In Re Midamerican Energy Company

286 F.3d 483, 2002 WL 496449
CourtCourt of Appeals for the Eighth Circuit
DecidedMay 22, 2002
Docket01-3886
StatusPublished
Cited by31 cases

This text of 286 F.3d 483 (In Re Midamerican Energy Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Midamerican Energy Company, 286 F.3d 483, 2002 WL 496449 (8th Cir. 2002).

Opinion

PER CURIAM.

Petitioner MidAmerican Energy Company (“MEC”) files this writ of mandamus seeking enforcement of our prior opinion, Nebraska Public Power District v. MidAmerican Energy Co., 234 F.3d 1032 (8th Cir.2000) (hereinafter NPPD 7).

I. BACKGROUND

A more complete recitation of the facts is found at NPPD I. However, a brief summary will provide context for the instant dispute.

In 1967, the parties’ predecessors entered a “Power Sales Contract” (“PSC”), obligating Nebraska Public Power District (“NPPD”) to construct and manage a nuclear power facility known as the Cooper Nuclear Station (“Cooper”), and obligating MEC to purchase power therefrom until *485 2004. The PSC remains in effect until that year and requires NPPD to submit to MEC a monthly statement reflecting the prior month’s Monthly Power Costs. In 1984, NPPD added a line item for decommissioning costs to this statement. While the parties neither reached a separate agreement nor amended the PSC to address these decommissioning costs, MEC paid these amounts without objection. As of the commencement of this litigation, MEC had paid approximately $78,000,000 toward these estimated charges.

This case originated in federal court when NPPD sought a declaratory judgment that the contract between NPPD and MEC required MEC to make current, non-refundable payments toward estimated decommissioning costs of Cooper, arguing that such payments fell within the contract definition of Monthly Power Costs. Essentially, NPPD wanted a declaration that the decommissioning costs paid to-date by MEC were not voluntary, but rather required under the PSC as payments for power and energy, and therefore non-refundable even if NPPD continued operation of Cooper after 2004. MEC counterclaimed to establish its right to recover the amounts it had already paid toward decommissioning if NPPD continued to operate the power plant after 2004. The district court found the PSC unambiguously supported NPPD’s position, holding that MEC had an unconditional obligation to pay, in the past and until the expiration of the PSC on September 21, 2004, nonrefundable decommissioning costs.

MEC appealed the district court ruling, arguing that the district court erred because the PSC does not require payments of estimated decommissioning costs and unambiguously exempts MEC from all decommissioning liability if NPPD continues operations after 2004. We agreed, and determined that “the PSC does not require MEC to make current, non-refundable payments of estimated decommissioning costs to NPPD, but makes MEC liable for Cooper’s decommissioning only in the event that NPPD shuts Cooper doiTvi in 2004.” 234 F.3d at 1046. Moreov». ve held that even though “the PSC does „ bar MEC’s claims for restitution oi amounts already paid,” we specifically left unresolved “the question whether MEC may recover payments already made in the event NPPD does continue operating Cooper after 2004.” Id. at 1045 n. 7,1046. As for MEC’s counterclaims under restitution and estoppel theories seeking recovery of those funds, we clarified that those claims were not before us and directed the parties to return to the district court to litigate them. Id. at 1045 n. 7. Thus, we reversed the district court’s ruling and remanded the case for trial on the narrow issue of whether MEC might succeed on its counterclaims for recovery of the funds it had already paid into the decommissioning sinking fund, and all other outstanding claims. 1

*486 On remand, NPPD sought leave to file a second amended complaint in order to raise new claims which, according to MEC, were recast versions of NPPD’s previous allegations. The magistrate judge granted NPPD’s motion, and on appeal the district judge affirmed the magistrate’s decision. MEC now files an emergency petition for writ of mandamus to compel compliance with our original mandate, NPPD I. MEC claims that our prior opinion forecloses the causes of action now raised by NPPD, and that if the parties proceed to trial, they will be relitigating the same claims as to MEC’s liability for decommissioning costs that we previously decided.

II. DISCUSSION

The All Writs Act, 28 U.S.C. § 1651(a) gives federal courts the power to issue writs of mandamus. The issuance of a writ of mandamus is an extraordinary remedy reserved for extraordinary situations. See, e.g., Gulfstream Aerospace Corp. v. Mayacamas Corp., 485 U.S. 271, 289, 108 S.Ct. 1133, 99 L.Ed.2d 296 (1988). The Supreme Court has held that only “exceptional circumstances amounting to a judicial ‘usurpation of power’ ” will justify issuance of the writ. Will v. United States, 389 U.S. 90, 95, 88 S.Ct. 269, 19 L.Ed.2d 305 (1967) (quoting De Beers Consol. Mines, Ltd. v. United States, 325 U.S. 212, 217, 65 S.Ct. 1130, 89 L.Ed. 1566 (1945)). Accordingly, courts seldom issue writs interfering with a lower court trial order. However, “it is important to remember that issuance of the writ is in large part a matter of discretion with the court to which the petition is addressed.” Kerr v. United States Dist. Court, 426 U.S. 394, 403, 96 S.Ct. 2119, 48 L.Ed.2d 725 (1976).

A federal court’s power to utilize mandamus to enforce its prior mandate is firmly established. Iowa Utils. Bd. v. FCC, 135 F.3d 535, 541 (8th Cir.1998), vacated on other grounds by 525 U.S. 1133, 119 S.Ct. 1022, 143 L.Ed.2d 34 (1999); Brictson Mfg. Co. v. Munger, 20 F.2d 793, 794 (8th Cir.1927). Mandamus will lie “to confine a lower court to the terms of an appellate tribunal’s mandate.” Will, 389 U.S. at 95-6, 88 S.Ct. 269. Ultimately, “[w]e have not only the power, but also a duty to enforce our prior mandate to prevent evasion.” Iowa Utils. Bd., 135 F.3d at 541.

In its second amended complaint, NPPD raises the following causes of action:

(1) Modification or Separate Contract (asserting that NPPD and MEC either modified the PSC or created a separate agreement to provide that MEC had an unconditional obligation to pay fifty percent of the estimated decommissioning costs);

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jacob v. Witty
D. Nebraska, 2022
Hopkins v. Jegley
E.D. Arkansas, 2020
Hunter v. Rhay
D. South Dakota, 2020
Warfield v. Mnuchin
D. South Dakota, 2020
Tripp v. South Dakota
D. South Dakota, 2020
Hunter v. Saul
D. South Dakota, 2020
Greg Hageman v. Dennis Barton, III
817 F.3d 611 (Eighth Circuit, 2016)
Inre: Nokia Inc.
760 F.3d 1348 (Federal Circuit, 2014)
Vicky v. United States
709 F.3d 712 (Eighth Circuit, 2013)
United States v. Yamil Rivera-Kader
399 F. App'x 146 (Eighth Circuit, 2010)
United States v. Jeffrey Crawford
376 F. App'x 651 (Eighth Circuit, 2010)
Saini v. Heinauer
552 F. Supp. 2d 974 (D. Nebraska, 2008)
Keith Barthel v. Daniel Glickman
264 F. App'x 541 (Eighth Circuit, 2008)
Alzuraiki v. Heinauer
544 F. Supp. 2d 862 (D. Nebraska, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
286 F.3d 483, 2002 WL 496449, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-midamerican-energy-company-ca8-2002.