. D.C. 346, 1977 U.S. App. LEXIS 12611, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-cleveland-ohio-v-federal-power-commission-cleveland-electric-cadc-1977.